Based only on equipment price, shipping cost, and spare parts cost, which of the following correctly ranks the vendors from lowest to highest total project cost?
• Vendor A: Equipment Price: $510,000
Shipping Cost: $10,000
Spare Parts Cost: $25,000
Total Cost = $510,000 + $10,000 + $25,000 =
$545,000 • Vendor B: Equipment Price: $470,000
Shipping Cost: $30,000
Spare Parts Cost: $20,000
Total Cost = $470,000 + $30,000 + $20,000 =
$520,000 • Vendor C: Equipment Price: $515,000
Shipping Cost: $15,000
Spare Parts Cost: $20,000
Total Cost = $515,000 + $15,000 + $20,000 =
$550,000 • Vendor D: Equipment Price: $490,000
Shipping Cost: $20,000
Spare Parts Cost: $23,000
Total Cost = $490,000 + $20,000 + $23,000 =
$533,000 Final Ranking (Lowest to Highest): Vendor B < Vendor D < Vendor A < Vendor C
Correct answer: Based only on equipment price, shipping cost, and spare parts cost, which of the following correctly ranks the vendors from lowest to highest total project cost?
"Vendor B < Vendor D < Vendor A < Vendor C"