Last visit was: 15 Jul 2025, 19:12 It is currently 15 Jul 2025, 19:12
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
SVaidyaraman
Joined: 17 Dec 2012
Last visit: 11 Jul 2025
Posts: 577
Own Kudos:
1,744
 [55]
Given Kudos: 20
Location: India
Expert
Expert reply
Posts: 577
Kudos: 1,744
 [55]
10
Kudos
Add Kudos
45
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
fameatop
Joined: 24 Aug 2009
Last visit: 09 Jun 2017
Posts: 383
Own Kudos:
2,441
 [20]
Given Kudos: 275
Concentration: Finance
Schools:Harvard, Columbia, Stern, Booth, LSB,
Posts: 383
Kudos: 2,441
 [20]
15
Kudos
Add Kudos
5
Bookmarks
Bookmark this Post
General Discussion
User avatar
vinnik
Joined: 14 Dec 2011
Last visit: 02 May 2020
Posts: 54
Own Kudos:
176
 [2]
Given Kudos: 86
Products:
Posts: 54
Kudos: 176
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Zarrolou
Joined: 02 Sep 2012
Last visit: 11 Dec 2013
Posts: 848
Own Kudos:
5,073
 [4]
Given Kudos: 219
Status:Far, far away!
Location: Italy
Concentration: Finance, Entrepreneurship
GPA: 3.8
Posts: 848
Kudos: 5,073
 [4]
4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
vinnik
Hello friends,

Is there any other way to do this question ?

Thanks & Regards
Vinni

A pure algebraic way can be this:

\(rate*time=work\)

\((A+B)*1=\frac{1}{9}\) and \(A*t=\)1 and \(B*k=1\) where t and k are the days A, B would take to finish the job and are integers.

From those we get: \(\frac{1}{t}+\frac{1}{k}=\frac{1}{9}\) or \(t+k=\frac{tk}{9}\). Lets study t (the time taken by A alone) \(t(1-\frac{k}{9})=-k\) or \(t=\frac{-9k}{9-k}\). How can we read this? Since k is a number the represents a number of days, must be positive=> -9k will be negative so because t must be positive, the denominator must be negative.
\(+ve=\frac{-ve}{-ve}\).
\(9-k<0\) so \(k>9\), but since k is an integer => THE LEAST number of days B can take to finish the job is 10.

So if this is THE LEAST for B, it must be the MOST for A => \(t=\frac{-9*10}{9-10}=90\).

You can repeat the whole analysis just by switching k and t and you find \(90-10=80\).

Hope I've explained myself well (and hope you enjoy algebra :) )
User avatar
vinnik
Joined: 14 Dec 2011
Last visit: 02 May 2020
Posts: 54
Own Kudos:
Given Kudos: 86
Products:
Posts: 54
Kudos: 176
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Thanks Zarrolou :-D

Regards
Vinni
avatar
Asifpirlo
Joined: 10 Jul 2013
Last visit: 26 Jan 2014
Posts: 222
Own Kudos:
1,129
 [1]
Given Kudos: 102
Posts: 222
Kudos: 1,129
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
vinnik
Thanks Zarrolou :-D

Regards
Vinni

solution:

1/A + 1/B = 1/9
when B max then A min. when B min A max. For minimum positive value(real), put B = 10 and consequently A=90. and vice versa. so difference= 90 - 10 = 80 (Answer)
avatar
sanket1991
Joined: 14 Sep 2014
Last visit: 22 Aug 2015
Posts: 74
Own Kudos:
103
 [3]
Given Kudos: 51
WE:Engineering (Consulting)
Posts: 74
Kudos: 103
 [3]
1
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
1/A + 1/B = 1/9

so A = 9B/(B-9)

A will be max when denominator is minimum (1) so B = 10 and A = 90
For A to be minimum these values will just be reverse so A = 10
Difference 80
User avatar
GyMrAT
Joined: 14 Dec 2017
Last visit: 03 Nov 2020
Posts: 413
Own Kudos:
495
 [4]
Given Kudos: 173
Location: India
Posts: 413
Kudos: 495
 [4]
4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
SravnaTestPrep
A and B together can complete one-ninth of a job in a day. What is the difference between the maximum and minimum number of days A could take to complete the job alone, if A and B take whole number of days to complete the job alone?

