Last visit was: 23 Apr 2026, 03:25 It is currently 23 Apr 2026, 03:25
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 23 Apr 2026
Posts: 109,773
Own Kudos:
810,735
 [3]
Given Kudos: 105,853
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,773
Kudos: 810,735
 [3]
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Shubhradeep
Joined: 11 Jan 2024
Last visit: 07 Feb 2026
Posts: 120
Own Kudos:
247
 [6]
Given Kudos: 108
Location: India
Posts: 120
Kudos: 247
 [6]
4
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
General Discussion
User avatar
Aryaa03
Joined: 12 Jun 2023
Last visit: 19 Feb 2026
Posts: 210
Own Kudos:
285
 [2]
Given Kudos: 159
Location: India
GMAT Focus 1: 645 Q86 V81 DI78
GMAT Focus 1: 645 Q86 V81 DI78
Posts: 210
Kudos: 285
 [2]
2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
ADITHISRINIVAS
Joined: 03 Jul 2024
Last visit: 29 Aug 2025
Posts: 2
Location: India
Posts: 2
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
If we leave the mathematical side of this question and look at it logically:

15 workers --> 12 days to complete the work
(+) Add 5 workers after 4 days -
Remaining: 20 workers & 8 days.

Logically, with the increased number of workers, the number of days required to complete the work will reduce. The only option lesser than 8 here is option B i.e, 6 days.