Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.
Customized for You
we will pick new questions that match your level based on your Timer History
Track Your Progress
every week, we’ll send you an estimated GMAT score based on your performance
Practice Pays
we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Thank you for using the timer!
We noticed you are actually not timing your practice. Click the START button first next time you use the timer.
There are many benefits to timing your practice, including:
Enter The Economist GMAT Tutor’s Brightest Minds competition – it’s completely free! All you have to do is take our online GMAT simulation test and put your mind to the test. Are you ready? This competition closes on December 13th.
Attend a Veritas Prep GMAT Class for Free. With free trial classes you can work with a 99th percentile expert free of charge. Learn valuable strategies and find your new favorite instructor; click for a list of upcoming dates and teachers.
Does GMAT RC seem like an uphill battle? e-GMAT is conducting a free webinar to help you learn reading strategies that can enable you to solve 700+ level RC questions with at least 90% accuracy in less than 10 days.
Machines X and Y can work at their respective constant rates
[#permalink]
Show Tags
Updated on: 13 Aug 2018, 06:00
2
23
00:00
A
B
C
D
E
Difficulty:
55% (hard)
Question Stats:
64% (01:49) correct 36% (01:38) wrong based on 358 sessions
HideShow timer Statistics
Solve Time and Work Problems Efficiently using Efficiency Method! - Exercise Question #4
Machines X and Y can work at their respective constant rates to manufacture a certain production unit. If both are working alone, then the time taken by machine Y is what percentage more/less than that of machine X?
(1) Machines X and Y, working together, complete a production order of the same size in two-thirds the time that machine Y, working alone, does. (2) Machine Y, working alone, fills a production order of twice the size in 6 hrs.
Option choices: A) Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient. B) Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient. C) BOTH statements TOGETHER are sufficient, but NEITHER statement ALONE is sufficient. D) EACH statement ALONE is sufficient. E) Statements (1) and (2) TOGETHER are NOT sufficient.
Re: Machines X and Y can work at their respective constant rates
[#permalink]
Show Tags
26 May 2018, 13:57
5
1
1
Question Stem:- Machines X and Y can work at their respective constant rates to manufacture a certain production unit. If both are working alone, then the time taken by machine Y is what percentage more/less than that of machine X? Rephrase:- Machines X and Y can work at their respective constant rates of 1/x and 1/y respectively (where x and y indicate time taken to complete one job).
\(\frac{y}{x}-1\) = ? i.e can we get the value of \(\frac{y}{x}\)
Kindly note:- When both work together means they work at a rate of \(\frac{1}{x}\)+\(\frac{1}{y}\) = \(\frac{x+y}{xy}\) Time taken when both machines work together = \(\frac{xy}{x+y}\)
Lets evaluate both the statements:- Statement (1) Machines X and Y, working together, complete a production order of the same size in two-thirds the time that machine Y, working alone, does.
Therefore from (1) \(\frac{xy}{x+y}\) = \(\frac{2y}{3}\) which implies \(\frac{x}{x+y}\) = \(\frac{2}{3}\) or\(\frac{y}{x} = \frac{1}{2}\) Since we have got the value of \(\frac{y}{x}\) Statement 1 is sufficient; Not lets check statement 2 [Cross B,C & E] Evaluate between A & D:-
Statement (2) Machine Y, working alone, fills a production order of twice the size in 6 hrs.
There is no mention about the rate of machine X hence statement (2) is insufficient. Hence the correct answer is option A.
_________________
________________ Manish
"Only I can change my life. No one can do it for me"
Re: Machines X and Y can work at their respective constant rates
[#permalink]
Show Tags
27 May 2018, 05:32
Solution
Given:
• Machine X and Y work at their respective constant rates to manufacture a certain production unit
To find:
• When both machines are working alone, the time taken by machine Y is what percentage more/less than that of machine X
Approach and Working: If we assume the time taken by machine X and Y individually to complete the work is \(t_1\) and \(t_2\) respectively, then
• Time \(t_2\) is more than time \(t_1\) by (as a percentage) = \(\frac{(t_2 – t_1)}{t_1} * 100\)
o This can be written as = (\(\frac{t_2}{t_1}\) – 1) * 100
[Note that if \(t_2\) is less than \(t_1\), then the above expression will be equal to (1 – \(\frac{t_2}{t_1}\)) * 100
• Hence, if we can find the value of the ratio \(\frac{t_2}{t_1}\), we can find out the required percentage
Analysing Statement 1
• As per the information given in statement 1, Machines X and Y, working together, complete a production order of the same size in two-thirds the time that machine Y, working alone, does.
