Last visit was: 23 Apr 2024, 19:55 It is currently 23 Apr 2024, 19:55

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
User avatar
Intern
Intern
Joined: 14 Jun 2011
Posts: 14
Own Kudos [?]: 271 [24]
Given Kudos: 25
Send PM
Most Helpful Reply
Tutor
Joined: 16 Oct 2010
Posts: 14816
Own Kudos [?]: 64883 [19]
Given Kudos: 426
Location: Pune, India
Send PM
User avatar
VP
VP
Joined: 02 Jul 2012
Posts: 1011
Own Kudos [?]: 3117 [7]
Given Kudos: 116
Location: India
Concentration: Strategy
GMAT 1: 740 Q49 V42
GPA: 3.8
WE:Engineering (Energy and Utilities)
Send PM
General Discussion
Director
Director
Joined: 17 Dec 2012
Posts: 589
Own Kudos [?]: 1519 [2]
Given Kudos: 20
Location: India
Send PM
Re: Jane and Ashley take 20 days and 40 days respectively to [#permalink]
2
Kudos
Expert Reply
tabsang wrote:
Jane and Ashley take 20 days and 40 days respectively to complete a project when they work on it alone. They thought if they worked on the project together, they would take fewer days to complete it.
During the period that they were working together, Jane took an eight day leave from work. This led to Jane's working for four extra days on her own to complete the project. How long did it take to finish the project ?

(A) 10 Days
(B) 15 Days
(C) 16 Days
(D) 18 Days
(E) 20 Days



Assume Jane and Ashley worked together for x days without considering the 8 day leave of Jane. They would have completed \(x(\frac{1}{40} + \frac{1}{20})\) of the total work in those days. In the period when Jane took a 8 day leave, Ashley worked alone. So Ashley worked alone for 8 days. He would have completed \(\frac{8}{40}\) th of the total work. The work finished before Jane started working alone, is \(x(\frac{1}{20} + \frac{1}{40}) + \frac{8}{40}\). This is equal to \(\frac{4}{5}\) of the total work as in the period when Jane was working alone which is 4 days, she would have completed \(\frac{4}{20}\) or \(\frac{1}{5}\) of the work. Previously done work is therefore \(\frac{4}{5}\).

\(x(\frac{1}{40} +\frac{1}{20}) +\frac{8}{40} = \frac{4}{5}\)

We have x = 8

Add to this the 8 days when Ashley worked alone and the 4 days when Jane worked alone. The total is 8+8+4=20 days.

Originally posted by SVaidyaraman on 27 Dec 2012, 15:57.
Last edited by SVaidyaraman on 27 Dec 2012, 18:04, edited 2 times in total.
User avatar
Intern
Intern
Joined: 03 Nov 2009
Posts: 47
Own Kudos [?]: 57 [0]
Given Kudos: 18
Send PM
Re: Jane and Ashley take 20 days and 40 days respectively to [#permalink]
I generally use take a constant (LCM) and a production example for this kind of questions.

Assuming that Jane and Ashley's work is production of certain number of Toys

In 20 days Jane completes making certain number of Toys and the same number of Toys takes 40 days for Ashley to complete, so we take the LCM (Lowest common Multiple) which would be the target work = 80 toys to complete

From above assumption we know that Jane completes 4 toys / day as in 80/20 days

And Ashley completes 2 toys / Day as in 80/40 days

Now if both worked without any break they would take 80/4+2 days to complete which is 13.333 days, so that eliminates choice (A) = 10 days

Now plugging in choices, B - Jane completes (15-8)*4 = 28
Ashley completes 15*2 =30
Total work in 15 days with 8 days break by Jane = 28+30 = 58 toys
Jane works for 4 days on her own = 4*4 = 16 toys
So in 15 days ( both Jane & Ashley)+ 4 days(only Jane) they complete 58+16 =74 toys, 6 short of the target of 80

Plug in choice C - Ashley completes 16*2= 32 toys
Jane completes 8*4 = 32 toys
Total in 16 days = 64 toys
Jane takes 4 days on her own, 4*4 = 16 toys
So in 16 days ( both Jane & Ashley)+ 4 days(only Jane) they complete = 64+16 = 80 toys which is the target.

