Last visit was: 25 Apr 2026, 11:30 It is currently 25 Apr 2026, 11:30
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 25 Apr 2026
Posts: 109,830
Own Kudos:
Given Kudos: 105,884
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,830
Kudos: 811,244
 [60]
8
Kudos
Add Kudos
52
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bowtye
Joined: 13 Nov 2014
Last visit: 29 Jun 2018
Posts: 90
Own Kudos:
127
 [15]
Given Kudos: 28
GMAT 1: 740 Q50 V40
Products:
GMAT 1: 740 Q50 V40
Posts: 90
Kudos: 127
 [15]
9
Kudos
Add Kudos
6
Bookmarks
Bookmark this Post
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 25 Apr 2026
Posts: 109,830
Own Kudos:
Given Kudos: 105,884
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,830
Kudos: 811,244
 [13]
7
Kudos
Add Kudos
6
Bookmarks
Bookmark this Post
General Discussion
avatar
PareshGmat
Joined: 27 Dec 2012
Last visit: 10 Jul 2016
Posts: 1,531
Own Kudos:
Given Kudos: 193
Status:The Best Or Nothing
Location: India
Concentration: General Management, Technology
WE:Information Technology (Computer Software)
Posts: 1,531
Kudos: 8,277
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Answer = B = 17 Minutes

A .............................. B ........................... C ............................ D

\(\frac{1}{a}\) .......................... \(\frac{1}{b}\) ......................... \(\frac{a+b}{ab}\) ..................... \(\frac{3(a+b)}{ab}\) ............... Rates

Given that \(4 * \frac{1}{b} = \frac{3(a+b)}{ab}\)

a = 3b

Re-writing all rates in terms of b

\(\frac{1}{3b}\) ........................... \(\frac{1}{b}\) ....................... \(\frac{4}{3b}\) ............................ \(\frac{4}{b}\)

Let the work done by A = 1

\(\frac{1}{3b} * 340 = 1\)

\(b = \frac{340}{3}\) ....................... (1)

Combined rate of all machines\(= \frac{1}{3b} + \frac{1}{b} + \frac{4}{3b} + \frac{4}{b} = \frac{20}{3b}\)

Placing value of b from (1)

Combined rate \(= \frac{1}{17}\)

Time required = 17 Minutes
User avatar
23a2012
Joined: 03 Oct 2013
Last visit: 14 Jun 2015
Posts: 62
Own Kudos:
Given Kudos: 144
Status:Kitchener
Location: Canada
Concentration: Finance, Finance
GPA: 2.9
WE:Education (Education)
Posts: 62
Kudos: 49
Kudos
Add Kudos
Bookmarks
Bookmark this Post
The answer is B

A,B,C=A+B, D=3(A+B) orD=4B

A =Ra*340=1
Ra=1/340
D=3A+3B=4B
3A=B
3/340=B
C=1/340+3/340=4/340
D=4B=4(3/340)=12/340

so working together =A+B+C+D*T=1
1/340+3/340+4/340+12/340*T=1
T=340/20=17 minutes
User avatar
SunthoshiTejaswi
Joined: 05 Feb 2014
Last visit: 24 Jan 2018
Posts: 14
Given Kudos: 18
Location: India
Concentration: Human Resources, General Management
GMAT 1: 720 Q49 V40
GPA: 3.33
GMAT 1: 720 Q49 V40
Posts: 14
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Bunuel
Machine A and machine B process the same work at different rates. Machine C processes work as fast as Machines A & B combined. Machine D processes work three times as fast as Machine C; Machine D’s work rate is also exactly four times Machine B’s rate. Assume all four machines work at fixed unchanging rates. If Machine A works alone on a job, it takes 5 hours and 40 minutes. If all four machines work together on the same job simultaneously, how long will it take all of them to complete it?

A. 8 minutes
B. 17 minutes
C. 35 minutes
D. 1 hour and 15 minutes
E. 1 hours and 35 minutes

Kudos for a correct solution.

MAGOOSH OFFICIAL SOLUTION:

Let A, B, C, and D be the rates of Machines A, B, C, and D respectively. We know that

(i) C = A + B

(ii) D = 3C

(iii) D = 4B

Starting with (ii) and (iii), equate the two expressions equal to D, and then substitute in the expression from (i) equal to C.

4B = 3C = 3(A + B) = 3A + 3B

B = 3A

Then, C = A + 3A = 4A, and D = 3*(4A) = 12A

The combined rate,

A + B + C + D = A + 3A + 4A + 12A = 20A

Since the combined rate is 20 times faster than Machine A alone, the combined time should be divided by 20.

Machine A alone takes 5 hr 40 min, or 340 minutes for the whole job. Divide this by 20:

340/20 = 17

The combination of the four machines will take 17 minutes to complete the job.

Answer = (B)


hi bunnuel can you please explain the same with rate of a taken as 1/a

then am getting 3b=a
User avatar
GMATinsight
User avatar
Major Poster
Joined: 08 Jul 2010
Last visit: 25 Apr 2026
Posts: 6,977
Own Kudos:
16,916
 [1]
Given Kudos: 128
Status:GMAT/GRE Tutor l Admission Consultant l On-Demand Course creator
Location: India
GMAT: QUANT+DI EXPERT
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
WE:Education (Education)
Products:
Expert
Expert reply
Schools: IIM (A) ISB '24
GMAT 1: 750 Q51 V41
Posts: 6,977
Kudos: 16,916
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
SunthoshiTejaswi
Bunuel
Machine A and machine B process the same work at different rates. Machine C processes work as fast as Machines A & B combined. Machine D processes work three times as fast as Machine C; . Assume all four machines work at fixed unchanging rates. If Machine A works alone on a job, it takes 5 hours and 40 minutes. If all four machines work together on the same job simultaneously, how long will it take all of them to complete it?

