Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.
Customized for You
we will pick new questions that match your level based on your Timer History
Track Your Progress
every week, we’ll send you an estimated GMAT score based on your performance
Practice Pays
we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Thank you for using the timer!
We noticed you are actually not timing your practice. Click the START button first next time you use the timer.
There are many benefits to timing your practice, including:
Still interested in this question? Check out the "Best Topics" block below for a better discussion on this exact question, as well as several more related questions.
Let total work be W Then work done by one machine in one day = W/(12X6)
Let n machines be required for 8 days total work done = W/(12X6) X n X 8 which should be again W hence n = 9 so 3 more machines are required to complete the the work in 8 days.
Alternatively:
W is directly proportional to number of machines and number of days
thus 12X 6 = n X 8 implies n=9 thus 3 more are required.
Archived Topic
Hi there,
This topic has been closed and archived due to inactivity or violation of community quality standards. No more replies are possible here.
Still interested in this question? Check out the "Best Topics" block above for a better discussion on this exact question, as well as several more related questions.