Last visit was: 21 Apr 2026, 14:02 It is currently 21 Apr 2026, 14:02
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 21 Apr 2026
Posts: 109,729
Own Kudos:
Given Kudos: 105,798
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,729
Kudos: 810,460
 [11]
1
Kudos
Add Kudos
10
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
CareerGeek
Joined: 20 Jul 2017
Last visit: 21 Apr 2026
Posts: 1,286
Own Kudos:
4,430
 [12]
Given Kudos: 162
Location: India
Concentration: Entrepreneurship, Marketing
GMAT 1: 690 Q51 V30
WE:Education (Education)
GMAT 1: 690 Q51 V30
Posts: 1,286
Kudos: 4,430
 [12]
9
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
General Discussion
User avatar
Archit3110
User avatar
Major Poster
Joined: 18 Aug 2017
Last visit: 21 Apr 2026
Posts: 8,626
Own Kudos:
5,190
 [2]
Given Kudos: 243
Status:You learn more from failure than from success.
Location: India
Concentration: Sustainability, Marketing
GMAT Focus 1: 545 Q79 V79 DI73
GMAT Focus 2: 645 Q83 V82 DI81
GPA: 4
WE:Marketing (Energy)
Products:
GMAT Focus 2: 645 Q83 V82 DI81
Posts: 8,626
Kudos: 5,190
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
EgmatQuantExpert
User avatar
e-GMAT Representative
Joined: 04 Jan 2015
Last visit: 02 Apr 2024
Posts: 3,657
Own Kudos:
20,859
 [2]
Given Kudos: 165
Expert
Expert reply
Posts: 3,657
Kudos: 20,859
 [2]
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post

Solution



Given:
    • A, B and C can do a work in 5 days, 10 days and 15 days respectively
    • They started together to do the work.
      o After 2 days A and B left and C completed the remaining work.

To find:
    • C did the remaining work in how many days.

Approach and Working:
    • Let the total work = LCM(5, 10, 15) units = 30 Units
      o Hence, work done by A in 1 day = 6 units
         Work done by B in 1 day = 3 units
         Work done by B in 1 day = 2 units

Work done by A, B, and C in 2 days = 2* (6+3+2) = 22 units
    • Remaining work = 8 units
      o Time taken by C to complete 8 units of work =\(\frac{8}{2}\) = 4 days

Hence, the correct answer is option C.

Answer: C
User avatar
EgmatQuantExpert
User avatar
e-GMAT Representative
Joined: 04 Jan 2015
Last visit: 02 Apr 2024
Posts: 3,657
Own Kudos:
Given Kudos: 165
Expert
Expert reply
Posts: 3,657
Kudos: 20,859
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hey,

We have also posted an article on how to solve Time and work questions easily by using the LCM method.

To read the article: Solve Time and Work Problems Efficiently using Efficiency Method!

Regards,
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 21 Apr 2026
Posts: 22,276
Own Kudos:
26,526
 [1]
Given Kudos: 302
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 22,276
Kudos: 26,526
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Bunuel
A, B and C can do a work in 5 days, 10 days and 15 days respectively. They started together to do the work but after 2 days A and B left. C did the remaining work in how many days.

(A) 6
(B) 5
(C) 4
(D) 3
(E) 2


The combined rate of A, B, and C is:

1/5 + 1/10 + 1/15 = 6/30 + 3/30 + 2/30 = 11/30.

In two days 11/30 x 2 = 22/30 work is done, so 8/30 = 8/30 = 4/15 is left to be completed.

Thus, it takes C (4/15)/(1/15) = 60/15 = 4 days to complete the rest of the work.

Answer: C
User avatar
CrackverbalGMAT
User avatar
Major Poster
Joined: 03 Oct 2013
Last visit: 21 Apr 2026
Posts: 4,846
Own Kudos:
Given Kudos: 226
Affiliations: CrackVerbal
Location: India
Expert
Expert reply
Posts: 4,846
Kudos: 9,180
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Assume that the total work = LCM(5, 10, 15) = 30 units
Work rate of A = 30/5= 6 units/day

Work rate of B = 30/10 = 3 units/day

Work rate of C = 30/15 = 2 units/day

If all of them work together, the work done per day= 6 + 3 + 2 = 11 units
For two days, the work done = 11*2= 22 units
Work left after 2 days = 30 - 22 = 8 units
Time taken by C = Work remaining/Rate of C = 8/2 = 4 days

Option C is the answer.

Thanks,
Clifin J Francis
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,954
Own Kudos:
Posts: 38,954
Kudos: 1,117
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Automated notice from GMAT Club BumpBot:

A member just gave Kudos to this thread, showing it’s still useful. I’ve bumped it to the top so more people can benefit. Feel free to add your own questions or solutions.

This post was generated automatically.
Moderators:
Math Expert
109729 posts
Tuck School Moderator
853 posts