Last visit was: 24 Apr 2024, 17:11 It is currently 24 Apr 2024, 17:11

Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 92900
Own Kudos [?]: 618813 [18]
Given Kudos: 81588
Send PM
Most Helpful Reply
Current Student
Joined: 18 Aug 2016
Posts: 531
Own Kudos [?]: 577 [8]
Given Kudos: 198
Concentration: Strategy, Technology
GMAT 1: 630 Q47 V29
GMAT 2: 740 Q51 V38
Send PM
General Discussion
Intern
Intern
Joined: 19 Jul 2020
Posts: 6
Own Kudos [?]: 1 [0]
Given Kudos: 24
Send PM
GMATWhiz Representative
Joined: 23 May 2022
Posts: 640
Own Kudos [?]: 429 [0]
Given Kudos: 6
Location: India
GMAT 1: 760 Q51 V40
Send PM
Re: 4 men and 10 women were assigned to complete a work. Can they complete [#permalink]
Expert Reply
Bunuel wrote:
4 men and 10 women were assigned to complete a work. Can they complete the work within 15 days? Assume that all men are equally efficient and all women are equally efficient.

(1) 4 men and 10 women employed initially completed 1/3 of the work in less than 6 days.
(2) If 2 additional men and 2 additional women had been employed, they would have completed 1/2 of the work in 5 days (the additional men and the additional women have efficiencies equal to the men and women employed initially, respectively).


Solution:
Pre Analysis:
  • Work by 4 men in 15 days \(=nRT=4\times M\times 15=60M\) where M is the rate of each man
  • Work by 10 women in 15 days \(=nRT=10\times W\times 15=150W\) where W is the rate of each woman
  • We are asked if \(60M+150W=Work \) or not

Statement 1: 4 men and 10 women employed initially completed 1/3 of the work in less than 6 days
  • If they (4 men and 10 women) complete the 1/3 work in 5 days, then they will complete the work in \(5\times 3=15\) days
  • However, if they complete it in less than that, they won't be able to complete the full work in 15 days
  • Thus, statement 1 alone is not sufficient and we can eliminate options A and D

Statement 2: If 2 additional men and 2 additional women had been employed, they would have completed 1/2 of the work in 5 days
  • Work by 6 men in 5 days \(=nRT=6\times M\times 5=30M\)
  • Work by 12 women in 5 days \(=nRT=12\times W\times 5=60W\)
  • According to the statement \(30M+60W=\frac{Work}{2}⇒60M+120W=Work\)
  • This means \(60M+150W=Work \) is not true and we can answer the question

Hence the right answer is Option B
GMAT Club Bot
Re: 4 men and 10 women were assigned to complete a work. Can they complete [#permalink]
Moderator:
Math Expert
92900 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne