If it takes 12 workers working independently 3 hours to make 500 boxes, how many minutes should it take for 16 workers to make 300 boxes?
(A) 60
(B) 72
(C) 81
(D) 98
(E) 240
I always try to find
the task a single worker can do in one hour and work my way from there.
12 workers can do the job in 3 hours ? so
12 workers can do 1/3 of the job in one hour
and one worker can do 1/36 of the job in one hour [1/3 * 1/12 = 1/36].
since all 12 can make 500 boxes in 3 hours - one worker can make 500/36 boxes in one hour.
now starts the real fun ! we need to know about 16 workers and 300 boxes.
500/36 (one worker - one hour) *16 (16 workers)
but we need time and not boxes amount so:
300/500*16/36 = 108/80 (don't forget we need minutes)
so 108/80*60 = 81 minutes (C).