Last visit was: 25 Apr 2024, 08:37 It is currently 25 Apr 2024, 08:37

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Intern
Intern
Joined: 04 Sep 2010
Posts: 9
Own Kudos [?]: 7 [2]
Given Kudos: 6
Send PM
User avatar
Senior Manager
Senior Manager
Joined: 24 Jun 2010
Status:Time to step up the tempo
Posts: 273
Own Kudos [?]: 673 [1]
Given Kudos: 50
Location: Milky way
Concentration: International Business, Marketing
Schools:ISB, Tepper - CMU, Chicago Booth, LSB
Send PM
User avatar
Senior Manager
Senior Manager
Joined: 24 Jun 2010
Status:Time to step up the tempo
Posts: 273
Own Kudos [?]: 673 [0]
Given Kudos: 50
Location: Milky way
Concentration: International Business, Marketing
Schools:ISB, Tepper - CMU, Chicago Booth, LSB
Send PM
Tutor
Joined: 16 Oct 2010
Posts: 14822
Own Kudos [?]: 64913 [1]
Given Kudos: 426
Location: Pune, India
Send PM
Re: Basic Time & Work problems [#permalink]
1
Kudos
Expert Reply
Type I:

To complete 2.5 km in 100 days, we need 45 men
To complete 12.5 km (leftover road) in 100 days, we need 45 x 12.5/2.5 men (It will be 12.5/2.5 and not 2.5/12.5 because more work will need more men. So we have to make 45 greater. Direct variation.) = 225 men

To complete 12.5 km in 100 days we need 225 men.
To complete 12.5 km in 200 days (this is the number of leftover days), we need 225 x 100/200 (Now if we have more days for same work, we need less men so 100/200 to make 225 smaller. Inverse Variation) = 112.5 men i.e. 113 men (112 men cannot finish the work. Even if this was 112.3, I would have made it 113)

We already have 45 men, we need 68 more.

Note: I could have done the above in a single step by saying 45 x 12.5/2.5 x 100/200 = 112.5
I used two steps to clarify.

Type II:
If we are given how much they were paid, we know the ratio of their rate of work. It will be the ratio in which they were paid. This is so because if you are twice as fast as me, you will be paid twice as much as me.
Ratio of rate of work = 54:81 = 2:3
Then, ratio of time taken will be 3:2 (Ratio of rate of work is inverse of ratio of time taken. If this is unclear, just check out work theory)
Then, B can do the work in 8 days.
Together, they will take 8 x 12/ (8 + 12) = 4.8 days

Type III:
Let me say that the amount of food one soldier consumes in one day is 1 soldier-day food.

Total amount of food was 200 x 31 soldier-days = 6200 soldier-days
In 27 days, 200 soldiers consumed the food which is equal to 27 x 200 = 5400 soldier-days.
Left over food = 800 soldier-days
Now 800 soldier-days food will last 80 soldiers 10 days. Since 27 days are already over, it would have lasted only 4 more days but now it is going to last 10 days so it will last an extra 6 days.
User avatar
Senior Manager
Senior Manager
Joined: 24 Jun 2010
Status:Time to step up the tempo
Posts: 273
Own Kudos [?]: 673 [0]
Given Kudos: 50
Location: Milky way
Concentration: International Business, Marketing
Schools:ISB, Tepper - CMU, Chicago Booth, LSB
Send PM
Re: Basic Time & Work problems [#permalink]
Type I - Extra number of men required/employed

1) An engineer undertakes a project to build a road 15 km long in 300 days with 45 men employed. After 100 days, only 2.5 km of the road has been completed. Find the (approx.) number of extra men needed to complete the work in time.

a) 43
b) 45
c) 55
d) 68
e) 60

Answer:

Work and Rate
RateMenDaysWork completed in meters
First 100 daysx451002.5*1000



We can find out the actual rate (x) at which the men are working.
=> x*45*100 = 2500
=> x = 5/9.

Now we will use the actual rate at which the men are working to find out the extra men required to complete the work in the remaining 200 days. [We should only use the actual rate at which the men are working not the rate which they were expected to work.]

Work and Rate
RateMenDaysWork completed in meters
First 100 days5/9451002.5*1000
Next 100 days5/9x20012.5*1000


(5/9)*x*200 = 12500
=> x = 112.5 ~ 113. So the number of extra men required to complete the work in the remaining 200 days is 113 - 45 = 68.

Answer
User avatar
Intern
Intern
Joined: 04 Sep 2010
Posts: 9
Own Kudos [?]: 7 [0]
Given Kudos: 6
Send PM
Re: Basic Time & Work problems [#permalink]
Great! Thank you for the help ezhilkumarank and VeritasPrepKarishma. For Time & Work, i tend to directly solve problems using the one days work approach. And for the above problems that approach did not get me the right answer.
Thank you for the help!
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32675
Own Kudos [?]: 821 [0]
Given Kudos: 0
Send PM
Re: Basic Time & Work problems [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.



Archived Topic
Hi there,
This topic has been closed and archived due to inactivity or violation of community quality standards. No more replies are possible here.
Where to now? Join ongoing discussions on thousands of quality questions in our Problem Solving (PS) Forum
Still interested in this question? Check out the "Best Topics" block above for a better discussion on this exact question, as well as several more related questions.
Thank you for understanding, and happy exploring!
GMAT Club Bot
Re: Basic Time & Work problems [#permalink]
Moderators:
Math Expert
92914 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne