Last visit was: 27 Apr 2026, 10:44 It is currently 27 Apr 2026, 10:44
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bismuth83
User avatar
DI Forum Moderator
Joined: 15 Sep 2024
Last visit: 01 Aug 2025
Posts: 714
Own Kudos:
3,155
 [16]
Given Kudos: 441
Expert
Expert reply
Posts: 714
Kudos: 3,155
 [16]
Kudos
Add Kudos
16
Bookmarks
Bookmark this Post
User avatar
Yxy
Joined: 31 Oct 2024
Last visit: 03 Nov 2024
Posts: 1
Own Kudos:
1
 [1]
Given Kudos: 2
Posts: 1
Kudos: 1
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
crimson_king
Joined: 21 Dec 2023
Last visit: 25 Apr 2026
Posts: 152
Own Kudos:
Given Kudos: 113
GRE 1: Q170 V170
GRE 1: Q170 V170
Posts: 152
Kudos: 156
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
poojaarora1818
Joined: 30 Jul 2019
Last visit: 27 Apr 2026
Posts: 1,625
Own Kudos:
Given Kudos: 3,821
Location: India
Concentration: General Management, Economics
GPA: 3
WE:Human Resources (Real Estate)
Products:
Kudos
Add Kudos
Bookmarks
Bookmark this Post
If x is the slower worker of the two workers, how can X be 20 and Y be 40? The slower one should take more days to complete a task.

Can you please walk us through the solution?
Bismuth83
It takes 5 days, 10 days, 20 days, 40 days, and 50 days respectively for workers A, B, C, D, and E to complete the same work independently. The employer wants the work to be inspected within one day of completion. Further, the employer can employ exactly two of these five workers, and due to certain administrative restrictions, the employer mandates that the work takes at least 10 days but not more than 14 days. X is the slower worker of the two workers selected, and Y is the other worker. Select an option for X and an option for Y that are jointly consistent with the information provided. Make only two selections, one in each column.
User avatar
Bismuth83
User avatar
DI Forum Moderator
Joined: 15 Sep 2024
Last visit: 01 Aug 2025
Posts: 714
Own Kudos:
Given Kudos: 441
Expert
Expert reply
Posts: 714
Kudos: 3,155
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Yxy
The slower worker should be the one with greater days to complete the work, so the given answer should be reversed
Correct! I reversed the order of the answers
User avatar
Bismuth83
User avatar
DI Forum Moderator
Joined: 15 Sep 2024
Last visit: 01 Aug 2025
Posts: 714
Own Kudos:
3,155
 [4]
Given Kudos: 441
Expert
Expert reply
Posts: 714
Kudos: 3,155
 [4]
3
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
poojaarora1818
If x is the slower worker of the two workers, how can X be 20 and Y be 40? The slower one should take more days to complete a task.

Can you please walk us through the solution?
Bismuth83
It takes 5 days, 10 days, 20 days, 40 days, and 50 days respectively for workers A, B, C, D, and E to complete the same work independently. The employer wants the work to be inspected within one day of completion. Further, the employer can employ exactly two of these five workers, and due to certain administrative restrictions, the employer mandates that the work takes at least 10 days but not more than 14 days. X is the slower worker of the two workers selected, and Y is the other worker. Select an option for X and an option for Y that are jointly consistent with the information provided. Make only two selections, one in each column.
Sure thing! I fixed the answers and reversed them. Let me walk you through the solution.

1. There are 5 workers with different speeds. We need to find a combination of 2 workers that will do the work in 10 to 14 days.

2. Let the amount of work be equal to 1. Then the worker speeds for A, B, C, D, and E are \(\frac{1}{5}\), \(\frac{1}{10}\), \(\frac{1}{20}\), \(\frac{1}{40}\), and \(\frac{1}{50}\).

3. That means our question can be rewritten. We need to find X and Y such that the value of t in this equation is between 10 and 14: \(t(X_{speed} + Y_{speed}) = 1\). Now, we can look at the extremes.

