Last visit was: 23 Apr 2026, 12:46 It is currently 23 Apr 2026, 12:46
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
avatar
kspice
Joined: 27 Jun 2011
Last visit: 09 Sep 2011
Posts: 2
Own Kudos:
110
 [110]
Given Kudos: 3
Posts: 2
Kudos: 110
 [110]
8
Kudos
Add Kudos
102
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 23 Apr 2026
Posts: 16,441
Own Kudos:
79,396
 [19]
Given Kudos: 484
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,441
Kudos: 79,396
 [19]
11
Kudos
Add Kudos
7
Bookmarks
Bookmark this Post
User avatar
Spidy001
Joined: 01 Feb 2011
Last visit: 16 Feb 2015
Posts: 298
Own Kudos:
355
 [12]
Given Kudos: 42
Posts: 298
Kudos: 355
 [12]
7
Kudos
Add Kudos
5
Bookmarks
Bookmark this Post
General Discussion
User avatar
fluke
User avatar
Retired Moderator
Joined: 20 Dec 2010
Last visit: 24 Oct 2013
Posts: 1,095
Own Kudos:
5,167
 [5]
Given Kudos: 376
Posts: 1,095
Kudos: 5,167
 [5]
4
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
kspice
Hello!

I just need help on setting up this work problem:

A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone.

A) 4 2/3
B) 7
C) 9
D) 14
E) 24

Please include a detailed explanation as to how you arrived at the solution.

Thank you kindly!

~k

A carpenter worked only 1 day on something that takes him 6 MORE days.
Means;
Carpenter finishes his work in 7 days.
Let his buddy finish the same task in x days.

Respective rates per day:
1/7 AND 1/x

To complete 1 work:
First guy worked for 5 days @ rate=1/7 per day.
Second one worked for 4 days @ rate=1/x per day

Expression:
Days*Rate=Work
5*1/7+4*1/x=1
5x+28=7x
2x=28
x=14 days.

Ans: "D"
User avatar
Aj85
Joined: 14 Mar 2011
Last visit: 23 Feb 2012
Posts: 157
Own Kudos:
332
 [6]
Given Kudos: 21
Posts: 157
Kudos: 332
 [6]
6
Kudos
Add Kudos
Bookmarks
Bookmark this Post
First carpenter can finish the job in 7 days. After first day carpentar 2 joins and the work gets completed in 5 days.

Let the total work be 35 units. (LCM of 5 & 7) Rate of carpentar 1 = 35/7 = 5 units per day. He works for 5 days , so he does total of 25 units out of 35 units. That means carpentar 2 does 35-25 units = 10 units in 4 days. so rate of carpentar 2 - 10/4 = 2.5 units per day. So he will do complete work in 35/2.5 = 14 days.
User avatar
pike
User avatar
Current Student
Joined: 08 Jan 2009
Last visit: 27 Dec 2020
Posts: 245
Own Kudos:
505
 [1]
Given Kudos: 7
GMAT 1: 770 Q50 V46
GMAT 1: 770 Q50 V46
Posts: 245
Kudos: 505
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
fluke
kspice
Hello!
...

A carpenter worked only 1 day on something that takes him 6 MORE days.
Means;
Carpenter finishes his work in 7 days.
Let his buddy finish the same task in x days.

Respective rates per day:
1/7 AND 1/x

To complete 1 work:
First guy worked for 5 days @ rate=1/7 per day.
Second one worked for 4 days @ rate=1/x per day

Expression:
Days*Rate=Work
5*1/7+4*1/x=1
5x+28=7x
2x=28
x=14 days.

