Last visit was: 03 May 2024, 21:49 It is currently 03 May 2024, 21:49

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 93025
Own Kudos [?]: 621026 [5]
Given Kudos: 81742
Send PM
Scoreleap Test Prep Representative
Joined: 08 Mar 2021
Posts: 224
Own Kudos [?]: 118 [0]
Given Kudos: 0
Send PM
Tutor
Joined: 16 Oct 2010
Posts: 14869
Own Kudos [?]: 65078 [2]
Given Kudos: 431
Location: Pune, India
Send PM
GMAT Club Legend
GMAT Club Legend
Joined: 03 Oct 2013
Affiliations: CrackVerbal
Posts: 4946
Own Kudos [?]: 7641 [2]
Given Kudos: 215
Location: India
Send PM
Re: Harsh alone can complete 2/3rd of a coding project in 6 days. Sumit [#permalink]
2
Kudos
Top Contributor
Harsh alone can complete 2/3rd of a coding project in 6 days- therefore, he can complete 1/3rd in 3 days and hence he can complete the entire work in 9 days.
Sumit alone can complete 1/3rd of a coding project in 8 days- therefore, he can complete the entire work in 24 days.
Mini alone can complete 3/4th of a coding project in 12 days- therefore, he can complete 1/4th in 4 days and hence he can complete the entire work in 16 days.

Let the Coding project (the total work to be done) be worth 144 units. Note that 144 is the LCM of the number of days each person individually takes i.e. 144 = LCM (9, 24, 16).

If the total work = 144 units,

Rate of Harsh = 16 units per day
Rate of Sumit = 6 units per day
Rate of Mini = 9 units per day.

When all 3 work together, combined rate = 31 units per day.
Since they worked together for 4 days, the quantum of work accomplished = 31 * 4 = 124 units.

Remaining work in the Coding project = 144 – 124 = 20 units.

These 20 units will have to be completed by Sumit, working alone, since Harsh and Mini quit.
Time taken by Sumit = \(\frac{20 }{ 6}\) = 3.33 days. Sumit will take 3.33 days more to complete the remaining work after Harsha and Mini leave.

The correct answer option is C.
Hope that helps!
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32804
Own Kudos [?]: 825 [0]
Given Kudos: 0
Send PM
Re: Harsh alone can complete 2/3rd of a coding project in 6 days. Sumit [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: Harsh alone can complete 2/3rd of a coding project in 6 days. Sumit [#permalink]
Moderators:
Math Expert
93025 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne