GMAT Question of the Day - Daily to your Mailbox; hard ones only

It is currently 18 Aug 2018, 11:33

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel

Five men started working on a job that was to be finished in hundred d

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

Intern
Intern
User avatar
Status: Learning
Joined: 07 Aug 2011
Posts: 37
Location: India
Schools: WBUT - Class of 2011
GMAT Date: 01-06-2014
GPA: 2.6
WE: Research (Education)
Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 31 Aug 2014, 01:09
3
11
00:00
A
B
C
D
E

Difficulty:

  85% (hard)

Question Stats:

60% (02:52) correct 40% (03:49) wrong based on 174 sessions

HideShow timer Statistics

Five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.

A) X= 16 Y= 20

B) X= 20 Y= 24

C) X= 24 Y= 28

D) X= 28 Y= 32

E) X= 20 Y= 28

_________________

If you like my post give me kudos.

Arindam Sur
Researcher, Academian

Most Helpful Community Reply
Intern
Intern
User avatar
Joined: 04 Jul 2014
Posts: 46
Schools: Smeal" 20
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 24 Oct 2014, 11:28
3
3
arindamsur wrote:
Five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.

A) X= 16 Y= 20

B) X= 20 Y= 24

C) X= 24 Y= 28

D) X= 28 Y= 32

E) X= 20 Y= 28


10% of the work = 10 days of work for the 5 men

(5+x) men work for (y-10) days to complete 90% of work.

5 men do 1/100th of the work in one day
1 man does 1/500th of the work in one day

Therefore (5+X) (Y-10)/500 = 9/10

X = 20 & Y = 28 satisfies this equation.

Hence Answer E.
General Discussion
Manager
Manager
avatar
Joined: 20 Dec 2013
Posts: 89
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 31 Aug 2014, 03:24
arindamsur wrote:
Five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.

A) X= 16 Y= 20

B) X= 20 Y= 24

C) X= 24 Y= 28

D) X= 28 Y= 32

E) X= 20 Y= 28


IMO -
None of these.

My equation -> (5+x)(y-10)= (500)*9/10 ->
one possible solution is - x=10, y=13.
_________________

Best
MKS
Appreciate it with Kudos !! :)

Intern
Intern
User avatar
Status: Learning
Joined: 07 Aug 2011
Posts: 37
Location: India
Schools: WBUT - Class of 2011
GMAT Date: 01-06-2014
GPA: 2.6
WE: Research (Education)
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 31 Aug 2014, 03:44
I saw the solution (5 + x) × (y – 10) = 450 Its is not clear to me (y - 10)

From there they jump to solution x = 20 and y = 28

MKS wrote:
arindamsur wrote:
Five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.

A) X= 16 Y= 20

B) X= 20 Y= 24

C) X= 24 Y= 28

D) X= 28 Y= 32

E) X= 20 Y= 28


IMO -
None of these.

My equation -> (5+x)(y-10)= (500)*9/10 ->
one possible solution is - x=10, y=13.

_________________

If you like my post give me kudos.

Arindam Sur
Researcher, Academian

Manager
Manager
avatar
Joined: 12 Sep 2014
Posts: 160
Concentration: Strategy, Leadership
GMAT 1: 740 Q49 V41
GPA: 3.94
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 08 Oct 2014, 17:14
1
I got E and here's how I got there.

At the beginning, we know it takes 100 days for 5 people working together to complete. This means each will take 500 days to complete working solo. But, 10% of the work is already done, so it will take another 90 days for the 5 people to complete. This means, the remaining work takes 450 days to complete solo.

To get this, I just did 5*(1/person) = 1/100 and 1/90, respectively to get 500 and 450 days, respectively, when solving for "person."

Next, you need to calculate (5+x)/450 = 1/(y-10) to form an analogy with the work/rate problem. This is only possible when x=20 and y=28, which means an additional 18 days is needed after 10% work is done. Hope that makes sense.
Intern
Intern
avatar
Joined: 18 Jul 2013
Posts: 42
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 22 Oct 2014, 10:54
five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.


From question i understand that if 5 men worked together they would have completed 1 task n 100 day mean seach person will take 20 days to complete a task.

Than how come below mention predication(500 )days are possible ???????????????????????????????????????

At the beginning, we know it takes 100 days for 5 people working together to complete. This means each will take 500 days to complete working solo. But, 10% of the work is already done, so it will take another 90 days for the 5 people to complete. This means, the remaining work takes 450 days to complete solo.

To get this, I just did 5*(1/person) = 1/100 and 1/90, respectively to get 500 and 450 days, respectively, when solving for "person."

Next, you need to calculate (5+x)/450 = 1/(y-10) to form an analogy with the work/rate problem. This is only possible when x=20 and y=28, which means an additional 18 days is needed after 10% work is done. Hope that makes.

Expert advice please....
Intern
Intern
avatar
Joined: 18 Jul 2013
Posts: 42
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 22 Oct 2014, 10:55
five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.


From question i understand that if 5 men worked together they would have completed 1 task n 100 day mean seach person will take 20 days to complete a task.

Than how come below mention predication(500 )days are possible ???????????????????????????????????????

At the beginning, we know it takes 100 days for 5 people working together to complete. This means each will take 500 days to complete working solo. But, 10% of the work is already done, so it will take another 90 days for the 5 people to complete. This means, the remaining work takes 450 days to complete solo.

To get this, I just did 5*(1/person) = 1/100 and 1/90, respectively to get 500 and 450 days, respectively, when solving for "person."

Next, you need to calculate (5+x)/450 = 1/(y-10) to form an analogy with the work/rate problem. This is only possible when x=20 and y=28, which means an additional 18 days is needed after 10% work is done. Hope that makes.

Expert advice please....
Manager
Manager
avatar
Joined: 22 Aug 2014
Posts: 174
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 22 Apr 2015, 04:38
arindamsur wrote:
I saw the solution (5 + x) × (y – 10) = 450 Its is not clear to me (y - 10)

From there they jump to solution x = 20 and y = 28

MKS wrote:
arindamsur wrote:
Five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.

A) X= 16 Y= 20

B) X= 20 Y= 24

C) X= 24 Y= 28

D) X= 28 Y= 32

E) X= 20 Y= 28


IMO -
None of these.

My equation -> (5+x)(y-10)= (500)*9/10 ->
one possible solution is - x=10, y=13.


please help
Still not clear to me why y-10 is taken instead of y?
(5+x)(y-10)= (500)*9/10
EMPOWERgmat Instructor
User avatar
V
Status: GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Joined: 19 Dec 2014
Posts: 12189
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 23 Apr 2015, 15:54
2
HI ssriva2,

This question can be solved in a couple of different ways. Beyond the Algebra that you might do, you can also TEST THE ANSWERS. Depending on the approach that you choose to take, the math involved will vary in difficulty. Staying organized is KEY though, since this prompt includes a LOT of details....

We're told that 5 men start a job that will take 100 days to finish. This means that 5(100) = 500 man-days of work are required to finish the job.

After 10% of the work was done, "X" ADDITIONAL men were added.

10% of 100 days = 10 days
10% of 500 man-days = 50 man-days

So, 10 days have gone by and 450 man-days of work remain.

We're told that AFTER adding those "X" men, the TOTAL number of days required to finish the job became "Y." We're asked to find the answer that gives us an X and Y that "fit" this situation.

Remember those initial 5 workers in the question....they still impact the calculation. Since all of the answer choices include INTEGERS, we'll need a value for X so that (X+5) divides evenly into 450. Considering the values of X that appear in the answers, you'll find that (20+5) divides into 450:

450/25 = 18

So with 25 workers, it would take 18 MORE days to finish the job (after the initial 10 days of work already occurred).