4. Workers A or B won’t work, since they can do all the work by themselves in 10 days or less. C, D and E are left.

5. For the combination D and E we have: \(t(\frac{1}{40} + \frac{1}{50}) = 1 \rightarrow t = \frac{1}{\frac{1}{40} + \frac{1}{50}} > \frac{1}{\frac{1}{40} + \frac{1}{40}} = \frac{1}{\frac{1}{20}} = 20\). This doesn’t work since t must be between 10 and 14.

6. We are left with 2 combinations - C+D and C+E. Since we know that C must be there, we can say that both combinations take more than 10 days and Y must be C. This is because \(10 * (\frac{1}{20} + \frac{1}{20}) = 1\) and replacing one 1/20 with something less would make t larger.

7. Because there is only one answer, the combination that takes less time should work and that’s C+D. However, let’s double-check just in case:
\(t(\frac{1}{20} + \frac{1}{40}) = 1 \rightarrow t = \frac{1}{\frac{1}{20} + \frac{1}{40}} = \frac{1}{\frac{3}{40}} = \frac{40}{3} < \frac{42}{3} = 14\) and \(t(\frac{1}{20} + \frac{1}{50}) = 1 \rightarrow t = \frac{1}{\frac{1}{20} + \frac{1}{50}} = \frac{1}{\frac{7}{100}} = \frac{100}{7} > \frac{98}{7} = 14\).

8. So, our answer is X = D and Y = C.
User avatar
poojaarora1818
Joined: 30 Jul 2019
Last visit: 27 Apr 2026
Posts: 1,625
Own Kudos:
Given Kudos: 3,821
Location: India
Concentration: General Management, Economics
GPA: 3
WE:Human Resources (Real Estate)
Products:
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bismuth83
poojaarora1818
If x is the slower worker of the two workers, how can X be 20 and Y be 40? The slower one should take more days to complete a task.

Can you please walk us through the solution?
Bismuth83
It takes 5 days, 10 days, 20 days, 40 days, and 50 days respectively for workers A, B, C, D, and E to complete the same work independently. The employer wants the work to be inspected within one day of completion. Further, the employer can employ exactly two of these five workers, and due to certain administrative restrictions, the employer mandates that the work takes at least 10 days but not more than 14 days. X is the slower worker of the two workers selected, and Y is the other worker. Select an option for X and an option for Y that are jointly consistent with the information provided. Make only two selections, one in each column.
Sure thing! I fixed the answers and reversed them. Let me walk you through the solution.

1. There are 5 workers with different speeds. We need to find a combination of 2 workers that will do the work in 10 to 14 days.

2. Let the amount of work be equal to 1. Then the worker speeds for A, B, C, D, and E are \(\frac{1}{5}\), \(\frac{1}{10}\), \(\frac{1}{20}\), \(\frac{1}{40}\), and \(\frac{1}{50}\).

3. That means our question can be rewritten. We need to find X and Y such that the value of t in this equation is between 10 and 14: \(t(X_{speed} + Y_{speed}) = 1\). Now, we can look at the extremes.

4. Workers A or B won’t work, since they can do all the work by themselves in 10 days or less. C, D and E are left.

5. For the combination D and E we have: \(t(\frac{1}{40} + \frac{1}{50}) = 1 \rightarrow t = \frac{1}{\frac{1}{40} + \frac{1}{50}} > \frac{1}{\frac{1}{40} + \frac{1}{40}} = \frac{1}{\frac{1}{20}} = 20\). This doesn’t work since t must be between 10 and 14.

6. We are left with 2 combinations - C+D and C+E. Since we know that C must be there, we can say that both combinations take more than 10 days and Y must be C. This is because \(10 * (\frac{1}{20} + \frac{1}{20}) = 1\) and replacing one 1/20 with something less would make t larger.

7. Because there is only one answer, the combination that takes less time should work and that’s C+D. However, let’s double-check just in case:
\(t(\frac{1}{20} + \frac{1}{40}) = 1 \rightarrow t = \frac{1}{\frac{1}{20} + \frac{1}{40}} = \frac{1}{\frac{3}{40}} = \frac{40}{3} < \frac{42}{3} = 14\) and \(t(\frac{1}{20} + \frac{1}{50}) = 1 \rightarrow t = \frac{1}{\frac{1}{20} + \frac{1}{50}} = \frac{1}{\frac{7}{100}} = \frac{100}{7} > \frac{98}{7} = 14\).

