Dillesh4096
Working alone, B needs 50% more time to complete a certain job than A does. A and B completes the same job in 15 days in the following manner: A works alone till half the job is done, then A and B work together for 2 days, and finally B works alone to complete the remaining 10% of the job. In how many days can B alone complete the entire job ?
A. 16
B. 20
C. 24
D. 30
E. 36
So, we know that B takes 50% more time..
If A does it in A days, B will take 1.5A days...A and B completes the same job in 15 days in the following manner:
1) A works alone till half the job is done,......
so time taken is \(\frac{A}{2}\)
2) then A and B work together for 2 days,.....
so time taken is 2 days3) and finally B works alone to complete the remaining 10% of the job, .....
as B days for 100%, so \(\frac{B}{10}\)days =\(\frac{1.5A}{10}\)
Adding all three \(\frac{A}{2}+2+\frac{1.5A}{10}=15......\frac{6.5A}{10}=15-2=13....A=\frac{13*10}{6.5}=20\).
A is 20, and, thus, B becomes 1.5*20=30.
D