X = 20 and Y = 28

Final Answer:

GMAT assassins aren't born, they're made,
Rich
_________________

760+: Learn What GMAT Assassins Do to Score at the Highest Levels
Contact Rich at: Rich.C@empowergmat.com

Rich Cohen

Co-Founder & GMAT Assassin

Special Offer: Save $75 + GMAT Club Tests Free
  Official GMAT Exam Packs + 70 Pt. Improvement Guarantee
www.empowergmat.com/

***********************Select EMPOWERgmat Courses now include ALL 6 Official GMAC CATs!***********************

Manager
Manager
User avatar
S
Joined: 01 Dec 2016
Posts: 115
Concentration: Finance, Entrepreneurship
GMAT 1: 650 Q47 V34
WE: Investment Banking (Investment Banking)
GMAT ToolKit User
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 09 Jun 2017, 00:54
Not sure to find the right answer in less than 2 min.
if this is a real Gmat question then it must be of 700+ level
_________________

What was previously considered impossible is now obvious reality.
In the past, people used to open doors with their hands. Today, doors open "by magic" when people approach them

VP
VP
User avatar
P
Status: Learning
Joined: 20 Dec 2015
Posts: 1219
Location: India
Concentration: Operations, Marketing
GMAT 1: 670 Q48 V36
GRE 1: Q157 V157
GPA: 3.4
WE: Engineering (Manufacturing)
Reviews Badge CAT Tests
Re: Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 09 Jun 2017, 08:58
I got it wrong took total no of days as 100
But now seeing it gain I got the concept of Man days

Sent from my ONE E1003 using GMAT Club Forum mobile app
_________________

Please give kudos if you found my answers useful

VP
VP
avatar
P
Joined: 07 Dec 2014
Posts: 1069
Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 09 Jun 2017, 11:16
arindamsur wrote:
Five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.

A) X= 16 Y= 20

B) X= 20 Y= 24

C) X= 24 Y= 28

D) X= 28 Y= 32

E) X= 20 Y= 28


number of men=5+x
rate of 1 man per 1 day=1/500
time to complete work=y-10 days
portion of work to be completed=9/10
hence, (5+x)/500*(y-10)=9/10➡(x+5)(y-10)=450
plugging in choices, only E works:
x=20; y=28
BSchool Forum Moderator
User avatar
V
Joined: 26 Feb 2016
Posts: 3043
Location: India
GPA: 3.12
Premium Member CAT Tests
Five men started working on a job that was to be finished in hundred d  [#permalink]

Show Tags

New post 09 Feb 2018, 06:26
arindamsur wrote:
Five men started working on a job that was to be finished in hundred days. After ten percent of the work was completed, “x” number of men were added to the taskforce and it was found that the whole work was completed in a total of “y” days. Select the values of x and y that are consistent with the given data.

A) X= 16 Y= 20
B) X= 20 Y= 24
C) X= 24 Y= 28
D) X= 28 Y= 32
E) X= 20 Y= 28


Consider the total work to be 1000 units. Since 10%(100 units) of the work was completed by 5 men,
each man did about 2 units/day as the work went on for 10 days.

Now that x men join the work force, the work done in a day will be 2(5+x). They will have y-10 days
to complete the work. For the correct combination of x and y, the men must complete 900 units(exactly)

A) X= 16 Y= 20 | Work done = 2(5+16)*(20-10) = 42*10 = 420 units
B) X= 20 Y= 24 | Work done = 2(5+20)*(24-10) = 50*14 = 700 units
C) X= 24 Y= 28 | Work done = 2(5+24)*(28-10) = 58*18 = 1044 units
D) X= 28 Y= 32 | Work done = 2(5+28)*(32-10) = 33*22 = 726 units

E) X= 20 Y= 28 | Work done = 2(5+20)*(28-10) = 50*18 = 900 units

Therefore, Option E(X= 20 Y= 28) has the values that are consistent and is our answer!
_________________

You've got what it takes, but it will take everything you've got

Five men started working on a job that was to be finished in hundred d &nbs [#permalink] 09 Feb 2018, 06:26
Display posts from previous: Sort by

Five men started working on a job that was to be finished in hundred d

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  

Events & Promotions

PREV
NEXT


GMAT Club MBA Forum Home| About| Terms and Conditions and Privacy Policy| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.