Last visit was: 25 Apr 2024, 12:30 It is currently 25 Apr 2024, 12:30

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Manager
Manager
Joined: 28 Aug 2006
Posts: 165
Own Kudos [?]: 278 [0]
Given Kudos: 0
Send PM
User avatar
Senior Manager
Senior Manager
Joined: 01 Oct 2006
Posts: 301
Own Kudos [?]: 71 [0]
Given Kudos: 0
User avatar
Manager
Manager
Joined: 28 Aug 2006
Posts: 165
Own Kudos [?]: 278 [0]
Given Kudos: 0
Send PM
User avatar
Manager
Manager
Joined: 28 Aug 2006
Posts: 165
Own Kudos [?]: 278 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Here comes our next question.......

3. Fresh Grapes contain 90% water and 10% grape pulp whereas Dry Grapes
contain 20% water and 80% grape pulp. How many kgs of Dry Grapes can
be obtained from 20 kgs of Fresh Grapes?
User avatar
Senior Manager
Senior Manager
Joined: 01 Oct 2006
Posts: 301
Own Kudos [?]: 71 [0]
Given Kudos: 0
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Amount of grape pulp will remain same.
80Z/100 =10/100*20
z=2.5

Answer is 2.5 kgs
User avatar
Manager
Manager
Joined: 28 Aug 2006
Posts: 165
Own Kudos [?]: 278 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
yogeshsheth wrote:
Amount of grape pulp will remain same.
80Z/100 =10/100*20
z=2.5

Answer is 2.5 kgs


As simple as that....................

Here comes our next question

4. A group of men can complete a work in certain number of days. After they
worked for 12 days 1/4 of them left. To complete the remaining work the
remaining men have taken as many days as the initial number of men
would have taken to complete the entire work. In how many days is the
work completed?
User avatar
Current Student
Joined: 08 Aug 2006
Posts: 324
Own Kudos [?]: 41 [0]
Given Kudos: 0
Location: San Francisco
Schools:Berkeley Haas
 Q50  V44
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
I got DC = 5 and CE = 11/5. Also used similarity of triangles by a side and two adjacent angles.

EDIT: whooops, missed the second page :) Sorry, this was for question 2.

EDIT2: here goes number 4...

S = total job
v = total speed of all men
t = original time

S = v*t
S = 12*v + 0.75v*t

vt = 12v + 0.75vt
0.25t = 12
t = 48

ANSWER: the work will be done in (48 + 12) = 60 days.
User avatar
Manager
Manager
Joined: 28 Aug 2006
Posts: 165
Own Kudos [?]: 278 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
That's the right answer......

Any other approaches.........
User avatar
Manager
Manager
Joined: 28 Aug 2006
Posts: 165
Own Kudos [?]: 278 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Here comes our next question.........

5. When a clock indicates completion of 24 hours it actually loses one hour. How much time does it loose in 5 days?
User avatar
Senior Manager
Senior Manager
Joined: 09 Aug 2006
Posts: 284
Own Kudos [?]: 492 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
I get 5 hrs .. I know it is not that simple but that's what I can see.

Amit
avatar
Director
Director
Joined: 03 Jan 2005
Posts: 971
Own Kudos [?]: 769 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
A little less than that I would say. How about 4.8 hours? (It loses 1 hour every 25 hours, if I understand correctly).
User avatar
Manager
Manager
Joined: 28 Aug 2006
Posts: 165
Own Kudos [?]: 278 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Yed Honghu, that's the right answer
User avatar
Manager
Manager
Joined: 28 Aug 2006
Posts: 165
Own Kudos [?]: 278 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Folks, it's time again to get into some fight............

Here comes our next question.........

6.

User avatar
Manager
Manager
Joined: 01 Jun 2006
Posts: 74
Own Kudos [?]: 25 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
very tough quest indeed
I find that the radius of the bigger circle is 5
I think this is not a kind of GMAT quest (easy math prob but take too much time and paper also)
User avatar
VP
VP
Joined: 01 May 2006
Posts: 1033
Own Kudos [?]: 251 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
I got 5 as well ;) It's true that it's not a usual GMAT question ;)

I worked it out using an XY plan.

The figure is symetrical. So, we can have the same kind of rectangle at the bottom left of the square (1 vertex on C and the other on the circle).

By defining the origin 0(0,0) = C(0,0), the equation of the circle is:
(1) (x-r)^2 + (y-r)^2 = r^2 with r the radius of the circle.

As the vertex of the rectangle on the circle has the coordinates (2,1), we can plug the values of x & y in (1).

(2-r)^2 + (1-r)^2 = r^2
<=> 4 - 4*r + r^2 + 1 - 2*r + r^2 = r^2
<=> r^2 - 6*r + 5 = 0

We can use the "reduiced" Delta = 3^2 - 5*1 = 4 = 2^2

Thus, we have 2 possibilies :
o r= (3+2)/1 = 5
o r= (3-2)/1 = 1

For the latter radius, the vertex lying on the circle is represented by a point on the "other side" of the circle. In the case of this picture, the radius is 5.
User avatar
Senior Manager
Senior Manager
Joined: 09 Aug 2006
Posts: 284
Own Kudos [?]: 492 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Hi Fig,

I m not clear how you can take the cordinates of vertex as (2 , 1) since 2 and 1 are the length of the rectangle and you are taking the center of the circle as the origin. Even by Visual observation I am not able to understand the login.. Can you please explain ..?


Regards,
Amit
User avatar
Senior Manager
Senior Manager
Joined: 09 Aug 2006
Posts: 284
Own Kudos [?]: 492 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
sorry c as the Origin
User avatar
VP
VP
Joined: 01 May 2006
Posts: 1033
Own Kudos [?]: 251 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Amit05 wrote:
Hi Fig,

I m not clear how you can take the cordinates of vertex as (2 , 1) since 2 and 1 are the length of the rectangle and you are taking the center of the circle as the origin. Even by Visual observation I am not able to understand the login.. Can you please explain ..?


Regards,
Amit


I take the origine O(0,0) at the point C : the vertex of the scare at the bottom left :)

Since this origine definied,
o the vertex of a silimar little rectangle from C and on the circle has the coordinates (2,1) (lenght, width).
o the center of the cicle Z is at (r,r)

Hope this help :)
User avatar
VP
VP
Joined: 01 May 2006
Posts: 1033
Own Kudos [?]: 251 [0]
Given Kudos: 0
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Amit05 wrote:
sorry c as the Origin


Ok ;)
User avatar
Senior Manager
Senior Manager
Joined: 12 Jun 2006
Posts: 263
Own Kudos [?]: 691 [0]
Given Kudos: 1
Send PM
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
Quote:
A group of men can complete a work in certain number of days. After they
worked for 12 days 1/4 of them left. To complete the remaining work the
remaining men have taken as many days as the initial number of men
would have taken to complete the entire work. In how many days is the
work completed?


I tried like this:

r (12) = w
.75r (t - 12) = w ---> .75rt - 9r = 12r ---> rt = 28r ---> t = 28

t = 28 + 12 = 40

I see this is the wrong answer. Should I not have set the two equations equal to one another? Can someone suggest how to correct this
GMAT Club Bot
Re: Problem Solving Territory: 700+ questions only.............. [#permalink]
   1   2   3   
Moderator:
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne