Last visit was: 28 Mar 2025, 03:30 It is currently 28 Mar 2025, 03:30
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
EgmatQuantExpert
User avatar
e-GMAT Representative
Joined: 04 Jan 2015
Last visit: 02 Apr 2024
Posts: 3,689
Own Kudos:
18,860
 [75]
Given Kudos: 165
Expert
Expert reply
Posts: 3,689
Kudos: 18,860
 [75]
2
Kudos
Add Kudos
72
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
EgmatQuantExpert
User avatar
e-GMAT Representative
Joined: 04 Jan 2015
Last visit: 02 Apr 2024
Posts: 3,689
Own Kudos:
18,860
 [18]
Given Kudos: 165
Expert
Expert reply
Posts: 3,689
Kudos: 18,860
 [18]
8
Kudos
Add Kudos
10
Bookmarks
Bookmark this Post
User avatar
pushpitkc
Joined: 26 Feb 2016
Last visit: 19 Feb 2025
Posts: 2,833
Own Kudos:
5,741
 [8]
Given Kudos: 47
Location: India
GPA: 3.12
Posts: 2,833
Kudos: 5,741
 [8]
5
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
General Discussion
User avatar
Nixondutta
Joined: 24 Apr 2017
Last visit: 10 Aug 2018
Posts: 40
Own Kudos:
Given Kudos: 83
Status:The journey is always more beautiful than the destination
Affiliations: Computer Science
Location: India
Concentration: Statistics, Strategy
GMAT 1: 570 Q40 V28
GPA: 3.14
GMAT 1: 570 Q40 V28
Posts: 40
Kudos: 76
Kudos
Add Kudos
Bookmarks
Bookmark this Post
EgmatQuantExpert
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 3

Leo, Shelly and Raj can complete a certain job in 10, 12, and 15 days respectively. They are assigned to work together to complete the job. All of them started the job together. Leo left 1 day before the completion day and Raj left 2 days before the completion day of the job. In how many days the job gets completed?

    A. \(\frac{34}{5}\) days

    B. \(\frac{48}{5}\) days

    C. \(\frac{57}{12}\) days

    D. \(\frac{66}{15}\) days

    E. \(\frac{74}{15}\) days

shouldn't the answer be A?
According to the question my soln comes 89/15. where am i going wrong?
avatar
zishu912
Joined: 31 Jan 2018
Last visit: 02 Nov 2019
Posts: 54
Own Kudos:
34
 [1]
Given Kudos: 39
GMAT 1: 700 Q46 V40
GMAT 1: 700 Q46 V40
Posts: 54
Kudos: 34
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
EgmatQuantExpert
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 3

Leo, Shelly and Raj can complete a certain job in 10, 12, and 15 days respectively. They are assigned to work together to complete the job. All of them started the job together. Leo left 1 day before the completion day and Raj left 2 days before the completion day of the job. In how many days the job gets completed?

    A. \(\frac{34}{5}\) days

    B. \(\frac{48}{5}\) days

    C. \(\frac{57}{12}\) days

    D. \(\frac{66}{15}\) days

    E. \(\frac{74}{15}\) days

Let's total unit of work LCM[10,12,15] = 60 units of work
Leo does 60 /10 = 6 units of work per day
shelly does 60/112 = 5 units of work per day
Raj does 60 / 15 = 4 units of work per day

now Raj leaves 2 before the completion day and leo leaves 1 day before the completion
Assume the work completed on x days
Therefore,
(6 + 4 +5)(x - 2) + (6 + 5) + 5= 60
==>15x - 30 = 60 - 16
==> 15x = 44 + 30 = 74

Hence x = 74 / 15
User avatar
gracie
Joined: 07 Dec 2014
Last visit: 11 Oct 2020
Posts: 1,042
Own Kudos:
1,780
 [1]
Given Kudos: 27
Posts: 1,042
Kudos: 1,780
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
EgmatQuantExpert
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 3

Leo, Shelly and Raj can complete a certain job in 10, 12, and 15 days respectively. They are assigned to work together to complete the job. All of them started the job together. Leo left 1 day before the completion day and Raj left 2 days before the completion day of the job. In how many days the job gets completed?

