GMAT Question of the Day - Daily to your Mailbox; hard ones only

It is currently 17 Nov 2018, 13:36

Gmatbusters' Weekly Quant Quiz

Join here 


Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel
Events & Promotions in November
PrevNext
SuMoTuWeThFrSa
28293031123
45678910
11121314151617
18192021222324
2526272829301
Open Detailed Calendar
  • FREE Quant Workshop by e-GMAT!

     November 18, 2018

     November 18, 2018

     07:00 AM PST

     09:00 AM PST

    Get personalized insights on how to achieve your Target Quant Score. November 18th, 7 AM PST
  • How to QUICKLY Solve GMAT Questions - GMAT Club Chat

     November 20, 2018

     November 20, 2018

     09:00 AM PST

     10:00 AM PST

    The reward for signing up with the registration form and attending the chat is: 6 free examPAL quizzes to practice your new skills after the chat.

A contractor undertakes to do a job within 100 days and hires 10 peopl

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

Manager
Manager
avatar
G
Joined: 31 Jul 2017
Posts: 138
Location: Tajikistan
Concentration: Finance, Economics
Schools: Booth '21, CBS '21
GMAT 1: 690 Q48 V35
GRE 1: Q164 V162
GPA: 3.85
WE: Accounting (Investment Banking)
Premium Member
Re: A contractor undertakes to do a job within 100 days and hires 10 peopl  [#permalink]

Show Tags

New post 14 Sep 2018, 05:13
1
A contractor undertakes to do a job within 100 days and hires 10 people to do it. After 20 days, he realizes that one fourth of the work is done so he fires 2 people. In how many more days will the work get over?
(A) 60
(B) 70
(C) 75
(D) 80
(E) 100


A,D,E are out for obvious reasons. Now, we are left with B and C. If contractor doesn't fire any worker, then it will take them 60 days, but since he is firing 2 workers (or 20%), the work will be slowed down by 20% as well. So 60 days is 80%, 75 days is 100%
Intern
Intern
avatar
B
Joined: 26 Jul 2017
Posts: 5
Location: Pakistan
Concentration: Strategy, Organizational Behavior
GPA: 2.25
WE: Consulting (Consulting)
Re: A contractor undertakes to do a job within 100 days and hires 10 peopl  [#permalink]

Show Tags

New post 16 Sep 2018, 10:21
We can also use the percentage method if someone is comfortable with it.

So we know that 25% (one fourth) work is done in 20 days. Which means that 1.25% work is done in a day. And .125% work was done by 1 person (since there were 10 people ). Now we have 8 people and not 10 so the total work done in a day will be .125%*8 = 1%. We know that since 3/4 work is done which is 75% and 1% work is done on daily basis it will take 75 more days. Hence Answer is (c)
Intern
Intern
avatar
B
Joined: 26 Jul 2017
Posts: 5
Location: Pakistan
Concentration: Strategy, Organizational Behavior
GPA: 2.25
WE: Consulting (Consulting)
Re: A contractor undertakes to do a job within 100 days and hires 10 peopl  [#permalink]

Show Tags

New post 16 Sep 2018, 10:22
We can also use the percentage method if someone is comfortable with it.

So we know that 25% (one fourth) work is done in 20 days. Which means that 1.25% work is done in a day. And .125% work was done by 1 person (since there were 10 people ). Now we have 8 people and not 10 so the total work done in a day will be .125%*8 = 1%. We know that since 3/4 work is done which is 75% and 1% work is done on daily basis it will take 75 more days. Hence Answer is (c)
GMAT Club Bot
Re: A contractor undertakes to do a job within 100 days and hires 10 peopl &nbs [#permalink] 16 Sep 2018, 10:22

Go to page   Previous    1   2   [ 23 posts ] 

Display posts from previous: Sort by

A contractor undertakes to do a job within 100 days and hires 10 peopl

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  


Copyright

GMAT Club MBA Forum Home| About| Terms and Conditions and Privacy Policy| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.