o The time taken by both of them together to complete the job = \(\frac{t_1t_2}{(t_1 + t_2)}\)
• Given that, \(\frac{t_1t_2}{(t_1 + t_2)}\) = \(\frac{2}{3} t_2\)
o Simplifying, we can write \(\frac{t_2}{t_1}\) = \(\frac{2}{1}\)
Hence, statement 1 is sufficient enough to answer the question
Analysing Statement 2
• As per the information given in statement 2, Machine Y, working alone, fills a production order of twice the size in 6 hrs
o From this statement, we can say \(t_2\) = 3 hours o But we cannot conclude any relationship between \(t_1\) and \(t_2\)
Hence, statement 2 is not sufficient to answer the question
Hence, the correct answer is option A.
Answer: A
Important Observation
• When we are calculating by what percentage one element is more/less than the other element, we only need to find out the ratio between those elements.
Re: Machines X and Y can work at their respective constant rates
[#permalink]
Show Tags
30 Oct 2018, 03:15
EgmatQuantExpert wrote:
Machines X and Y can work at their respective constant rates to manufacture a certain production unit. If both are working alone, then the time taken by machine Y is what percentage more/less than that of machine X?
(1) Machines X and Y, working together, complete a production order of the same size in two-thirds the time that machine Y, working alone, does. (2) Machine Y, working alone, fills a production order of twice the size in 6 hrs.
Re: Machines X and Y can work at their respective constant rates
[#permalink]
Show Tags
27 Jun 2019, 07:52
CAMANISHPARMAR wrote:
Question Stem:- Machines X and Y can work at their respective constant rates to manufacture a certain production unit. If both are working alone, then the time taken by machine Y is what percentage more/less than that of machine X? Rephrase:- Machines X and Y can work at their respective constant rates of 1/x and 1/y respectively (where x and y indicate time taken to complete one job).
\(\frac{y}{x}-1\) = ? i.e can we get the value of \(\frac{y}{x}\)
Kindly note:- When both work together means they work at a rate of \(\frac{1}{x}\)+\(\frac{1}{y}\) = \(\frac{x+y}{xy}\) Time taken when both machines work together = \(\frac{xy}{x+y}\)
Lets evaluate both the statements:- Statement (1) Machines X and Y, working together, complete a production order of the same size in two-thirds the time that machine Y, working alone, does.
Therefore from (1) \(\frac{xy}{x+y}\) = \(\frac{2y}{3}\) which implies \(\frac{x}{x+y}\) = \(\frac{2}{3}\) or\(\frac{y}{x} = \frac{1}{2}\) Since we have got the value of \(\frac{y}{x}\) Statement 1 is sufficient; Not lets check statement 2 [Cross B,C & E] Evaluate between A & D:-
Statement (2) Machine Y, working alone, fills a production order of twice the size in 6 hrs.
There is no mention about the rate of machine X hence statement (2) is insufficient. Hence the correct answer is option A.
Re: Machines X and Y can work at their respective constant rates
[#permalink]
Show Tags
27 Jun 2019, 08:02
nsato wrote:
nsato wrote:
Kindly note:- When both work together means they work at a rate of 1/x+1/y = (x+y)/xy
Can somebody explain why this is?
So the rule here is that Rate of A + Rate of B = the combined Rate of A and B.
Here, if x is the time taken by Machine X to complete a job, its rate is 1/x. If y is the time taken by Machine Y to complete a job, its rate is 1/y. So the combined Rate of Machines X and Y is 1/x + 1/y.
Let's take this math step by step:
\(\frac{1}{x}+\frac{1}{y}\)
Get a common denominator by multiplying first fraction by y/y and second fraction by x/x: