Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.
Customized for You
we will pick new questions that match your level based on your Timer History
Track Your Progress
every week, we’ll send you an estimated GMAT score based on your performance
Practice Pays
we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Thank you for using the timer!
We noticed you are actually not timing your practice. Click the START button first next time you use the timer.
There are many benefits to timing your practice, including:
Be sure to select an answer first to save it in the Error Log before revealing the correct answer (OA)!
Difficulty:
55%
(hard)
Question Stats:
80%
(03:13)
correct 20%
(03:02)
wrong
based on 5
sessions
History
Date
Time
Result
Not Attempted Yet
A project to be carried out over one year has a budget of $40'800, divided into 12 equal allocations for each month. If at the end of the third quarter the project is over budget by $2'400, and assuming that during the last quarter the project will increase its over budget in line with the previous three months, what will the project's final budget be at the end of the year?
-----
A) $42'000
B) $43'200
C) $44'000
D) $45'600
E) $46'200
-----
Find more questions on https://www.gmatwiz.co - Tutor in your pocket Daily questions in your inbox - Progress stats - Study reminders
Still interested in this question? Check out the "Best Topics" block below for a better discussion on this exact question, as well as several more related questions.
A project to be carried out over one year has a budget of $40'800, divided into 12 equal allocations for each month. If at the end of the third quarter the project is over budget by $2'400, and assuming that during the last quarter the project will increase its over budget in line with the previous three months, what will the project's final budget be at the end of the year?
-----
A) $42'000
B) $43'200
C) $44'000
D) $45'600
E) $46'200
-----
Find more questions on https://www.gmatwiz.co - Tutor in your pocket Daily questions in your inbox - Progress stats - Study reminders
A project to be carried out over one year has a budget of $40'800, divided into 12 equal allocations for each month. If at the end of the third quarter the project is over budget by $2'400, and assuming that during the last quarter the project will increase its over budget in line with the previous three months, what will the project's final budget be at the end of the year?
-----
A) $42'000
B) $43'200
C) $44'000
D) $45'600
E) $46'200
-----