Last visit was: 31 Aug 2026, 13:51 It is currently 31 Aug 2026, 13:51
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 31 Aug 2026
Posts: 113,035
Own Kudos:
Given Kudos: 111,233
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 113,035
Kudos: 838,196
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
SS990
Joined: 17 Apr 2023
Last visit: 31 Aug 2026
Posts: 111
Own Kudos:
Given Kudos: 199
Location: India
Posts: 111
Kudos: 100
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
dhart
Joined: 02 Feb 2026
Last visit: 31 Aug 2026
Posts: 175
Own Kudos:
Given Kudos: 34
Posts: 175
Kudos: 85
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
madsb18
Joined: 06 Nov 2025
Last visit: 31 Aug 2026
Posts: 9
Own Kudos:
GMAT Focus 1: 555 Q80 V78 DI75
GMAT Focus 1: 555 Q80 V78 DI75
Posts: 9
Kudos: 3
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Total work = 120 Units

Mac A's rate 120/12 = 10 units per hr. Mac B's Rate = 2 units per hr.

Mac A finishes 3/4 th of work = 3/4 * (120) = 90 units in 9 hrs. Mac B finishes the rest 30 units in 15 hrs ( 2 units per hr rate)

Total Time Taken 9+ 15 = 24 hrs.

C
User avatar
laborumpossimus
Joined: 07 Jan 2026
Last visit: 31 Aug 2026
Posts: 33
Own Kudos:
Given Kudos: 25
Location: India
Concentration: Marketing, Strategy
GPA: 3.8
Products:
Posts: 33
Kudos: 14
Kudos
Add Kudos
Bookmarks
Bookmark this Post
so i assumed work done to be 120

A efficiency is 10 as it can complete work in 12 hrs
meanwhile efficiency of B is 1/5 of A so it is 2
Now the question says A completes 3/4 of the job so 90 is done by A and remaining 30 is completed by b
So
A MACHINE
10{ EFFICIENCY } X HOURS = 90

Time taken 9 hours

B

2 (Efficiency ) x hours = 30

time taken - 15 hours

adding A and B
we get 24 hours
SO c

Bunuel
Machine A can complete a job in 12 hours, and Machine B can do the same job at 1/5 of the rate of Machine A. If Machine A completes 3/4 of the job and then Machine B finishes the remaining portion, what is the total amount of time taken by Machine A and Machine B?

(A) 18 hours
(B) 20 hours
(C) 24 hours
(D) 28 hours
(E) 30 hours