Last visit was: 22 Apr 2026, 12:20 It is currently 22 Apr 2026, 12:20
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
DisciplinedPrep
Joined: 15 Jan 2018
Last visit: 08 Jul 2023
Posts: 1,341
Own Kudos:
2,416
 [26]
Given Kudos: 628
Concentration: Marketing, Leadership
Posts: 1,341
Kudos: 2,416
 [26]
2
Kudos
Add Kudos
24
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
lucajava
Joined: 21 Feb 2019
Last visit: 18 Jul 2019
Posts: 68
Own Kudos:
353
 [11]
Given Kudos: 66
Location: Italy
Posts: 68
Kudos: 353
 [11]
10
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
effatara
Joined: 09 Nov 2015
Last visit: 17 Jul 2024
Posts: 194
Own Kudos:
476
 [7]
Given Kudos: 96
Posts: 194
Kudos: 476
 [7]
4
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
General Discussion
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 22 Apr 2026
Posts: 22,278
Own Kudos:
26,528
 [4]
Given Kudos: 302
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 22,278
Kudos: 26,528
 [4]
1
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
DisciplinedPrep
A contract must be completed in 56 days and 104 men are recruited to work, each working 8 hours a day. After 30 days, \(\frac{2}{5}\) of the work is finished. How many additional men must be employed so that the work is completed on time?

A. 180
B. 64
C. 76
D. 96
E. 120

The rate of 104 men is (2/5)/30 = 2/150 = 1/75. So we see that we need to complete 3/5 of the job in 26 days for a rate of:

(3/5)/26 = 3/130.

We can determine how many men must be used with the following proportion:

104/(1/75) = n/(3/130)

7,800 = 130n/3

23,400 = 130n

180 = n

Since they have 104 men already, they need 76 more men.

Alternate Solution:

If it took 104 men to complete 2/5 of the job in 30 days, then it would take the whole job

30/(2/5) = (30*5)/2 = 75

days to complete, without any additional men. Since we want the remaining job to be completed in 56 - 30 = 26 days instead of 75 - 30 = 45 days, we can find the number of men necessary by setting up an inverse proportion: It would take (104*45)/26 = 180 men to complete the remaining job in 26 days. Thus, 180 - 104 = 76 more men are needed.

Answer: C
User avatar
GyanOne
Joined: 24 Jul 2011
Last visit: 22 Apr 2026
Posts: 3,237
Own Kudos:
1,719
 [1]
Given Kudos: 33
Status: World Rank #4 MBA Admissions Consultant
Expert
Expert reply
Posts: 3,237
Kudos: 1,719
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
DisciplinedPrep
A contract must be completed in 56 days and 104 men are recruited to work, each working 8 hours a day. After 30 days, \(\frac{2}{5}\) of the work is finished. How many additional men must be employed so that the work is completed on time?

A. 180
B. 64
C. 76
D. 96
E. 120

Work done by 104 men working 8 hours a day in 30 days = 104*8*30 man hours
=> Work remaining at that point = (3/2)*104*8*30 = 45*8*104 man hours
=> If x additional men are deployed, then (104+x)*8*26 = 45*8*104
=> x = 76

Option (C).
User avatar
GyanOne
Joined: 24 Jul 2011
Last visit: 22 Apr 2026
Posts: 3,237
Own Kudos:
Given Kudos: 33
Status: World Rank #4 MBA Admissions Consultant
Expert
Expert reply
Posts: 3,237
Kudos: 1,719
Kudos
Add Kudos
Bookmarks
Bookmark this Post
GyanOne
DisciplinedPrep
A contract must be completed in 56 days and 104 men are recruited to work, each working 8 hours a day. After 30 days, \(\frac{2}{5}\) of the work is finished. How many additional men must be employed so that the work is completed on time?

A. 180
B. 64
C. 76
D. 96
E. 120

Work done by 104 men working 8 hours a day in 30 days = 104*8*30 man hours
=> Work remaining at that point = (3/2)*104*8*30 = 45*8*104 man hours
=> If x additional men are deployed, then (104+x)*8*26 = 45*8*104
=> x = 76

Option (C).

Alternative solution 1:
Note that the number of hours worked per man per day are not relevant here.

So, according to the question, 104 men working for 30 days complete 2/5 of the work.
In how many days would these 104 men complete all of the work? In 30*(5/2) = 75 days.
So, to complete (3/5) of the work in 56 days, we need (75*104/26)*(3/5) men, or 180 men.
Thus, we need 76 additional men.

Option (C).

Alternative solution 2:
Let k be the efficiency (work done per person per day) and W the total work.
Then we have:
104*30*8*k = (2/5)*W
AND
x*26*8*k=(3/5)*W

Dividing the equations, we get
x= 3*104*30/(2*26) = 180, or 76 additional men.

Option (C).
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 22 Apr 2026
Posts: 22,278
Own Kudos:
26,528
 [1]
Given Kudos: 302
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 22,278
Kudos: 26,528
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
DisciplinedPrep
A contract must be completed in 56 days and 104 men are recruited to work, each working 8 hours a day. After 30 days, \(\frac{2}{5}\) of the work is finished. How many additional men must be employed so that the work is completed on time?

A. 180
B. 64
C. 76
D. 96
E. 120

Notice that 1 - 2/5 = 3/5 of the job must be completed in 56 - 30 = 26 days.

Since 104 men complete 2/5 of the job in 30 days, they would complete 1/5 of the job in 15 days, and thus, they would complete 3/5 of the job in 3 x 15 = 45 days.

Let’s find the number of men necessary to complete the job (which would be completed by 104 men in 45 days) in 26 days. Let n be the number of men necessary to complete the job in 26 days. Notice that the number of men and the number of days is inversely proportional; thus we must have:

26n = 45 * 104

n = (45 * 104)/26 = 45 * 4 = 180

So, a total of 180 men must work on the job so that it is completed in 26 days. Since we already have 104 men, we need 180 - 104 = 76 additional men.

Answer: C
User avatar
giovanni.ch92
Joined: 04 Jul 2024
Last visit: 20 Apr 2026
Posts: 6
Own Kudos:
Given Kudos: 1
Location: Peru
GMAT 1: 620 Q55 V33
GMAT 1: 620 Q55 V33
Posts: 6
Kudos: 3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Can someone tell me if this approach is correct?

2/5 of work are done in 30days by 104men:
2/5 = 104*rate*30
rate = [2][/5*104*30] = [1][/5*30*52]

we need to do 3/5 of the work in 26days:
[3][/5] = 26days*(104+x)*rate
[3][/5] = 26*([104+x][/5*30*52])
[3*5*30*52][/26*5] = 104 + x
180 = 104 + x
x = 76

Thanks
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,966
Own Kudos:
Posts: 38,966
Kudos: 1,117
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Automated notice from GMAT Club BumpBot:

A member just gave Kudos to this thread, showing it’s still useful. I’ve bumped it to the top so more people can benefit. Feel free to add your own questions or solutions.

This post was generated automatically.
Moderators:
Math Expert
109752 posts
Tuck School Moderator
853 posts