Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.
Customized for You
we will pick new questions that match your level based on your Timer History
Track Your Progress
every week, we’ll send you an estimated GMAT score based on your performance
Practice Pays
we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Thank you for using the timer!
We noticed you are actually not timing your practice. Click the START button first next time you use the timer.
There are many benefits to timing your practice, including:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?
* 14 * 13 * 11 * 9 * 7
In this question, shouldn't Machine A's no. of days to do the job working 1.5 shifts be 18? Because working 2 shifts, its 12 and working 1 shift its 24. Please tell me what am I missing here.
Archived Topic
Hi there,
Archived GMAT Club Tests question - no more replies possible.
This is my approach. A can do the job in 12 days working two shifts => Number of shifts A takes to complete the job is = 2*12 = 24 shifts. Work done by A per shift = 1/24
B can do the job in 15 days working two shifts =>Number of shifts B takes to complete the job is = 2*15 = 30 shifts. Work done by B per shift = 1/30
Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift => Per day there are three shifts.
First shift A is utilized => work done = 1/24 Second shift B is utilized => work done = 1/30 Work done by A in half shift + Work done by B in half shift = 1/(2*24) + 1/(2*30) = 1/48+1/60.
Total work done in a day (shift1+shift2+shift3) = 1/24+1/30+(1/48+1/60) Solving this gives us 9/80 as the work done per day. So number of days required to complete the job = 80/9 which is nearly equal to 9 days.
My Answer is D.
Please post the OA.