A 45
B.60
C.80
D.90
E.Cannot be determined

Given, A & B together can complete 1/9th of the job in one day.

Let the job consist of 90 units. Therefore in one day A & B together can produce 10 units.

A & B together work at a rate of 10 units/day

So the combinations for the no. of units per day produced by A & B can be (1,9), (2,8), (3,7), (4,6), (5,5), (6,4), (7,3), (8,2), (9,1)

So Maximum units produced per day by A = 9 units/ day at its highest efficiency.

Hence to complete 90 units, A will take (90/9) = 10 days, this is the fastest for A at its highest efficiency.

So Minimum Days to finish the job = 10 days

Now, Similarly, minimum units produced per day by A = 1 unit/ day at its lowest efficiency.

Hence to complete 90 units, A will take (90/1) = 90 days, this is the slowest for a its lowest efficiency.

So Maximum Days to finish the job = 90 days

Required is Difference of Max Days & Min Days = 90 - 10 = 80

Answer C
User avatar
JeffTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 04 Mar 2011
Last visit: 05 Jan 2024
Posts: 2,996
Own Kudos:
7,937
 [1]
Given Kudos: 1,646
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Expert
Expert reply
Posts: 2,996
Kudos: 7,937
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
SravnaTestPrep
A and B together can complete one-ninth of a job in a day. What is the difference between the maximum and minimum number of days A could take to complete the job alone, if A and B take whole number of days to complete the job alone?

A 45
B.60
C.80
D.90
E.Cannot be determined

We a = the number of days A needs to take to complete the job alone and b = the number of days B needs to take to complete the job alone. So A and B’s rates are 1/a and 1/b, respectively and we have:

1/a + 1/b = 1/9

1/a = 1/9 - 1/b

1/a = (b - 9)/(9b)

a = 9b/(b - 9)

Since a and b are positive integers, we see that the smallest positive integer for b is 10. In that case, a = 9(10)/(10 - 9) = 90 and this must be the maximum value of a since b is minimum.

Notice that in the above we’ve solved a in terms of b. If we solve b in terms of a, we should have:
b = 9a/(a - 9)

In this case we see that the minimum value of a is 10. Therefore, the difference between the maximum and minimum number of days A takes to complete the job alone is 90 - 10 = 80.

Answer: C
User avatar
bobnil
Joined: 28 May 2017
Last visit: 22 Sep 2023
Posts: 41
Own Kudos:
38
 [1]
Given Kudos: 82
Location: India
Posts: 41
Kudos: 38
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I did in a different way.
R(A+B) = 1/(9 )=10/90=(1+9)/90=1/90+9/90=1/90+1/10
so, their rates can be divided as 1/90 & 1/10
i.e. Time TA & TB can be divided as 90 & 10
Thus, Time(Max – MIN) = 90-10 = 80 days.
Bunuel, is this approach OK?
User avatar
HRCS
Joined: 13 Mar 2022
Last visit: 13 Nov 2024
Posts: 2
Given Kudos: 13
GMAT Focus 1: 735 Q88 V87 DI84
GMAT Focus 1: 735 Q88 V87 DI84
Posts: 2
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A very good question indeed!

A pure algebraic solution shall be as follows:

Let a be the number of days taken by A to do the job and b be the number of days taken by B to complete the job.

From the information given, we can deduce that

1/a + 1/b = 1/9

Solving further will lead to the following equation:

9a + 9b = ab

Since we are told that the number of days shall always be whole numbers, there is merit in solving the equation further. Even though we have the classic problem of having 2 variables and one equation, there is still enough information to be derived from this.

Let us rewrite the equation as follows

9a + 9b -ab =0
a(9-b) + 9b = 0
a(9-b) + 9b - 81 + 81 = 0
a(9-b) -9(9-b) +81 = 0
=> (a-9)x(b-9) = 81

The problem is now a simple number properties problem where the two terms on the left (in order to be whole) have to be factors of 81.

Case 1: Minimize a by choosing a - 9 as 1 and b - 9 as 81, leading to a value of 10 for a
Case 2: Maximize a by choosing a-9 as 81 and b-9 as 1, leading to a value of 90 for a

We can see that the difference between the maximum and minimum value of a shall come out to be 90 - 10 = 80­
Moderators:
Math Expert
102582 posts
PS Forum Moderator
695 posts