Last visit was: 25 Apr 2026, 17:51 It is currently 25 Apr 2026, 17:51
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 25 Apr 2026
Posts: 109,830
Own Kudos:
811,285
 [3]
Given Kudos: 105,886
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,830
Kudos: 811,285
 [3]
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
avatar
AquamarineEyes1
Joined: 22 Oct 2020
Last visit: 15 Apr 2021
Posts: 9
Own Kudos:
Given Kudos: 11
Posts: 9
Kudos: 7
Kudos
Add Kudos
Bookmarks
Bookmark this Post
avatar
Danraf
Joined: 15 Aug 2020
Last visit: 24 Aug 2021
Posts: 9
Own Kudos:
Given Kudos: 23
Location: Canada
GMAT 1: 710 Q49 V38
GPA: 3.46
GMAT 1: 710 Q49 V38
Posts: 9
Kudos: 11
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 23 Apr 2026
Posts: 16,441
Own Kudos:
79,413
 [2]
Given Kudos: 485
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,441
Kudos: 79,413
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Bunuel
30 men take 15 days to complete a job working at the rate of 3 h per day. How much time would 18 men, who work for 6 h per day, take to complete the same job?

(A) 10 days
(B) 25/2 days
(C) 51/4 days
(D) 13 days
(E) 14 days

30 men ..... 15 days ..... 3 hrs
18 men ..... ??? days ..... 6 hrs

No of days = 15 * (30/18) * (3/6) = 25/2 days

Check: https://www.gmatclub.com/forum/veritas-prep-resource-links-no-longer-available-399979.html#/2015/1 ... made-easy/
avatar
Akp880
Joined: 24 Mar 2019
Last visit: 08 Nov 2021
Posts: 192
Own Kudos:
Given Kudos: 196
Location: India
Concentration: Marketing, Operations
Schools: IIMA PGPX'23 IIM
WE:Operations (Aerospace and Defense)
Schools: IIMA PGPX'23 IIM
Posts: 192
Kudos: 151
Kudos
Add Kudos
Bookmarks
Bookmark this Post
30 men take 15 days to complete a job working at the rate of 3 h per day. How much time would 18 men, who work for 6 h per day, take to complete the same job?

(A) 10 days
(B) 25/2 days
(C) 51/4 days
(D) 13 days
(E) 14 days

Explanation: A pretty simple logic that requires equating man-hours involved i.e

30 men*3 hrs/day*15 days=18 men*6 hrs/day*(K no.of days)
K=30*3*15/18*6
K=25/2 days

Hence B is the correct answer.
avatar
HinalAmin24
Joined: 10 Jul 2020
Last visit: 24 Mar 2021
Posts: 9
Own Kudos:
Given Kudos: 14
Posts: 9
Kudos: 16
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
30 men take 15 days to complete a job working at the rate of 3 h per day. How much time would 18 men, who work for 6 h per day, take to complete the same job?

(A) 10 days
(B) 25/2 days
(C) 51/4 days
(D) 13 days
(E) 14 days


case 1 : 30 men are working for 3 hr per day for 15 days
case 2 : 18 men are working for 6 hr per day for x days
so case 2 men are working 2 times than case 1 men, so lets consider 18*2 men are working for 3 hr

case 1 work = 30 * 15
case 2 work = 18*2 * x

work done is same for both the cases

30* 15 = 18*2 * x
x = 25/2
avatar
RohitSinha
Joined: 04 May 2020
Last visit: 10 Jul 2025
Posts: 14
Own Kudos:
Given Kudos: 23
GPA: 3.66
WE:Consulting (Computer Software)
Posts: 14
Kudos: 7
Kudos
Add Kudos
Bookmarks
Bookmark this Post
15* 3*30=6*18*x
x=25/2

Posted from my mobile device