GMAT Question of the Day - Daily to your Mailbox; hard ones only

It is currently 24 Sep 2018, 04:38

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel

40 employees take 30 days,working at 8 hrs per day,to complete a task.

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

Manager
Manager
User avatar
S
Joined: 11 Jul 2016
Posts: 53
Location: India
Concentration: Technology, General Management
GMAT 1: 550 Q36 V30
GPA: 3.65
WE: Information Technology (Consulting)
40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 22 Nov 2017, 21:57
2
6
00:00
A
B
C
D
E

Difficulty:

  75% (hard)

Question Stats:

62% (01:45) correct 38% (02:43) wrong based on 125 sessions

HideShow timer Statistics

40 employees take 30 days,working at 8 hrs per day,to complete a task. 40 employees start the work but after 10 days,20 leave and are replaced by employees who are 1/2 as productive.How many hours per day should the new team work if the work has to be completed in the scheduled timeline?

1. 12
2. 20
3. 10.6
4. 6
5. 30

Source: Experts' Global
Most Helpful Expert Reply
Veritas Prep GMAT Instructor
User avatar
P
Joined: 16 Oct 2010
Posts: 8293
Location: Pune, India
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 23 Nov 2017, 07:07
4
1
Sangeeta2018 wrote:
40 employees take 30 days,working at 8 hrs per day,to complete a task. 40 employees start the work but after 10 days,20 leave and are replaced by employees who are 1/2 as productive.How many hours per day should the new team work if the work has to be completed in the scheduled timeline?

1. 12
2. 20
3. 10.6
4. 6
5. 30

Source: Experts' Global


Using Ratios:

When half the employees are exchanged for 1/2 as productive employees, the total rate of work becomes 3/4 of original.

Time taken = 4/3 of original for same work

Original time taken for remaining work would have been = 20*8 = 160 hrs
New time taken for remaining work = 160 * 4/3 hrs = 640/3 hrs
In 20 days, this implies 640/3*20 = 10.6 hrs per day

Answer (C)
_________________

Karishma
Veritas Prep GMAT Instructor

Learn more about how Veritas Prep can help you achieve a great GMAT score by checking out their GMAT Prep Options >

GMAT self-study has never been more personalized or more fun. Try ORION Free!

General Discussion
Math Expert
User avatar
V
Joined: 02 Aug 2009
Posts: 6803
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 23 Nov 2017, 02:16
Sangeeta2018 wrote:
40 employees take 30 days,working at 8 hrs per day,to complete a task. 40 employees start the work but after 10 days,20 leave and are replaced by employees who are 1/2 as productive.How many hours per day should the new team work if the work has to be completed in the scheduled timeline?

1. 12
2. 20
3. 10.6
4. 6
5. 30

Source: Experts' Global



Hi...

the TIMER shows all have gone wrong, so here is something which may help ..

two ways..
1) LOGICAL...
for the remaining days 20 are working for 8 hrs and other 20 will require to work for 16hrs..
so all 40 work for entire 8 hrs and then share the remaining work of 16-8=8 hrs..
these 8 hrs are of the speed of 1/2 productive and if we add full productive person, it is SAME as adding 2 half-productive persons..

so these 8 hrs is being shared by 1+2=3 person, MEANING each person requires to do \(\frac{8}{3}=2.66\) hrs
so the hours required is \(8+2.66=10.66\)
C
_________________

1) Absolute modulus : http://gmatclub.com/forum/absolute-modulus-a-better-understanding-210849.html#p1622372
2)Combination of similar and dissimilar things : http://gmatclub.com/forum/topic215915.html
3) effects of arithmetic operations : https://gmatclub.com/forum/effects-of-arithmetic-operations-on-fractions-269413.html


GMAT online Tutor

Math Expert
User avatar
V
Joined: 02 Aug 2009
Posts: 6803
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 23 Nov 2017, 02:29
1
Sangeeta2018 wrote:
40 employees take 30 days,working at 8 hrs per day,to complete a task. 40 employees start the work but after 10 days,20 leave and are replaced by employees who are 1/2 as productive.How many hours per day should the new team work if the work has to be completed in the scheduled timeline?

1. 12
2. 20
3. 10.6
4. 6
5. 30

Source: Experts' Global


PROPER method..
40 require \(30*8=240\) hrs, so 1 full productive will require \(240*40\)h.....1hr work = \(\frac{1}{240*40}\), so
1 hr work of half productive = \(\frac{1}{2}*\frac{1}{240*40}= \frac{1}{480*40}\)..
combined work of these two - set of productive+half productive = \(\frac{1}{240*40}+\frac{1}{480*40} = \frac{3}{480*40}\)
now there are 20 sets so 1 hr work of all 40 = \(20*\frac{3}{480*40}=\frac{1}{320}\)
so they require to work for 320 h for complete work but remaining work is \(\frac{30-10}{30}=\frac{2}{3}\), this will be completed in \(\frac{320*2}{3}\)
and these hours are equally spread across 20 days, so per day = \(\frac{320*2}{3*20}=\frac{32}{3} = 10.66\)

