Last visit was: 26 Apr 2026, 00:32 It is currently 26 Apr 2026, 00:32
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
KSBGC
Joined: 31 Oct 2013
Last visit: 10 Mar 2022
Posts: 1,240
Own Kudos:
1,509
 [24]
Given Kudos: 635
Concentration: Accounting, Finance
GPA: 3.68
WE:Analyst (Accounting)
Posts: 1,240
Kudos: 1,509
 [24]
2
Kudos
Add Kudos
22
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 23 Apr 2026
Posts: 16,441
Own Kudos:
79,413
 [17]
Given Kudos: 485
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,441
Kudos: 79,413
 [17]
12
Kudos
Add Kudos
5
Bookmarks
Bookmark this Post
General Discussion
User avatar
gracie
Joined: 07 Dec 2014
Last visit: 11 Oct 2020
Posts: 1,028
Own Kudos:
2,023
 [2]
Given Kudos: 27
Posts: 1,028
Kudos: 2,023
 [2]
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
pushpitkc
Joined: 26 Feb 2016
Last visit: 19 Feb 2025
Posts: 2,800
Own Kudos:
6,235
 [1]
Given Kudos: 47
Location: India
GPA: 3.12
Posts: 2,800
Kudos: 6,235
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
selim
John appointed 25 men to complete a small bridge in 40 days. After 20 days he appointed 15 more workers and the bridge was completed 5 days earlier. If he had not appointed the additional workers by how many days he would have been behind the schedule time ?

A)2 days
B)3 days
C)4 days
D)5 days
E)5/2 Days


Given: Originally, the work was to be completed by 25 workers in 40 days. If we assume the total
work a worker does in a day to be 1 units, the total work must be 1000(40*25) units.

In second statement of question stem we are given "After 20 days he appointed 15 more workers
and the bridge was completed 5 days earlier" - Here, we need to know how many workers actually
did the job.

x workers work for 20 days and x+15 work for 15 days to complete the work in 35 days.
\(x*20+ (x+15)15 > 1000\) -> \(35x > 775\) -> \(x > 22\). Minimum workers must be 23

Now, 23 workers complete 23*40 units or 920 units of work in 40 days.
Incomplete work: 80 units | Therefore, it will take 4(Option C) days in order to complete the pending work.
User avatar
Mizan383838
Joined: 11 May 2020
Last visit: 15 Dec 2025
Posts: 4
Own Kudos:
1
 [1]
Given Kudos: 4
Posts: 4
Kudos: 1
 [1]
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Suppose, 1 man's 1 days' work = x

Now, 25*x*20+ 40*x*15 = 1
=>x = 1/1100

Again,
suppose, y days needed to complete whole work

Now,

25*y/1100=1

=> y = 44

So, extra days= 4 (ans)

Posted from my mobile device
User avatar
Kinshook
User avatar
Major Poster
Joined: 03 Jun 2019
Last visit: 25 Apr 2026
Posts: 5,986
Own Kudos:
Given Kudos: 163
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Products:
GMAT 1: 690 Q50 V34
Posts: 5,986
Kudos: 5,859
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Given: John appointed 25 men to complete a small bridge in 40 days. After 20 days he appointed 15 more workers and the bridge was completed 5 days earlier.

Asked: If he had not appointed the additional workers by how many days he would have been behind the schedule time ?

Total man-days required to complete the small bridge = 25*20 + (25+15)*(40-5-20) = 25*20 + 40*15 = 500 + 600 = 1100 man-days
Days required by 25 men to complete the bridge = 1100/25 = 44 days

If he had not appointed the additional workers, he would have been behind the schedule by days = 44-40 = 4 days

IMO C
User avatar
01862603526
Joined: 23 Jul 2023
Last visit: 05 May 2025
Posts: 1
Given Kudos: 2
Posts: 1
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Firt part. 25 men take 20 days.
Second part. 25+15=40 take 15 days, so 1 man take= 40×15
So 25 men take =40×15÷25=24 days.so 25 men take to complete the bridge in 20+24=44 days. He would have been behind scheduled time by 4 days.

Posted from my mobile device
User avatar
anirudhjay
Joined: 30 Nov 2025
Last visit: 15 Feb 2026
Posts: 4
Own Kudos:
Given Kudos: 38
Posts: 4
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Shouldn't it be explicit that the additional workers work at the same capacity or work per unit time as the other 25 men? I had to figure out the implicit assumption, since the problem would otherwise be unsolvable.
KSBGC
John appointed 25 men to complete a small bridge in 40 days. After 20 days he appointed 15 more workers and the bridge was completed 5 days earlier. If he had not appointed the additional workers by how many days he would have been behind the schedule time ?

A) 2 days
B) 3 days
C) 4 days
D) 5 days
E) 5/2 Days
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 26 Apr 2026
Posts: 109,832
Own Kudos:
811,317
 [1]
Given Kudos: 105,889
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,832
Kudos: 811,317
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
anirudhjay
Shouldn't it be explicit that the additional workers work at the same capacity or work per unit time as the other 25 men? I had to figure out the implicit assumption, since the problem would otherwise be unsolvable.


A properly written GMAT question would state that explicitly. In this problem, as you correctly noted, if you do not assume that all workers work at the same rate, the question is unsolvable. So here you should simply make that assumption and proceed.
User avatar
patpathaha
Joined: 28 May 2025
Last visit: 09 Mar 2026
Posts: 7
Own Kudos:
Given Kudos: 16
Posts: 7
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
1 men : 1 day : 1/x bridge done
=> 25 men : 1 day : 25/x bridge done
=> 25 men : 20 days : 25*20/x = 500/x bridge done
so after the first 20 days, 500/x bridge is done


1 men : 1 day : 1/x bridge done
he add 15 men to the existing 25 men, so now we have 40 men => 40 men : 1 day : 40/x bridge done
the deadline is 40 days, 20 days have passed, and they complete 5 days earlier, so the rest of the time all 40 men works is 40-20-5=15 days => 40 men : 15 days : 40*15/x = 600/x bridge done

After 35 days, 1 bridge should be completely done
=> 500/x + 600/x = 1 => x = 1100

=> 1 men : 1 day : 1/1100 bridge done
=> 25 men : 1 day : 25/1100 = 1/44 bridge done
=> 25 men : 44 days : 1/44*44 = 1 bridge done
=> they need 44 days
Moderators:
Math Expert
109831 posts
Tuck School Moderator
852 posts