Given: A dye company received an order of 400 litres of black dye and 360 litres of brown dye. It has two machines (X and Y) to make these dyes. X takes 4 hours to make 16 litres of black dye and 3 hours to make 9 litres of brown dye. Y takes 4 hours to make 12 litres of black dye and 3 hours to make 12 litres of brown dye.
Asked: If the company has to deliver the order in 93 hours, its delivery will be delayed by at least
To make 400 litres of black dye, it will take minimum 400*4/16 = 100 hours using machine X.
To make 360 litres of brown dye, it will take minimum 360*3/12 = 90 hours using machine Y.
In 90 hours, machine X & machine Y will produce
360 litres of brown dye & 360 litres of black dye.
Remaining work = 400 -360 = 40 litres of black dye.
Machine X & Machine Y will produce = 16/4 + 12/4 = 4 + 3 = 7 litres of black dye/hour
Time required = 40/7 = 5 5/7 hours
Total time required = 90 + 5 5/7 = 95 5/7 hours
Minimum delay = 95 5/7 - 93 = 2 5/7 hours
IMO D