Last visit was: 19 Nov 2025, 08:16 It is currently 19 Nov 2025, 08:16
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
catinabox
Joined: 27 Nov 2019
Last visit: 18 Nov 2025
Posts: 567
Own Kudos:
588
 [1]
Given Kudos: 223
Location: United States (IL)
GMAT 1: 770 Q50 V44
GPA: 4
Products:
GMAT 1: 770 Q50 V44
Posts: 567
Kudos: 588
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 Nov 2025
Posts: 105,389
Own Kudos:
Given Kudos: 99,977
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,389
Kudos: 778,265
Kudos
Add Kudos
Bookmarks
Bookmark this Post
General Discussion
User avatar
catinabox
Joined: 27 Nov 2019
Last visit: 18 Nov 2025
Posts: 567
Own Kudos:
Given Kudos: 223
Location: United States (IL)
GMAT 1: 770 Q50 V44
GPA: 4
Products:
GMAT 1: 770 Q50 V44
Posts: 567
Kudos: 588
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Keshav1404
Joined: 11 Jun 2022
Last visit: 19 Nov 2025
Posts: 64
Own Kudos:
Given Kudos: 44
GMAT 1: 660 Q48 V32
GMAT 1: 660 Q48 V32
Posts: 64
Kudos: 18
Kudos
Add Kudos
Bookmarks
Bookmark this Post
catinabox
A manufacturing facility has two production lines A and B, that operate at constant but different rates. Line A's output rate is 50% higher than Line B's.

If the total output at the end of an 8-hour shift is 800 boxes, select the possible hourly output rate for each line. Make only one selection in each column.­
­Let R be the hourly output rate of Line B. Line A’s rate is 1.5R.

In an 8-hour shift, the total output is:
  • Line A: 8×1.5R=12R
  • Line B: 8×R=8R
Total output: 12R+8R=20

Given total output is 800 boxes:

20R=800

Solving for R:

R=800/20=40

So:
  • Line A’s hourly output rate: 1.5×40=60 boxes
  • Line B’s hourly output rate: 40 boxes
­
Moderators:
Math Expert
105389 posts