C
_________________

1) Absolute modulus : http://gmatclub.com/forum/absolute-modulus-a-better-understanding-210849.html#p1622372
2)Combination of similar and dissimilar things : http://gmatclub.com/forum/topic215915.html
3) effects of arithmetic operations : https://gmatclub.com/forum/effects-of-arithmetic-operations-on-fractions-269413.html


GMAT online Tutor

Manager
Manager
avatar
B
Status: Sky is the limit
Affiliations: CIPS
Joined: 01 Apr 2012
Posts: 68
Location: United Arab Emirates
Concentration: General Management, Strategy
GMAT 1: 720 Q50 V38
WE: Supply Chain Management (Energy and Utilities)
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 23 Nov 2017, 03:33
2
2
Total man hour required to complete the task = 40*30*8 = 9,600 man hours

Situation 1:
40 employees works 8 hour each for 10 days = 40*10*8 = 3,200 man hours completed

Situation 2:
20 employees (Set 1) replaced by another set of 20 employees (Set 2) who are half productive as Set 1

Here, the new group has been asked to complete the task within 30 days by working additional hours in a day. Remaining no. of days is 20.

Hence, the new group has to complete 6,400 man hours in 20 days. 20 employees in set 1 is twice productive as 20 employees in set 2. All employees will work for same no. of hours in the day.

20 employees in set 1 * 20 days * x days + 1/2 (20 employees in set 2 * 20 days * x days) = 6,400
400 x + 200 x = 6,400
600 x = 6,400
x = 10.66

So the answer is C
EMPOWERgmat Instructor
User avatar
V
Status: GMAT Assassin/Co-Founder
Affiliations: EMPOWERgmat
Joined: 19 Dec 2014
Posts: 12443
Location: United States (CA)
GMAT 1: 800 Q51 V49
GRE 1: Q170 V170
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 04 Jan 2018, 15:33
Hi All,

We're told that 40 employees take 30 days (working at 8 hrs per day) to complete a task. 40 employees start the work - BUT after 10 days, 20 workers leave and are replaced by employees who are 1/2 as productive. We're asked for the number hours per day that the new team must work to complete the job in the scheduled timeline. With these types of rate questions, it helps to first figure out the total amount of 'work' needed to complete the job, then use that information with whatever other information you've been given.

The original team would need (40)(30)(8) = 9600 worker-hours to complete the job

For the first 10 days, all 40 employees work as planned, so (40)(10)(8) = 3200 worker-hours are completed, leaving 9600 - 3200 = 6400 worker-hours to go

20 of the 40 employees are replaced with workers who are HALF as productive, meaning that each of those employees completes 1/2 a worker-hour of work per 1 hour. With those 20 replacement workers, the 'new' team of 40 employees will complete LESS work per hour than the original team did.

New team:
20 original workers complete 20 worker-hours per hour
20 new workers complete 10 worker-hours per hour
20 + 10 = 30 worker-hours completed per hour

With 20 days remaining and 6400 worker-hours to go...
6400/20 = 320 worker-hours must be completed each day.

At the new rate, that would require...
320/30 = 10 2/3 hours of work per worker each day

Final Answer:

GMAT assassins aren't born, they're made,
Rich
_________________

760+: Learn What GMAT Assassins Do to Score at the Highest Levels
Contact Rich at: Rich.C@empowergmat.com

Rich Cohen

Co-Founder & GMAT Assassin

Special Offer: Save $75 + GMAT Club Tests Free
  Official GMAT Exam Packs + 70 Pt. Improvement Guarantee
www.empowergmat.com/

***********************Select EMPOWERgmat Courses now include ALL 6 Official GMAC CATs!***********************

Intern
Intern
avatar
B
Joined: 09 Dec 2013
Posts: 29
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 13 Jan 2018, 02:50
Sangeeta2018 wrote:
40 employees take 30 days,working at 8 hrs per day,to complete a task. 40 employees start the work but after 10 days,20 leave and are replaced by employees who are 1/2 as productive.How many hours per day should the new team work if the work has to be completed in the scheduled timeline?

1. 12
2. 20
3. 10.6
4. 6
5. 30

Source: Experts' Global


generis please help with this question using your method.
Senior SC Moderator
avatar
V
Joined: 22 May 2016
Posts: 1979
Premium Member CAT Tests
40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 14 Jan 2018, 16:22
1
Buttercup3 wrote:
Sangeeta2018 wrote:
40 employees take 30 days,working at 8 hrs per day,to complete a task. 40 employees start the work but after 10 days,20 leave and are replaced by employees who are 1/2 as productive.How many hours per day should the new team work if the work has to be completed in the scheduled timeline?

1. 12
2. 20
3. 10.6
4. 6
5. 30

Source: Experts' Global

generis please help with this question using your method.

Buttercup3 - Sure. The approach, though, works when all workers are equally productive.
When all the workers are not equally productive, we have to finesse the formula a bit.*
These employees are all going to be men. Time is in hours.

