Last visit was: 09 Jul 2025, 00:21 It is currently 09 Jul 2025, 00:21
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
SVaidyaraman
Joined: 17 Dec 2012
Last visit: 05 Jul 2025
Posts: 577
Own Kudos:
1,740
 [34]
Given Kudos: 20
Location: India
Expert
Expert reply
Posts: 577
Kudos: 1,740
 [34]
3
Kudos
Add Kudos
31
Bookmarks
Bookmark this Post
Most Helpful Reply
avatar
GSBae
Joined: 23 May 2013
Last visit: 07 Mar 2025
Posts: 167
Own Kudos:
443
 [6]
Given Kudos: 42
Location: United States
Concentration: Technology, Healthcare
GMAT 1: 760 Q49 V45
GPA: 3.5
GMAT 1: 760 Q49 V45
Posts: 167
Kudos: 443
 [6]
3
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
General Discussion
User avatar
manpreetsingh86
Joined: 13 Jun 2013
Last visit: 19 Dec 2022
Posts: 219
Own Kudos:
1,147
 [2]
Given Kudos: 14
Posts: 219
Kudos: 1,147
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Vetrik
Joined: 04 Jul 2014
Last visit: 05 Jan 2022
Posts: 37
Own Kudos:
85
 [2]
Given Kudos: 40
Schools: Smeal" 20
Schools: Smeal" 20
Posts: 37
Kudos: 85
 [2]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
SravnaTestPrep
A, B and C work on a task. To complete the task alone, B takes twice the time that A would take to complete the task alone and 2/3rd the time that C would take to complete the task alone. If B actually worked for half the number of days that A worked and 3/2 times the number of days that C worked, what proportion of the total work was completed by B?

A. 1/3
B. 2/9
C. 9/49
D. 7/19
E. 1/6

The first thing to notice is that A is faster than B and B is faster than C.

Since work is proportional to time, in 1 day lets say if A does 2 works, B does 1 work and C does 2/3rd of a work.

If A works for 2 days, B works for 1 day and C works for only 2/3 of the day.

Therefore total work done = (2*2) + (1*1) + (2/3*2/3) = 49/9

Proportion of work done by B = (1*1) / (49/9) = 9/49

Hence Answer C.
--------------------------------

Kudos please, if this post helps.
avatar
Kezia9
Joined: 04 Oct 2017
Last visit: 23 Mar 2019
Posts: 55
Own Kudos:
Given Kudos: 467
Posts: 55
Kudos: 23
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Vetrik
SravnaTestPrep
A, B and C work on a task. To complete the task alone, B takes twice the time that A would take to complete the task alone and 2/3rd the time that C would take to complete the task alone. If B actually worked for half the number of days that A worked and 3/2 times the number of days that C worked, what proportion of the total work was completed by B?

A. 1/3
B. 2/9
C. 9/49
D. 7/19
E. 1/6

The first thing to notice is that A is faster than B and B is faster than C.

Since work is proportional to time, in 1 day lets say if A does 2 works, B does 1 work and C does 2/3rd of a work.

If A works for 2 days, B works for 1 day and C works for only 2/3 of the day.

Therefore total work done = (2*2) + (1*1) + (2/3*2/3) = 49/9

Proportion of work done by B = (1*1) / (49/9) = 9/49

Hence Answer C.
--------------------------------

Kudos please, if this post helps.

How did you arrive at ...C does 2/3 of the work??? I did not understand ...B works for 3/2 times the number of days C worked???
avatar
DarkMatter00000
Joined: 23 Feb 2018
Last visit: 10 Nov 2018
Posts: 1
Own Kudos:
1
 [1]
Given Kudos: 1
Posts: 1
Kudos: 1
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Kezia9
Vetrik
SravnaTestPrep
A, B and C work on a task. To complete the task alone, B takes twice the time that A would take to complete the task alone and 2/3rd the time that C would take to complete the task alone. If B actually worked for half the number of days that A worked and 3/2 times the number of days that C worked, what proportion of the total work was completed by B?

A. 1/3
B. 2/9
C. 9/49
D. 7/19
E. 1/6

The first thing to notice is that A is faster than B and B is faster than C.

Since work is proportional to time, in 1 day lets say if A does 2 works, B does 1 work and C does 2/3rd of a work.

If A works for 2 days, B works for 1 day and C works for only 2/3 of the day.

Therefore total work done = (2*2) + (1*1) + (2/3*2/3) = 49/9

Proportion of work done by B = (1*1) / (49/9) = 9/49

Hence Answer C.
--------------------------------

Kudos please, if this post helps.

How did you arrive at ...C does 2/3 of the work??? I did not understand ...B works for 3/2 times the number of days C worked???