8. So, our answer is X = D and Y = C.
Thank you so much for the detailed solution. Awesome!
User avatar
Yangyixi
Joined: 25 Jan 2024
Last visit: 05 Jan 2025
Posts: 6
Given Kudos: 2
Posts: 6
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
why is it not possible to combine A with somebody who is not B?
Bismuth83
poojaarora1818
If x is the slower worker of the two workers, how can X be 20 and Y be 40? The slower one should take more days to complete a task.

Can you please walk us through the solution?
Bismuth83
It takes 5 days, 10 days, 20 days, 40 days, and 50 days respectively for workers A, B, C, D, and E to complete the same work independently. The employer wants the work to be inspected within one day of completion. Further, the employer can employ exactly two of these five workers, and due to certain administrative restrictions, the employer mandates that the work takes at least 10 days but not more than 14 days. X is the slower worker of the two workers selected, and Y is the other worker. Select an option for X and an option for Y that are jointly consistent with the information provided. Make only two selections, one in each column.
Sure thing! I fixed the answers and reversed them. Let me walk you through the solution.

1. There are 5 workers with different speeds. We need to find a combination of 2 workers that will do the work in 10 to 14 days.

2. Let the amount of work be equal to 1. Then the worker speeds for A, B, C, D, and E are \(\frac{1}{5}\), \(\frac{1}{10}\), \(\frac{1}{20}\), \(\frac{1}{40}\), and \(\frac{1}{50}\).

3. That means our question can be rewritten. We need to find X and Y such that the value of t in this equation is between 10 and 14: \(t(X_{speed} + Y_{speed}) = 1\). Now, we can look at the extremes.

4. Workers A or B won’t work, since they can do all the work by themselves in 10 days or less. C, D and E are left.

5. For the combination D and E we have: \(t(\frac{1}{40} + \frac{1}{50}) = 1 \rightarrow t = \frac{1}{\frac{1}{40} + \frac{1}{50}} > \frac{1}{\frac{1}{40} + \frac{1}{40}} = \frac{1}{\frac{1}{20}} = 20\). This doesn’t work since t must be between 10 and 14.

6. We are left with 2 combinations - C+D and C+E. Since we know that C must be there, we can say that both combinations take more than 10 days and Y must be C. This is because \(10 * (\frac{1}{20} + \frac{1}{20}) = 1\) and replacing one 1/20 with something less would make t larger.

7. Because there is only one answer, the combination that takes less time should work and that’s C+D. However, let’s double-check just in case:
\(t(\frac{1}{20} + \frac{1}{40}) = 1 \rightarrow t = \frac{1}{\frac{1}{20} + \frac{1}{40}} = \frac{1}{\frac{3}{40}} = \frac{40}{3} < \frac{42}{3} = 14\) and \(t(\frac{1}{20} + \frac{1}{50}) = 1 \rightarrow t = \frac{1}{\frac{1}{20} + \frac{1}{50}} = \frac{1}{\frac{7}{100}} = \frac{100}{7} > \frac{98}{7} = 14\).

8. So, our answer is X = D and Y = C.
User avatar
Bismuth83
User avatar
DI Forum Moderator
Joined: 15 Sep 2024
Last visit: 01 Aug 2025
Posts: 714
Own Kudos:
3,155
 [1]
Given Kudos: 441
Expert
Expert reply
Posts: 714
Kudos: 3,155
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Yangyixi
why is it not possible to combine A with somebody who is not B?
If A worked with anyone it would take less time than if A worked alone.

A has a speed of \(\frac{1}{5}\). In 5 days, A would complete the work alone, which is less 10. Thus, working with anyone else would take even less and that doesn't work.

I hope that answered your question!
User avatar
Yangyixi
Joined: 25 Jan 2024
Last visit: 05 Jan 2025
Posts: 6
Given Kudos: 2
Posts: 6
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
You did, thank you !
Bismuth83
Yangyixi
why is it not possible to combine A with somebody who is not B?
If A worked with anyone it would take less time than if A worked alone.