    A. \(\frac{34}{5}\) days

    B. \(\frac{48}{5}\) days

    C. \(\frac{57}{12}\) days

    D. \(\frac{66}{15}\) days

    E. \(\frac{74}{15}\) days

let d=days to complete job
d(15/60)-14/60=1
d=74/15 days
E
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 27 Mar 2025
Posts: 15,835
Own Kudos:
72,330
 [5]
Given Kudos: 461
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 15,835
Kudos: 72,330
 [5]
2
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
EgmatQuantExpert
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 3

Leo, Shelly and Raj can complete a certain job in 10, 12, and 15 days respectively. They are assigned to work together to complete the job. All of them started the job together. Leo left 1 day before the completion day and Raj left 2 days before the completion day of the job. In how many days the job gets completed?

    A. \(\frac{34}{5}\) days

    B. \(\frac{48}{5}\) days

    C. \(\frac{57}{12}\) days

    D. \(\frac{66}{15}\) days

    E. \(\frac{74}{15}\) days



To solve question 4: Question 4

To read the article: 3 Deadly Mistakes You Must Avoid in Time and Work Questions

Responding to a pm:

On the last day of the job, only Shelly worked so she could have done only 1/12 of the work.

So 11/12 of the work was done before the completion day.

On the day before last, only Leo and Shelly worked so they would have done 1/10 + 1/12 = 11/60 of the work

So 11/12 - 11/60 = 11/15 of the work was done before by all three.
Combined rate of all three = 1/10 + 1/12 + 1/15 = 1/4
For this, time taken = (11/15) / (1/4) = 44/15

Total time taken = 44/15 + 2 = 74/15

Note: Usually in questions with fractional number of days, the fractional day is the last day. It is certainly unsettling that as per this question, the work was started in the middle of the day some time.
avatar
Krotishka1
Joined: 02 May 2018
Last visit: 09 Jan 2025
Posts: 10
Own Kudos:
Given Kudos: 16
GMAT 1: 660 Q49 V31
GMAT 1: 660 Q49 V31
Posts: 10
Kudos: 5
Kudos
Add Kudos
Bookmarks
Bookmark this Post
pushpitkc
EgmatQuantExpert
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 3

Leo, Shelly and Raj can complete a certain job in 10, 12, and 15 days respectively. They are assigned to work together to complete the job. All of them started the job together. Leo left 1 day before the completion day and Raj left 2 days before the completion day of the job. In how many days the job gets completed?

    A. \(\frac{34}{5}\) days

    B. \(\frac{48}{5}\) days

    C. \(\frac{57}{12}\) days

    D. \(\frac{66}{15}\) days

    E. \(\frac{74}{15}\) days

Given data: Leo, Shelly,and Raj can complete a certain job in 10,12,and 15 days.

We assume the work that needs to be done as LCM(10,12,15) = 60 units.
Individual rates are as follows: Leo - 6 units/day | Shelly - 5 units/day | Raj - 4 units/day

If they work together, they will complete 6+5+4 = 15 units in a day. When Raj leaves 2 days before,
Leo & Shelly do 11 units/day. When Leo also leaves work 1 day before, Shelly does 5 units in a day.

Let x be the number of days.
\(15(x-2) + 11 + 6 = 60\) -> \(15x - 30 + 16 = 60\) -> \(15x - 14 = 60\) -> \(x = \frac{74}{15}\) days

Therefore, Leo, Shelly and Raj complete the job in \(\frac{74}{15}\) days (Option E)

There's a typo in your first equation - it should be \(15(x-2) + 11 + 5\)
avatar
Krotishka1
Joined: 02 May 2018
Last visit: 09 Jan 2025
Posts: 10
Own Kudos:
Given Kudos: 16
GMAT 1: 660 Q49 V31
GMAT 1: 660 Q49 V31
Posts: 10
Kudos: 5
Kudos
Add Kudos
Bookmarks
Bookmark this Post
By the way, how do I understand that the completion day does not vary, i.e. it is fixed?

