GyanOne
DisciplinedPrep
A contract must be completed in 56 days and 104 men are recruited to work, each working 8 hours a day. After 30 days, \(\frac{2}{5}\) of the work is finished. How many additional men must be employed so that the work is completed on time?
A. 180
B. 64
C. 76
D. 96
E. 120
Work done by 104 men working 8 hours a day in 30 days = 104*8*30 man hours
=> Work remaining at that point = (3/2)*104*8*30 = 45*8*104 man hours
=> If x additional men are deployed, then (104+x)*8*26 = 45*8*104
=> x = 76
Option (C).
Alternative solution 1:Note that the number of hours worked per man per day are not relevant here.
So, according to the question, 104 men working for 30 days complete 2/5 of the work.
In how many days would these 104 men complete all of the work? In 30*(5/2) = 75 days.
So, to complete (3/5) of the work in 56 days, we need (75*104/26)*(3/5) men, or 180 men.
Thus, we need 76 additional men.
Option (C).
Alternative solution 2:Let k be the efficiency (work done per person per day) and W the total work.
Then we have:
104*30*8*k = (2/5)*W
AND
x*26*8*k=(3/5)*W
Dividing the equations, we get
x= 3*104*30/(2*26) = 180, or 76 additional men.
Option (C).