Last visit was: 19 Nov 2025, 06:40 It is currently 19 Nov 2025, 06:40
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 Nov 2025
Posts: 105,388
Own Kudos:
Given Kudos: 99,977
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,388
Kudos: 778,227
 [32]
Kudos
Add Kudos
31
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
GMATWhizTeam
User avatar
GMATWhiz Representative
Joined: 07 May 2019
Last visit: 14 Oct 2025
Posts: 3,380
Own Kudos:
2,141
 [11]
Given Kudos: 69
Location: India
GMAT 1: 740 Q50 V41
GMAT 2: 760 Q51 V40
Expert
Expert reply
GMAT 2: 760 Q51 V40
Posts: 3,380
Kudos: 2,141
 [11]
6
Kudos
Add Kudos
5
Bookmarks
Bookmark this Post
User avatar
nick1816
User avatar
Retired Moderator
Joined: 19 Oct 2018
Last visit: 06 Nov 2025
Posts: 1,849
Own Kudos:
8,237
 [9]
Given Kudos: 707
Location: India
Posts: 1,849
Kudos: 8,237
 [9]
5
Kudos
Add Kudos
4
Bookmarks
Bookmark this Post
General Discussion
User avatar
preetamsaha
Joined: 14 Oct 2019
Last visit: 18 Jan 2025
Posts: 337
Own Kudos:
541
 [6]
Given Kudos: 127
Status:Today a Reader; Tomorrow a Leader.
Location: India
GPA: 4
WE:Engineering (Energy)
Posts: 337
Kudos: 541
 [6]
5
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
B needs 25% more time than A
So, if Time taken by A = 4x days, Time taken by B = 5x days
A does half the work, So A works alone for 2x days --- (1)
A and B work for 4 days --- (2)
B works alone for 5x/20 = x/4 days ---(3)
therefore, 2x + 4 + x/4 = 13
or, x= 4
So, B alone can do the work in 5 × 4 = 20 days

correct answer is B
avatar
fireagablast
Joined: 30 Jun 2019
Last visit: 17 Aug 2021
Posts: 263
Own Kudos:
Given Kudos: 8
Posts: 263
Kudos: 123
Kudos
Add Kudos
Bookmarks
Bookmark this Post
1/2-0.05 = (A+B)4
45/100 = (5/4B+B)4
45/100 = (9/4B)4
9/20 = 9B
1/20 = B

20 days for B alone (and 16 days for A alone)
User avatar
Greg1234
Joined: 21 Nov 2023
Last visit: 02 Nov 2025
Posts: 11
Own Kudos:
9
 [2]
Given Kudos: 5
Posts: 11
Kudos: 9
 [2]
1
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Apologies for the format, however I would like to post my way of solving this question.

The rate of A is 1/a and the rate of B is 1/1.25a. Using a common denominator of 5 you get rate of A is 5/5a and rate of B is 4/5a. The question tells us that A did 50% of the job, and when A and B were done working together after 4 days only 5% of the work was left to do. This tell us that the rate of A and B together is 45% of the job / 4 days. In other words 45/100 * 1/4 which is 45/400. This can be rewritten as 9/80. Using 5/5a and 4/5a we get that the combined rate is 9/5a. Therefore, 5a = 80 and a = 16. B takes 25% longer and 25% of 16 is 4 therefore B takes 20 days.
User avatar
thukahuaengineer
Joined: 12 Jun 2024
Last visit: 17 Nov 2025
Posts: 1
Own Kudos:
Given Kudos: 4
Posts: 1
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
50% done by A alone 1st; 5% done by b alone at last. In total 55% work done. Now, this means (A+B) does 45% work in 4 days => 100% work will be done by (A+B) in 80/9 days (by unitary method).

Let A take t time to complete the whole work alone. Then
1/t + 1/1.25t = 1/ (80/9)
=> t = 16
=> 1.25 t = 20 days . (Answer)
User avatar
thekingslay
Joined: 30 Mar 2021
Last visit: 17 Nov 2025
Posts: 83
Own Kudos:
Given Kudos: 146
GMAT 1: 720 Q56 V50
GMAT 1: 720 Q56 V50
Posts: 83
Kudos: 18
Kudos
Add Kudos
Bookmarks
Bookmark this Post
GMATWhizTeam
Bunuel
When they work alone, B needs 25% more time to finish a job than A does. They two finish the job in 13 days in the following manner: A works alone till half the job is done, then A and B work together for four days, and finally B works alone to complete the remaining 5% of the job. In how many days can B alone finish the entire job?

A. 22
B. 20
C. 18
D. 16
E. 14


Are You Up For the Challenge: 700 Level Questions

Solution


    • Let us assume that the time taken by B to complete the job be \(b\) days.
      o Then time taken by A to complete the job = \(\frac{b}{1.25}\) days \(= \frac{4b}{5}\) days.
         Then time taken by A to complete the half of the job \(= \frac{2b}{5} \)days
      o Also, time taken by B to complete 5% of the job \(= b*\frac{5}{100} = \frac{b}{20}\) days
    • According to the questions,
      o \(\frac{2b}{5} + 4 + \frac{b}{20} = 13\)
      \(⟹\frac{(8b + b)}{20} = 9\)
      \(⟹9b = 9*20\)
      \(⟹b = 20\)
Thus, the correct answer is Option B.

How time taken by A is b/1.25?
­
User avatar
adewale223
Joined: 07 Oct 2022
Last visit: 15 Oct 2025
Posts: 113
Own Kudos:
72
 [1]
Given Kudos: 45
Location: Nigeria
Posts: 113
Kudos: 72
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Let time taken for A alone to complete the job be x then B's time will be 1.25x


A and B work for 4 days

1/x + 1/1.25x = w/4

w = 9/1.25x


1/2 + 9/1.25x + 1/20 = 1

x = 16

So time taken for B alone to do the job = 1.25 x 16 = 20

Answer B

Adewale Fasipe, GMAT quant instructor from Lagos Nigeria.­
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,589
Own Kudos:
Posts: 38,589
Kudos: 1,079
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
Moderators:
Math Expert
105388 posts
Tuck School Moderator
805 posts