I've spent ~40 freaking mins trying to solve this, because I thought that the completion day changes once a person leaves the team, which is logical. That is, when Raj left, I changed the Work value to \(1/2\) and Rate value to \(11/60\). Using these values I calculated the time needed to finish the work - \(30/11\). Then I figured out that Leo leaves at moment \(30/11 - 11/11 = 19/11\). I calculated the amount of work done by both Leo and Shelly, which is \(11/60 * 19/11 = 19/60\).

Now, knowing that the amount of Work left is \(1 - (30/60) - (19/60) = (11/60)\), I calculated the time needed for Shelly to finish the work alone, which is \((11/60) : (5/60) = (11/5)\).

Finally, I added up all the time values, i.e. \(2 days + (19/11) days + (11/5) days\), and obtained a result \((326/55)\).

This did not match any of the answers provided here, and I tried to find my mistake for 40 FREAKING MINUTES. As you can see, my logic was not wrong. So, how should have I figured out what I was supposed to calculate?
User avatar
pushpitkc
Joined: 26 Feb 2016
Last visit: 19 Feb 2025
Posts: 2,833
Own Kudos:
Given Kudos: 47
Location: India
GPA: 3.12
Posts: 2,833
Kudos: 5,741
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Krotishka1
pushpitkc
EgmatQuantExpert
3 Deadly Mistakes You Must Avoid in Time and Work Questions – Practice question 3

Leo, Shelly and Raj can complete a certain job in 10, 12, and 15 days respectively. They are assigned to work together to complete the job. All of them started the job together. Leo left 1 day before the completion day and Raj left 2 days before the completion day of the job. In how many days the job gets completed?

    A. \(\frac{34}{5}\) days

    B. \(\frac{48}{5}\) days

    C. \(\frac{57}{12}\) days

    D. \(\frac{66}{15}\) days

    E. \(\frac{74}{15}\) days

Given data: Leo, Shelly,and Raj can complete a certain job in 10,12,and 15 days.

We assume the work that needs to be done as LCM(10,12,15) = 60 units.
Individual rates are as follows: Leo - 6 units/day | Shelly - 5 units/day | Raj - 4 units/day

If they work together, they will complete 6+5+4 = 15 units in a day. When Raj leaves 2 days before,
Leo & Shelly do 11 units/day. When Leo also leaves work 1 day before, Shelly does 5 units in a day.

Let x be the number of days.
\(15(x-2) + 11 + 6 = 60\) -> \(15x - 30 + 16 = 60\) -> \(15x - 14 = 60\) -> \(x = \frac{74}{15}\) days

Therefore, Leo, Shelly and Raj complete the job in \(\frac{74}{15}\) days (Option E)

There's a typo in your first equation - it should be \(15(x-2) + 11 + 5\)

Thanks for notifying Krotishka1 - Made the necessary change
User avatar
pushpitkc
Joined: 26 Feb 2016
Last visit: 19 Feb 2025
Posts: 2,833
Own Kudos:
Given Kudos: 47
Location: India
GPA: 3.12
Posts: 2,833
Kudos: 5,741
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Krotishka1
By the way, how do I understand that the completion day does not vary, i.e. it is fixed?

I've spent ~40 freaking mins trying to solve this, because I thought that the completion day changes once a person leaves the team, which is logical. That is, when Raj left, I changed the Work value to \(1/2\) and Rate value to \(11/60\). Using these values I calculated the time needed to finish the work - \(30/11\). Then I figured out that Leo leaves at moment \(30/11 - 11/11 = 19/11\). I calculated the amount of work done by both Leo and Shelly, which is \(11/60 * 19/11 = 19/60\).

Now, knowing that the amount of Work left is \(1 - (30/60) - (19/60) = (11/60)\), I calculated the time needed for Shelly to finish the work alone, which is \((11/60) : (5/60) = (11/5)\).

Finally, I added up all the time values, i.e. \(2 days + (19/11) days + (11/5) days\), and obtained a result \((326/55)\).

This did not match any of the answers provided here, and I tried to find my mistake for 40 FREAKING MINUTES. As you can see, my logic was not wrong. So, how should have I figured out what I was supposed to calculate?