Ans : E
avatar
Intern
Intern
Joined: 25 Sep 2012
Posts: 11
Own Kudos [?]: 3 [0]
Given Kudos: 0
Send PM
Re: Jane and Ashley take 20 days and 40 days respectively to [#permalink]
SravnaTestPrep wrote:
tabsang wrote:
Jane and Ashley take 20 days and 40 days respectively to complete a project when they work on it alone. They thought if they worked on the project together, they would take fewer days to complete it.
During the period that they were working together, Jane took an eight day leave from work. This led to Jane's working for four extra days on her own to complete the project. How long did it take to finish the project ?

(A) 10 Days
(B) 15 Days
(C) 16 Days
(D) 18 Days
(E) 20 Days



Assume Jane and Ashley worked together for x days without considering the 8 day leave of Jane. They would have completed \(x(\frac{1}{40} + \frac{1}{20})\) of the total work in those days. In the period when Jane took a 8 day leave, Ashley worked alone. So Ashley worked alone for 8 days. He would have completed \(\frac{8}{40}\) th of the total work. The work finished before Jane started working alone, is \(x(\frac{1}{20} + \frac{1}{40}) + \frac{8}{40}\). This is equal to \(\frac{4}{5}\) of the total work as in the period when Jane was working alone which is 4 days, she would have completed \(\frac{4}{20}\) or \(\frac{1}{5}\) of the work. Previously done work is therefore \(\frac{4}{5}\).

\(x(\frac{1}{40} +\frac{1}{20}) +\frac{8}{40} = \frac{4}{5}\)

We have x = 8

Add to this the 8 days when Ashley worked alone and the 4 days when Jane worked alone. The total is 8+8+4=20 days.




How could you reach to 4/5th of the total work please explain in detail
Target Test Prep Representative
Joined: 04 Mar 2011
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Posts: 3043
Own Kudos [?]: 6271 [0]
Given Kudos: 1646
Send PM
Re: Jane and Ashley take 20 days and 40 days respectively to [#permalink]
Expert Reply
tabsang wrote:
Jane and Ashley take 20 days and 40 days respectively to complete a project when they work on it alone. They thought if they worked on the project together, they would take fewer days to complete it. During the period that they were working together, Jane took an eight day leave from work. This led to Jane's working for four extra days on her own to complete the project. How long did it take to finish the project ?

(A) 10 Days
(B) 15 Days
(C) 16 Days
(D) 18 Days
(E) 20 Days


Jane’s rate is 1/20, Ashley’s rate is 1/40, and their combined rate is 1/20 + 1/40 = 2/40 + 1/40 = 3/40. We can let n = the number of days they actually worked together and create the equation:

Together + Ashley alone + Jane alone = 1 job

(3/40)n + (1/40)8 + (1/20)4 = 1

3n/40 + 8/40 + 4/20 = 1

Multiplying by 40 we have:

3n + 8 + 8 = 40

3n = 24

n = 8

So it took 8 + 8 + 4 = 20 days to complete the project.

Answer: E
Manager
Manager
Joined: 09 Nov 2015
Posts: 202
Own Kudos [?]: 320 [0]
Given Kudos: 96
Send PM
Jane and Ashley take 20 days and 40 days respectively to [#permalink]
We are told that Jane had to work FOUR extra days to make up for the work-loss incurred because of the EIGHT days leave that she took while working together with Ashley.We can thus conclude that, while determining how many days they would need to complete the project (Scheduled Time for Completion or STC), Jane and Ashley had factored in a four-day leave for Jane.
If we denote STC by 'x', the plan was that Jane would work for (x-4) days and Ashley 'x' days. So as per the STC, Jane would have done (1/20)*(x-4)th of the work and Ashley (1/40)*(x)th.

(1/20)*(x-4) + (1/40)*x = 1....> x=16

Scheduled time for completion of project = 16 days
Actual time taken to complete project = 16+4=20 days.
ANS: E
User avatar
Non-Human User
Joined: 09 Sep 2013
Posts: 32632
Own Kudos [?]: 821 [0]
Given Kudos: 0
Send PM
Re: Jane and Ashley take 20 days and 40 days respectively to [#permalink]
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
GMAT Club Bot
Re: Jane and Ashley take 20 days and 40 days respectively to [#permalink]
Moderators:
Math Expert
92883 posts
Senior Moderator - Masters Forum
3137 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne