Last visit was: 22 Apr 2026, 11:57 It is currently 22 Apr 2026, 11:57
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,751
Own Kudos:
810,648
 [8]
Given Kudos: 105,821
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,751
Kudos: 810,648
 [8]
1
Kudos
Add Kudos
7
Bookmarks
Bookmark this Post
User avatar
Aryaa03
Joined: 12 Jun 2023
Last visit: 19 Feb 2026
Posts: 210
Own Kudos:
285
 [3]
Given Kudos: 159
Location: India
GMAT Focus 1: 645 Q86 V81 DI78
GMAT Focus 1: 645 Q86 V81 DI78
Posts: 210
Kudos: 285
 [3]
2
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
Shubhradeep
Joined: 11 Jan 2024
Last visit: 07 Feb 2026
Posts: 120
Own Kudos:
247
 [2]
Given Kudos: 108
Location: India
Posts: 120
Kudos: 247
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
PranavVyas
Joined: 13 Aug 2020
Last visit: 19 Apr 2026
Posts: 97
Own Kudos:
107
 [1]
Given Kudos: 94
Concentration: Marketing, Operations
GMAT 1: 540 Q15 V29
WE:Operations (Manufacturing)
GMAT 1: 540 Q15 V29
Posts: 97
Kudos: 107
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
N*15units
5 days working, N workers have done N*5 units of work, and the remaining work is
N*15-N*5 = N*10 units
(N+8)*16 units
N*10=(N+8)*6
4n=48
N=12

IMO-D

Posted from my mobile device
User avatar
unraveled
Joined: 07 Mar 2019
Last visit: 10 Apr 2025
Posts: 2,706
Own Kudos:
2,328
 [1]
Given Kudos: 763
Location: India
WE:Sales (Energy)
Posts: 2,706
Kudos: 2,328
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
N workers can finish a job in 15 days. After working 5 days, additional 8 workers joined them. Together, they finished remaining job in 6 days. What is the value of n?

A. 15
B. 18
C. 24
D. 12
E. 9

We know that it takes 15 days to complete the work. Now that 5 days work is done we now have \(\frac{1}{3}\) work done since \(\frac{5}{15}\) and left with \(1 - \frac{1}{3} = \frac{2}{3}\) work to be done by N + 8 workers in 6 days.
Now, the fraction of number of persons who worked initially(N) and numbers of persons who worked later(N+8) would be equal to the ratio of work left to be done and work done in 6 days(6 units). Here the assumption is that rate of work done by individual is same foe each worker.
Thus,
\(\frac{N}{N+8} = \frac{6}{10}\)
10N = 6N + 48
N = 12

Answer D.­