A has a speed of \(\frac{1}{5}\). In 5 days, A would complete the work alone, which is less 10. Thus, working with anyone else would take even less and that doesn't work.

I hope that answered your question!
User avatar
Ashok2530
Joined: 20 Apr 2025
Last visit: 07 Jul 2025
Posts: 1
Own Kudos:
1
 [1]
Posts: 1
Kudos: 1
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
A=5 Days
B=10 Days
C=20Days
D=40 Days
E=50 Days

Total Units of Work = 200 Units

C= 200/20 = 10 Units/Day
D= 200/40 = 5 Units/Day

C+ D = 15 Units/Day

200/15 = 40/3 days which is greater than 10 days and less than 14 days.
User avatar
ag821
Joined: 06 Jun 2021
Last visit: 27 Apr 2026
Posts: 21
Own Kudos:
Given Kudos: 39
Location: India
Concentration: Entrepreneurship, Technology
GPA: 3.9
WE:Other (Other)
Products:
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Not sure if this is right, but I did it this way -
x < y

In 10 days, each does how much work -
A : 1/5*10 = 2 units
B : 1/10*10 = 1 unit
C : 1/20* 10 = 0.5 unit
D : 1/40*10 = 0.4 unit
E : 1/ 50 * 10 = 0.2 unit

Since we have to make 1 unit of work jointly in min 10 days and max 14 days, C & D is the best combination because they finish 0.9 unit of work in 10 days, and in less than 14 days, they will finish the other 0.1 unit of remaining work.

D & E combination won't make sense because in 10 days they finish only 0.6 unit of work, and the remaining work of 0.4 is still left, and by the 15th day they would have jointly completed only 0.9 unit of work (0.2 of D and 0.1 of E), which is more than 14 days & the job is still not complete.

Hence x = 0.4 i.e. D and y = 0.5 i.e. C

Used this method to solve within 2 mins
User avatar
Hrley
Joined: 04 Aug 2025
Last visit: 18 Dec 2025
Posts: 15
Own Kudos:
Given Kudos: 1
GMAT Focus 1: 625 Q86 V78 DI79
GMAT Focus 1: 625 Q86 V78 DI79
Posts: 15
Kudos: 3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I did this question correctly in a bit over 3min, and I used somewhat of a cheeky way for this...

If X is slower than Y, and the time that both need to work is from 10 to 14 days, then:
1/14 <= (1/X + 1/Y) <= 1/10
Or,
0.0714 <= (1/X + 1/Y) <= 0.1

Then I converted all the workers' rates into decimals.
I can use a calculator in DI so this can be done quickly.
1/A = 0.2, 1/B = 0.1, 1/C = 0.05, 1/D = 0.025, 1/E = 0.02

It's D and C, bc their rate total falls between 0.0714 and 0.1. And in that order since D is obviously slower than C, according to their rates.
If I did not round 1/14 correctly, I would have seriously been confused between D/C or D/E.
User avatar
quamquia
Joined: 01 Sep 2025
Last visit: 30 Dec 2025
Posts: 1
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
For easier calculations and approximation i took lcm of days 5, 10 and rest which was 200. I now equated 200 as the work , from rate time concept . For individual rates i divided work by time of all for eg A took 5 days to complete work so 200/ 5 i.e 40 units of work a day. Aim is to complete 200 units of work in more than 10 but less than 14 days , so directly add units of work and divide by 200 . Here C ,D have 15 units of combined rate . 200 /15 gives 13 something days which is what we want hence is the answer.
Bismuth83
It takes 5 days, 10 days, 20 days, 40 days, and 50 days respectively for workers A, B, C, D, and E to complete the same work independently. The employer wants the work to be inspected within one day of completion. Further, the employer can employ exactly two of these five workers, and due to certain administrative restrictions, the employer mandates that the work takes at least 10 days but not more than 14 days. X is the slower worker of the two workers selected, and Y is the other worker. Select an option for X and an option for Y that are jointly consistent with the information provided. Make only two selections, one in each column.
Moderators:
Math Expert
109928 posts
498 posts
212 posts