A, B and C can do a piece of work in 11 days, 20 and 55 days, respectively, working alone. How soon can the work be done if A is assisted by B and C on alternate days?
Let' s use LCM method is solve this work related problem.
Assume that total work = LCM (11,20,55) = 220 units
Calculating the per day work:Amount of work done by A in one day = 220/11 = 20 units
Similarly , B in one day = 220/20 = 11 units
C in one day = 220/55 = 4 units
How soon can the work be done if A is assisted by B and C on alternate days?
A will be working everyday and (B and C ) will join A on every alternate days i.e 2 nd day, fourth day...
Per day work of A = 20 units
Per day work of B and C = 11 + 4 = 15 units
First day : A will complete 20 units
Second day: A,B and C together will complete 20+11+4 = 35 units
That means (20 + 35) = 55 units are completed in every 2 days.
Total work to complete = 220 units
Since 55 units are completed in 2 days , (55* 4) = 220 units will be completed in 2*4 = 8 days
Option B is the answer.Thanks,