Ans: "D"

Nicely explained Fluke
User avatar
shahideh
Joined: 25 May 2011
Last visit: 11 Mar 2012
Posts: 58
Own Kudos:
157
 [6]
Given Kudos: 71
Posts: 58
Kudos: 157
 [6]
5
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
the speed of first carpenter\(=\frac{1}{7}\)
the speed of second carpenter\(=\frac{1}{X}\)

\(1*\frac{1}{7}+4*(\frac{1}{7}+\frac{1}{X})=1\)

\(\frac{4}{7}+\frac{4}{X}=\frac{6}{7}\)

\(X=14\)
avatar
mahdiir
Joined: 30 Oct 2011
Last visit: 04 Nov 2011
Posts: 1
Own Kudos:
Posts: 1
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
shahideh
the speed of first carpenter\(=\frac{1}{7}\)
the speed of second carpenter\(=\frac{1}{X}\)

\(1*\frac{1}{7}+4*(\frac{1}{7}+\frac{1}{X})=1\)

\(\frac{4}{7}+\frac{4}{X}=\frac{6}{7}\)

\(X=14\)


Fascinatingggggggggggg
User avatar
Lucky2783
Joined: 07 Aug 2011
Last visit: 08 May 2020
Posts: 415
Own Kudos:
2,109
 [2]
Given Kudos: 75
Concentration: International Business, Technology
GMAT 1: 630 Q49 V27
GMAT 1: 630 Q49 V27
Posts: 415
Kudos: 2,109
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
kspice
A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?

A) 4 2/3
B) 7
C) 9
D) 14
E) 24


Carpenter takes 1+6 = 7days
When he was joined by his fellow carpenter i.e. after 1 day \(\frac{1 ^t^h}{7}\) of the work was already done so remaining \(\frac{6^t^h}{7}\) was done together in 4 days . setting this up on equation .

\(\frac{1}{7} + \frac{1}{X} = \frac{6}{7} * \frac{1}{4}\)
X=14
Answer D .
User avatar
Divyadisha
User avatar
Current Student
Joined: 18 Oct 2014
Last visit: 01 Jun 2018
Posts: 660
Own Kudos:
Given Kudos: 69
Location: United States
GMAT 1: 660 Q49 V31
GPA: 3.98
GMAT 1: 660 Q49 V31
Posts: 660
Kudos: 1,958
Kudos
Add Kudos
Bookmarks
Bookmark this Post
kspice
A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?

A) 4 2/3
B) 7
C) 9
D) 14
E) 24

On 1st day one carpenter did = 1/7th work (Total days required to finish work= 7 days

Remaining work = 6/7

In next 4 days 1st carpenter must have done 4/7 work, leaving 6/7-4/7= 2/7 for 2nd carpenter.

Now, if 2nd carpenter does 2/7 work in 4 days. he requires 4*7/2= 14 days to finish the whole task.

D is the answer
User avatar
SVaidyaraman
Joined: 17 Dec 2012
Last visit: 11 Jul 2025
Posts: 566
Own Kudos:
1,833
 [1]
Given Kudos: 20
Location: India
Expert
Expert reply
Posts: 566
Kudos: 1,833
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
kspice
A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?

A) 4 2/3
B) 7
C) 9
D) 14
E) 24
1.(no.of days worked by the first person)/ time taken by him if working alone + (no.of days worked by the second person)/ time taken by him if working alone=1
2. (5/7)+ (4/x) = 1, So x=14
User avatar
JeffTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 04 Mar 2011
Last visit: 05 Jan 2024
Posts: 2,974
Own Kudos:
Given Kudos: 1,646
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Expert
Expert reply
Posts: 2,974
Kudos: 8,710
Kudos
Add Kudos
Bookmarks
Bookmark this Post
kspice
A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?

A) 4 2/3
B) 7
C) 9
D) 14
E) 24

The rate of the first carpenter is 1/7.

Since the two carpenters can complete the remaining 6/7 of the job in 4 days, their combined rate is:

(6/7)/4 = 6/28 = 3/14

We can let x = the number of days it takes the second carpenter to complete the job alone; thus, his rate = 1/x. We can create the following equation:

1/7 + 1/x = 3/14

Multiplying the equation by 14x, we have:

2x + 14 = 3x

14 = x

The second carpenter could complete the job alone in 14 days.

Answer: D
User avatar
BrentGMATPrepNow
User avatar
Major Poster
Joined: 12 Sep 2015
Last visit: 31 Oct 2025
Posts: 6,733
Own Kudos:
36,451
 [1]
Given Kudos: 799
Location: Canada
Expert
Expert reply
Posts: 6,733
Kudos: 36,451
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
kspice
A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?