Hey Krotishka1

The mistake you are making is that you have calculated the time for Leo and Shelly to complete
the work, but the work doesn't get completed. When you are adding up the individual times you
have added the time that Leo and Shelly would have taken to complete the work :)

Whenever you want to solve this kind of problem using this method you need to go backward from
the last day to the first day. The solution provided by VeritasPrepKarishma should make it clear.

Hope this helps you.
User avatar
pratik2018
Joined: 09 Apr 2017
Last visit: 23 Jun 2020
Posts: 37
Own Kudos:
Given Kudos: 188
Location: Nepal
Concentration: Finance, Entrepreneurship
GMAT 1: 580 Q47 V22
GMAT 2: 640 Q48 V29
GMAT 3: 690 Q48 V36
WE:Information Technology (Computer Software)
Products:
GMAT 3: 690 Q48 V36
Posts: 37
Kudos: 157
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Is there a different way to solve this? The traditional way of taking what work would be done on a day to day basis.
User avatar
Abhishek009
User avatar
Board of Directors
Joined: 11 Jun 2011
Last visit: 16 Dec 2024
Posts: 5,997
Own Kudos:
Given Kudos: 463
Status:QA & VA Forum Moderator
Location: India
GPA: 3.5
WE:Business Development (Commercial Banking)
Posts: 5,997
Kudos: 5,063
Kudos
Add Kudos
Bookmarks
Bookmark this Post
EgmatQuantExpert
Leo, Shelly and Raj can complete a certain job in 10, 12, and 15 days respectively. They are assigned to work together to complete the job. All of them started the job together. Leo left 1 day before the completion day and Raj left 2 days before the completion day of the job. In how many days the job gets completed?

    A. \(\frac{34}{5}\) days

    B. \(\frac{48}{5}\) days

    C. \(\frac{57}{12}\) days

    D. \(\frac{66}{15}\) days

    E. \(\frac{74}{15}\) days
Let the total work be 60 units....

So, Individual efficiencies are -

Leo : 6 units/day , Shelly : 5 units/day & Raj : 4 Units/day

Now, consider that the total work was considered in "t" days and from this part

Quote:
Leo left 1 day before the completion day and Raj left 2 days before the completion day of the job.
We understand that only shelly worked for "t" days....

Now, \(6*(t - 1) + 4*(t - 2) + 5t = 60\)

Or, \(6t - 6 + 4t - 8 + 5t = 60\)

Or, \(15t - 14 = 60\)

Or, \(t = 74/15\), Answer must be (E)
User avatar
jhaamod10
Joined: 31 Oct 2018
Last visit: 29 Dec 2024
Posts: 12
Own Kudos:
Given Kudos: 6
Posts: 12
Kudos: 3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let work is completed in n days
Then
n/12 + (n-1)/10 + (n-2)/15 = 1
15n - 14 = 60
n = 74/15

Posted from my mobile device
User avatar
jhaamod10
Joined: 31 Oct 2018
Last visit: 29 Dec 2024
Posts: 12
Own Kudos:
Given Kudos: 6
Posts: 12
Kudos: 3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let work is completed in n days
Then
n/12 + (n-1)/10 + (n-2)/15 = 1
15n - 14 = 60
n = 74/15

Posted from my mobile device
User avatar
adman
Joined: 11 May 2023
Last visit: 25 Dec 2024
Posts: 1
Given Kudos: 18
Location: India
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
­Rate of work for Shelly, Leo and Raj with W being 1 work unit -
1. Shelly = 1/12 W/day
2. Leo = 1/10 W/day
3. Raj = 1/15 W/day

Now solving these using the timeline method -

start |-------L+R+S-------|-------S+L-------|-------S-------|
                             [-2 days]         [ -1 days]

Assuming total number of days is X - 

Total time Shelly works is X x 1/12
Total time Leo works is (X - 1) x 1/10
Total time Raj works is (X - 2) x 1/15

All of this adds up to 1 Work unit -

X x 1/12 + (X-1) x 1/10 + (X-2) x 1/15 = 1

Solving for X we get => 74/15 days
Moderators:
Math Expert
100116 posts
PS Forum Moderator
521 posts