Last visit was: 24 Apr 2026, 09:46 It is currently 24 Apr 2026, 09:46
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 24 Apr 2026
Posts: 109,814
Own Kudos:
811,030
 [6]
Given Kudos: 105,871
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,814
Kudos: 811,030
 [6]
Kudos
Add Kudos
6
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 24 Apr 2026
Posts: 109,814
Own Kudos:
Given Kudos: 105,871
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,814
Kudos: 811,030
Kudos
Add Kudos
Bookmarks
Bookmark this Post
General Discussion
User avatar
obedear
Joined: 05 Sep 2024
Last visit: 23 Apr 2026
Posts: 61
Own Kudos:
39
 [2]
Given Kudos: 11
Products:
Posts: 61
Kudos: 39
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Dereno
Joined: 22 May 2020
Last visit: 24 Apr 2026
Posts: 1,398
Own Kudos:
1,374
 [2]
Given Kudos: 425
Products:
Posts: 1,398
Kudos: 1,374
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Bunuel
A contractor was hired to complete a certain construction job in 80 days. To meet this deadline, the contractor initially assigns 120 men, each working 10 hours per day at a constant rate. After 40 days with these 120 men, an inspection shows that only 3/8 of the job has been completed. At that point, how many additional men, working at the same rate and for 10 hours per day, must be hired to finish the job on time?

(A) 50
(B) 60
(C) 70
(D) 80
(E) 90

Experience GMAT Club Test Questions
Yes, you've landed on a GMAT Club Tests question
Craving more? Unlock our full suite of GMAT Club Tests here
Want to experience more? Get a taste of our tests with our free trial today
Rise to the challenge with GMAT Club Tests. Happy practicing!
The question mentions a deadline date was fixed before starting the work.

So, to meet the deadline. The contractor assigns 120 men, each working for 10 hours per day, at a constant rate.

So after 40 days, the inspection of work is done.

120 * 40 * 10 * rate = (3/8) of the total job.

Total job = (8*120*40*10)/3 = 128000.

So we need to complete the work on time, which means the number of days left is 80-40 = 40 days.

With this rate , we can finish another (3/8) of the work. So, we hire additional workforce. Let that be w.

(120+w) * 40 * 10 = (5/8)* (128000)

(120+w) * 40 * 10 = 80,000

120+W = 200

w = 80

so, additional work force needed is 80.

Option D
User avatar
rajatsahu
Joined: 21 Jan 2026
Last visit: 02 Apr 2026
Posts: 1
Own Kudos:
1
 [1]
Given Kudos: 8
Posts: 1
Kudos: 1
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Work done in the first 40 days
Men = 120
Hours/day = 10
Days worked = 40
Total man-hours used so far: 120×10×40=48,000 (This completes 3/8 of the job)

If 48,000 man-hours = 3/8 of the job, then total work is: 48,000×8/3=128,000 man-hours
Work left = 128,000−48,000=80,000 man-hours
Time remaining = 80-40 days = 40 days

Each man works: 10×40=400 hours
So required number of men:80,000 / 400= 200 men

We already have 120 men , so required men: 200 - 120 = 80 men (option D)
Moderators:
Math Expert
109814 posts
Tuck School Moderator
853 posts