A can build a wall in 10 days, working alone, B can build the same wall in 20 days, working alone and C can break the entire built wall in 8 days, working alone. The three of them work alone on the wall on successive days with A working on first day, B on second day and C on third day and the cycle then repeats. In how many days will the wall be built for the first time?I don't know how many of you prefer the LCM method over the fraction method to solve time and Work-related questions. For me, Since we are using integers in the LCM method, it is more easy to connect and understand the question.
Let's apply the LCM method here as well,
Assume the work as LCM ( 10,20,8 ) = 40 units
Now, let's calculate their per day work, Per day Work = Total Work done/Time taken
Per day work of A is 40/10 = 4 units/day
Per day work of B is 40/20 = 2 units/day
Per day work of A is 40/8 = -5 units/day. * We put negative sign as its a negative work
The three of them work alone on the wall on successive days with A working on the first day, B on the second day, and C on the third day, and the cycle then repeats.
Total work completed by them in 3 days (A working on the first day, B on the second day, and C on the third day )= 4 + 2 - 5 = 1 unit in 3 days.
Since 40 units of work is to be completed, then Time taken would be 40 * 3 = 120 days i.e Option D.
If you got Option D as the answer that means you have
fallen for the GMAT trap. Most of the students would have fallen for it. This is evident from the question statistics i.e 59% made it wrong.
Since C's job is to destroy the wall and he's working on the third day, there could be a chance that the wall will be completed a day before C's turn during the last stretch. This thought process should lead you to do the detailed analysis of work done by them in the last 3 days.
Since A and B can do 6 units in 2 days, let us calculate the time taken to complete 34 units i.e 40 units - 6 units.
Why 34 units? because we know that if we calculate the time for 34 units, A and B can complete the remaining work of 6 units in the next 2 days without C's intervention on the third day.
34 units of work will be completed in 34 * 3 = 102 days.
The next day, A will be completing 4 units and the day after B will be completing 2 units. So a total of 6 units will be completed by A and B in the next 2 days.
So by the end of 104 days, total work of 40 units will be completed. C will not get a chance to destroy it as work is already completed.
Option B is the answer.Thanks,
Clifin J Francis,
GMAT QUANT SME