A) 4 2/3
B) 7
C) 9
D) 14
E) 24

A straightforward approach is to assign a nice value to the job.
We're looking for a number that works well with the given numbers (7 days to complete the job, and 4 extra days with help).
So let's say the carpentry job consists of making 56 wooden widgets

GIVEN: A carpenter worked alone for 1 day on a job that would take him 6 more days to finish.
This tells us that it would take the carpenter 7 days to make 56 wooden widgets
So, in ONE day, the carpenter can make 8 wooden widgets.
So, after the first day, the number of widgets we still need to make = 56 - 8 = 48

GIVEN: He and another carpenter completed the job in 4 more days.
So the two carpenters we're able to make 48 wooden widgets in 4 days
This means their COMBINED rate is 12 widgets per day
We already know that the FIRST carpenter makes 8 wooden widgets per day
This means the SECOND carpenter can make 4 wooden widgets per day.

QUESTION: How many days would it have taken the second carpenter to do the complete job working alone?
The job consists of making 56 wooden widgets
The SECOND carpenter can make 4 wooden widgets per day

time = output/rate
So, time = 56/4 = 14 days

Answer: D

Cheers,
Brent
avatar
mm229966
Joined: 05 Oct 2019
Last visit: 07 Jun 2020
Posts: 34
Own Kudos:
Given Kudos: 91
Location: Georgia
Concentration: Marketing, General Management
GMAT 1: 540 Q37 V27
GPA: 2.88
GMAT 1: 540 Q37 V27
Posts: 34
Kudos: 7
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A's rate is 1/7, he worked for 1 day and did 1*1/7=1/7 work;
B's rate is 1/X, he worked with A for 4 days 4*(1/7 + 1/X) work;

Now if we combine them both we'll get completed job:
1/7 + 4*(1/7 + 1/X) = 1; => (4(X+7))+X)/7X = 1;
5X + 28 = 7X; => X = 14;
User avatar
VIGHNESHKAMATH
Joined: 28 Sep 2021
Last visit: 21 Nov 2022
Posts: 145
Own Kudos:
Given Kudos: 259
Posts: 145
Kudos: 54
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let time taken for second carpenter to complete the job working alone is B days

so, as per the given question, equation is as follows.

1/7 + (1/7+1/B) *4 =1

Solve for B, answer is 14.
User avatar
GmatPoint
Joined: 02 Jan 2022
Last visit: 13 Oct 2022
Posts: 246
Own Kudos:
Given Kudos: 3
GMAT 1: 760 Q50 V42
GMAT 1: 760 Q50 V42
Posts: 246
Kudos: 140
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Given that the first carpenter would have completed the work in 7 days. His rate of work per day = \(\frac{W}{7}\)

Since after working for 1 day he started working with another person and got the work done in 4 more days.

In these 5 days, he completed a total work of\( \frac{5W}{7}\)

The other person in the 4 days completed the remaining: \(W\ -\ \frac{5W}{7}=\ \frac{2W}{7}\) part of work in 4 days.

His rate of work is: \(\frac{W}{14}\)

It would take 14 days alone for him to complete the work.
User avatar
horrorslive
Joined: 28 Aug 2023
Last visit: 23 Apr 2026
Posts: 96
Own Kudos:
Given Kudos: 100
Posts: 96
Kudos: 20
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel chetan2u KarishmaB
Doesn't 4 more days mean 5 days? So together won't they complete the remaining job in 5 days?
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 23 Apr 2026
Posts: 16,441
Own Kudos:
Given Kudos: 484
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,441
Kudos: 79,396
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The first carpenter worked alone for 1 day. He and another carpenter completed the job in 4 more days

This means the two worked together for 4 days. The word "more" is used to indicate that they worked for 4 days after the first carpenter worked alone for 1 day.


horrorslive
Bunuel chetan2u KarishmaB
Doesn't 4 more days mean 5 days? So together won't they complete the remaining job in 5 days?
Moderators:
Math Expert
109785 posts
Tuck School Moderator
853 posts