Last visit was: 14 Jul 2024, 09:43 It is currently 14 Jul 2024, 09:43
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Manager
Manager
Joined: 13 Jun 2012
Posts: 166
Own Kudos [?]: 505 [14]
Given Kudos: 467
Location: United States
WE:Supply Chain Management (Computer Hardware)
Send PM
Most Helpful Reply
Tutor
Joined: 16 Oct 2010
Posts: 15108
Own Kudos [?]: 66626 [8]
Given Kudos: 436
Location: Pune, India
Send PM
General Discussion
Manager
Manager
Joined: 13 Jun 2012
Posts: 166
Own Kudos [?]: 505 [0]
Given Kudos: 467
Location: United States
WE:Supply Chain Management (Computer Hardware)
Send PM
Manager
Manager
Joined: 20 Feb 2017
Posts: 75
Own Kudos [?]: 103 [1]
Given Kudos: 84
Location: United States
Send PM
Re: A contractor undertakes to do a job within 20 days and hires 60 [#permalink]
1
Kudos
Turkish wrote:
What am I doing wrong

60 men *20 days= Total number of work 1200
Now after 5 days the amount of work that should be done was 5*60=300 but one fifth of the work was done ie 1200*1/5= 240
which means he still has= 960 amount of work
Let X be the number of men, So (60+x)15=960.. which is 4.


You are missing that initial estimation of contractor was wrong.

60 people were able to complete only 1/5 of work in 5 days. So For person, it is 1500 days work not 1200.

Hope it helps.

Sent from my SM-G955F using GMAT Club Forum mobile app
VP
VP
Joined: 07 Dec 2014
Posts: 1068
Own Kudos [?]: 1606 [0]
Given Kudos: 27
Send PM
A contractor undertakes to do a job within 20 days and hires 60 [#permalink]
Turkish wrote:
A contractor undertakes to do a job within 20 days and hires 60 people to do it. After 5 days, he realizes that one fifth of the work is done so he hires more people. How many more man he has to hire to complete the job in time?

1. 10
2. 12
3. 15
4. 20
5. 25


let 1/x=rate of one man for one day
60*1/x*5 days=1/5 of work
x=1500 days
let y=total men needed to finish job on time
y*1/1500*15 days=4/5 of work
y=80 men
80-60=20 more men needed
D
User avatar
Intern
Intern
Joined: 07 Mar 2022
Posts: 1
Own Kudos [?]: 1 [1]
Given Kudos: 0
Send PM
Re: A contractor undertakes to do a job within 20 days and hires 60 [#permalink]
1
Kudos
A contractor undertakes to do a job within 20 days and hires 60 people to do it. After 5 days, he realizes that one fifth of the work is done so he hires more people. How many more man he has to hire to complete the job in time?


By using the Unitary method
60 people, in 5 days can complete 1/5 part of the work
60 people, in 1 day can complete (1/5) /5 part of the work
=1/25 part of the work

Work left = 1 - 1/5
= 4/5 part
Again,
1/25 part of the work is completed in 1 day by 60 people
1 part of the work is completed in 1 day by 60 / (1/25) people
4/5 part of the work is completed in 15 days by (60 * 25 * 4)/(15*5)
= 80 people
People required = 80 – 60
= 20 people
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 33966
Own Kudos [?]: 851 [0]
Given Kudos: 0
Send PM
Re: A contractor undertakes to do a job within 20 days and hires 60 [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.