A. 8 minutes
B. 17 minutes
C. 35 minutes
D. 1 hour and 15 minutes
E. 1 hours and 35 minutes

Kudos for a correct solution.


hi bunnuel can you please explain the same with rate of a taken as 1/a

then am getting 3b=a

Machine A processes work in 5 hours 40 mins = 5x60 + 40 = 340 Mins

i.e. Machine A processes in 1 mins = 1/340 work

Let Machine B processes in 1 min = 1/b work

i.e. The Work of Machine C in 1 Min = Work of A and B together in 1 min = (1/340)+(1/b)

i.e. The Work of Machine D in 1 Min = 3*Work of C in 1 min = 3*[(1/340)+(1/b)]

But, Machine D’s work rate is also exactly four times Machine B’s rate

i.e. The Work of Machine D in 1 Min = 4* (1/b) = 3*[(1/340)+(1/b)]

i.e. 4/b = 3*[(b+340)/340*b]

i.e. (4/b) * (340*b) = 3b + 1020

i.e. 1360 = 3b + 1020
i.e. b = 340/3

i.e. B's 1 Min work = 3/340
i.e. C's 1 Min work = (3/340)+(1/340) = 4/340
i.e. D's 1 Min work = 3*(4/340) = 12/340

Work of A, B, C and D combined in 1 min = (1/340) + (3/340) + (4/340) + (12/340) = (20/340)

i.e. Time taken by A, B, C and D working together = 340/20 mins = 17 mins

Answer: option
P.S.Your Mistake is you are getting 3b = a whereas the CORRECT relation is b=3a
User avatar
mvictor
User avatar
Board of Directors
Joined: 17 Jul 2014
Last visit: 14 Jul 2021
Posts: 2,118
Own Kudos:
Given Kudos: 236
Location: United States (IL)
Concentration: Finance, Economics
GMAT 1: 650 Q49 V30
GPA: 3.92
WE:General Management (Transportation)
Products:
GMAT 1: 650 Q49 V30
Posts: 2,118
Kudos: 1,277
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Machine A and machine B process the same work at different rates. Machine C processes work as fast as Machines A & B combined. Machine D processes work three times as fast as Machine C; Machine D’s work rate is also exactly four times Machine B’s rate. Assume all four machines work at fixed unchanging rates. If Machine A works alone on a job, it takes 5 hours and 40 minutes. If all four machines work together on the same job simultaneously, how long will it take all of them to complete it?

A. 8 minutes
B. 17 minutes
C. 35 minutes
D. 1 hour and 15 minutes
E. 1 hours and 35 minutes

Kudos for a correct solution.


a pretty basic question, yet with a lot of information...

C=A+B
D=4B=3(A+B) = 3A+3B -> B=3A.
thus, we have:
A
B=3A
C=4A
D=12A
total: 20A - combined rate.

time taken by A alone to finish: 5h40m -> i think it's better to work with minutes...340 minutes.
Rate for A is thus 1/340
total rate A+B+C+D = 20A
20/340 or 2/34 or 1/17
this means that all machines, combined, do 1 job in 17 minutes.

the answer must be B.
User avatar
ScottTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 14 Oct 2015
Last visit: 25 Apr 2026
Posts: 22,286
Own Kudos:
Given Kudos: 302
Status:Founder & CEO
Affiliations: Target Test Prep
Location: United States (CA)
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 22,286
Kudos: 26,537
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
Machine A and machine B process the same work at different rates. Machine C processes work as fast as Machines A & B combined. Machine D processes work three times as fast as Machine C; Machine D’s work rate is also exactly four times Machine B’s rate. Assume all four machines work at fixed unchanging rates. If Machine A works alone on a job, it takes 5 hours and 40 minutes. If all four machines work together on the same job simultaneously, how long will it take all of them to complete it?

A. 8 minutes
B. 17 minutes
C. 35 minutes
D. 1 hour and 15 minutes
E. 1 hours and 35 minutes

Since Machine A’s time to complete the job is 5 hours and 40 minutes, or 5 ⅔ = 17/3 hours, its rate is 3/17. We can let Machines B’s rate = b and thus, Machine C’s rate = 3/17 + b and Machine D’s rate = 3(3/17 + b) = 9/17 + 3b. We are also given that Machine D’s rate = 4b. Thus we have:

9/17 + 3b = 4b

9/17 = b

Now, we can determine that C’s rate = 3/17 + 9/17 = 12/17 and D’s rate = 4(9/17) = 36/17.

Thus, if we let x = the time, in hours, for the 4 machines to work together to complete the job, we have:

(3/17)x + (9/17)x + (12/17)x + (36/17)x = 1

[(3 + 9 + 12 + 36)/17]x = 1

(60/17)x = 1

x = 1/(60/17) = 17/60

Thus it takes 17/60 hours, or 17 minutes to complete the job when 4 machines work together.

Answer: B
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,985
Own Kudos:
Posts: 38,985
Kudos: 1,118
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Automated notice from GMAT Club BumpBot:

A member just gave Kudos to this thread, showing it’s still useful. I’ve bumped it to the top so more people can benefit. Feel free to add your own questions or solutions.

This post was generated automatically.
Moderators:
Math Expert
109829 posts
Tuck School Moderator
852 posts