Last visit was: 22 Apr 2026, 20:31 It is currently 22 Apr 2026, 20:31
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,685
 [17]
3
Kudos
Add Kudos
14
Bookmarks
Bookmark this Post
User avatar
stne
Joined: 27 May 2012
Last visit: 22 Apr 2026
Posts: 1,808
Own Kudos:
Given Kudos: 678
Posts: 1,808
Kudos: 2,090
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
luisdicampo
Joined: 10 Feb 2025
Last visit: 19 Apr 2026
Posts: 480
Own Kudos:
Given Kudos: 328
Products:
Posts: 480
Kudos: 73
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Edskore
Joined: 29 Dec 2022
Last visit: 22 Apr 2026
Posts: 273
Own Kudos:
Given Kudos: 5
Posts: 273
Kudos: 128
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The concept being tested here is Work and Rate Problems with a split-timeline setup — a classic GMAT Focus twist where two workers don't work together the entire time.

The key is to break the job into two phases and let total work = 1.

Step 1 — Extract the combined rate from the first 7 days.

In the first 7 days, A and B work together and complete 4/5 of the job.

Combined rate (A + B) per day = (4/5) ÷ 7 = 4/35 of the job per day.

Step 2 — Map out the full 10-day timeline.

"A did not work during the last 2 days" means A is absent on days 9 and 10.

- Days 1–8: both A and B work → 8 × (4/35) = 32/35 of the job done
- Days 9–10: only B works → remaining work = 1 − 32/35 = 3/35

B alone completes 3/35 of the job in 2 days → B's rate = 3/70 per day.

Step 3 — Isolate A's rate.

A + B = 4/35, and B = 3/70.

A = 4/35 − 3/70 = 8/70 − 3/70 = 5/70 = 1/14 per day.

A alone takes 14 days → Answer: C.

Common trap: The most frequent mistake is misreading "last 2 days" as days 8 and 9 instead of days 9 and 10, which throws off how much B works alone. Always anchor your timeline to the full job length first — the last 2 days of a 10-day job are days 9 and 10, full stop.

Takeaway: In split-timeline Work and Rate problems, set total work = 1, extract the combined rate from the phase where both workers are present, then use remaining work to isolate each individual rate.
User avatar
Edskore
Joined: 29 Dec 2022
Last visit: 22 Apr 2026
Posts: 273
Own Kudos:
Given Kudos: 5
Posts: 273
Kudos: 128
Kudos
Add Kudos
Bookmarks
Bookmark this Post
This is a classic Work and Rate problem with a split timeline — the kind where GMAT Focus loves to hide the trick in the middle of the setup. Let me share a framing that makes it almost mechanical.

Step 1 — Assign total work = 1, and name the rates.
Let A's rate = a (work/day), B's rate = b (work/day).

Step 2 — Read the timeline carefully.
"A did not work during the last 2 days" means days 9 and 10.
So: Days 1–8: both A and B work. Days 9–10: only B works.

Step 3 — Use the given: in the first 7 days they completed 4/5 of the job.
7(a + b) = 4/5
→ a + b = 4/35

Step 4 — Account for the remaining work.
Remaining after day 7 = 1 − 4/5 = 1/5.
This 1/5 is done over days 8, 9, and 10:
- Day 8: both work → 4/35 of the job
- Days 9–10: only B works → 2b of the job

So: 4/35 + 2b = 1/5
→ 2b = 1/5 − 4/35 = 7/35 − 4/35 = 3/35
→ b = 3/70

Step 5 — Solve for A.
a = 4/35 − 3/70 = 8/70 − 3/70 = 5/70 = 1/14

A alone would take 14 days. Answer: C.

The common trap: Most people read "last 2 days" and assume A stopped working on day 8 as well, treating days 8–10 as all-B. Re-read carefully — "last 2 days" of a 10-day job means days 9 and 10 only. Always map the timeline explicitly before writing equations.

Takeaway: In split-timeline work problems, draw out which workers are active on which days first — one misread of the timeline sends your whole solution off track.

— Kavya | 725 (Q90, V85, DI79) | GMAT Focus Edition
Moderators:
Math Expert
109754 posts
Tuck School Moderator
853 posts