We can use ratios to understand it better-
Given that B worked half the number of days that A worked,implies: B= (1/2)*A
Or, A/B = 2/1 (Here it means that when A works for 2 days,B works for a day).

Now, relating B and C: B works 3/2 times C.
Or, B= (3/2)*C
B/C = 3/2.
This can be rewritten as : B/C = 1/(2/3) {In other words, when B works for a day, C works for 2/3 day}



Sent from my iPhone using GMAT Club Forum mobile app
User avatar
HouseStark
Joined: 06 Oct 2019
Last visit: 22 Jan 2021
Posts: 98
Own Kudos:
238
 [1]
Given Kudos: 90
Status:BELIEVE IN YOURSELF
Location: India
Posts: 98
Kudos: 238
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
SravnaTestPrep
A, B and C work on a task. To complete the task alone, B takes twice the time that A would take to complete the task alone and 2/3rd the time that C would take to complete the task alone. If B actually worked for half the number of days that A worked and 3/2 times the number of days that C worked, what proportion of the total work was completed by B?

A. 1/3
B. 2/9
C. 9/49
D. 7/19
E. 1/6

Quote:
To complete the task alone, B takes twice the time that A would take to complete the task alone and 2/3rd the time that C would take to complete the task alone
A=A
B=2A
B=\(\frac{2}{3}\)C

Put the value of B here, so that we can get everything in term A
so, C=3A

Quote:
B actually worked for half the number of days that A worked and 3/2 times the number of days that C worked

A=x
B=\(\frac{1}{2}\)x
B=\(\frac{3}{2}\)C

In this also we put value of B so that we can get everything in term of x
C=\(\frac{1}{3}\)x

Now for suppose the x=6.
A=6
B=3
C=2

Let,total work =1

work is done by A, \(\frac{1}{A}\)=\(\frac{W(A)}{6}\)= W(A)=\(\frac{6}{A}\)

work is done by B, \(\frac{1}{2A}\)=\(\frac{W(B)}{3}\)= W(B)=\(\frac{3}{2A}\)

work is done by C, \(\frac{1}{3A}\)=\(\frac{W(C)}{2}\)= W(C)=\(\frac{2}{3A}\)

now the proportion of the total work was completed by B

\(\frac{(3|2A)}{(6/A)+(3/2A)+(2/3A)}\)
=\(\frac{9A}{49A}\)
=9/49

IMO C

:cool: :cool: :cool: :cool:
avatar
Rachit4126
Joined: 14 Jul 2019
Last visit: 28 Sep 2021
Posts: 35
Own Kudos:
Given Kudos: 72
Location: India
Schools: IMD '21
Schools: IMD '21
Posts: 35
Kudos: 17
Kudos
Add Kudos
Bookmarks
Bookmark this Post
HouseStark
SravnaTestPrep
A, B and C work on a task. To complete the task alone, B takes twice the time that A would take to complete the task alone and 2/3rd the time that C would take to complete the task alone. If B actually worked for half the number of days that A worked and 3/2 times the number of days that C worked, what proportion of the total work was completed by B?

A. 1/3
B. 2/9
C. 9/49
D. 7/19
E. 1/6

Quote:
To complete the task alone, B takes twice the time that A would take to complete the task alone and 2/3rd the time that C would take to complete the task alone
A=A
B=2A
B=\(\frac{2}{3}\)C

Can you check and confirm: Both your assumptions are time variables: A=A is Time; A=x is also time. You have then multiplied timextime to calculate work!
Am i missing something here?

Put the value of B here, so that we can get everything in term A
so, C=3A

Quote:
B actually worked for half the number of days that A worked and 3/2 times the number of days that C worked

A=x
B=\(\frac{1}{2}\)x
B=\(\frac{3}{2}\)C

In this also we put value of B so that we can get everything in term of x
C=\(\frac{1}{3}\)x

Now for suppose the x=6.
A=6
B=3
C=2

now the proportion of the total work was completed by B

\(\frac{3*3A}{6*6A+3*3A+2*2A}\)
=\(\frac{9A}{49A}\)
=9/49

IMO C

:cool: :cool: :cool: :cool:
User avatar
HouseStark
Joined: 06 Oct 2019
Last visit: 22 Jan 2021
Posts: 98
Own Kudos:
Given Kudos: 90
Status:BELIEVE IN YOURSELF
Location: India
Posts: 98
Kudos: 238
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Quote:
Can you check and confirm: Both your assumptions are time variables: A=A is Time; A=x is also time. You have then multiplied timextime to calculate work!
Am I missing something here?

yes, I have done it wrong on the last part calculating the proportion of the total work completed by B.


Thanks, Rachit4126 now, I have corrected it.
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 37,360
Own Kudos:
Posts: 37,360
Kudos: 1,010
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
Moderators:
Math Expert
102597 posts
PS Forum Moderator
679 posts