Rewrite the standard work formula RT=W by adding (# of workers) to LHS:
(# of workers) * (Rate) * (Time) = Work

Scenario 1, FIRST 10 DAYS - equally productive workers
1) Find the rate of each man
# * R * T = W
# = 40
R = ??
T = 240 (30 days * 8 hrs per day)
W = 1
40 * R * 240 = 1
R = \(\frac{1}{(40)(240)}=\frac{1}{9600}\) = rate of individual man

2) How much work is finished?**
W = # * R * T
# \(= 40\)
\(R = \frac{1}{9600}\)
\(T = 80\) (10 days * 8 hrs per day)
\(W = 40 * \frac{1}{9600} * 80\)
\(W = \frac{3200}{9600}=\frac{1}{3}\)
Work is \(\frac{1}{3}\) finished, \(\frac{2}{3}W\) remains

Scenario 2: NEXT 20 DAYS, workers not equally productive
20 men leave. Replaced by 20 men who are half as productive
Adding individual rates (fast and slow) and simply multiplying by number of men (40) will not work because the workers are not equally productive.

chetan2u shows one way to handle the different levels of productivity.
Pair one fast man with one slow man, add their rates, then multiply by the number of pairs (20 pairs).

You can also find each group's rate (or each "set's" rate), then add them.
Group rate in this context is simply # (of men) * \(R\) (individual man) -- i.e. two of the three variables on LHS

Find each group's / set's rate, then add

• FAST set's rate: (# \(* R) = (20 * \frac{1}{9600}) = \frac{20}{9600}\)
• SLOW set's rate: (# \(* R * \frac{1}{2}) =\)
\((20*\frac{1}{9600}*\frac{1}{2})= \frac{20}{(9600)(2)} = \frac{20}{19200}\)

FAST set + SLOW set = new rate = \(R_2\)

\(R_{2}= (\frac{20}{9600}+\frac{20}{19200})=(\frac{40}{19200} + \frac{20}{19200})=\)
\(\frac{60}{19200}=\frac{6}{1920}= \frac{1}{320} = R_2\)

With \(R_2\) , we have calculated (#\(* R)\) on LHS.
We can substitute \(R_{2}\) for those two variables, thus \(R_2 * T = W\)

Number of hours per day? Total hours divided by number of days

Total hours, \(R_2 * T = W\), so \(T = \frac{W}{R_{2}}\)
\(W = \frac{2}{3}\)
\(R_{2} = \frac{1}{320}\)

\(T = \frac{\frac{2}{3}}{\frac{1}{320}}= \frac{2}{3} * 320 = \frac{640}{3}\) total hours

Hours per day: \(\frac{TotalHours}{NumberOfDays}\)
\(\frac{\frac{640}{3}}{20}= \frac{640}{60} = \frac{64}{6} = \frac{32}{3} \approx{10.66}\approx{10.6}\) hours per day

Answer C

Hope that helps. :-)

* If all 40 workers were replaced by workers half as productive, you would stay with an unmodified (# * R * T) = W
You would: 1) Find "normal" rate 2) Find work finished after 10 days; 3) Find the slower rate (1/2 * R); 4) use the formula straightforwardly. No modifications
**We know this already, from direct proportionality between time and work when rate is constant.

_________________

In the depths of winter, I finally learned
that within me there lay an invincible summer.

-- Albert Camus, "Return to Tipasa"

Intern
Intern
User avatar
B
Joined: 31 Dec 2017
Posts: 19
Concentration: Finance
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 14 Jan 2018, 18:30
1
1
Sangeeta2018 wrote:
40 employees take 30 days,working at 8 hrs per day,to complete a task. 40 employees start the work but after 10 days,20 leave and are replaced by employees who are 1/2 as productive.How many hours per day should the new team work if the work has to be completed in the scheduled timeline?

1. 12
2. 20
3. 10.6
4. 6
5. 30

Source: Experts' Global


Total work \(= 40 * 30 * 8 = 9600\) units

Work done by \(40\) employees in \(10\) days \(= 40*10*8 = 3200\) units.

Remaining work \(= 9600-3200 = 6400\) units.

In order to complete the work on scheduled time \(40\) employees must work for \(\frac{6400}{(40*20)} = 8\) hours a day, but since \(20\) of the current employees are only \(\frac{1}{2}\) as efficient, \(20\) employees with \(100\%\) efficiency would equal to \(10\) with \(50\%\) efficiency, hence the total number of employees can be treated as \(30\).

So, the no. of hours to be worked = \(\frac{6400}{(30*20)} = \frac{6400}{600} = 10.6\). Ans - C.
Manager
Manager
User avatar
B
Joined: 28 Jan 2018
Posts: 54
Location: Netherlands
Concentration: Finance
GMAT 1: 710 Q50 V36
GPA: 3
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 06 Feb 2018, 08:26
Here is my way of solving this problem:

In the first 10 days, the original set of employees did 1/3 of the work, so the remain is 2/3 of the work. After 10 days, 20 of the employees will be replaced with new employees that is half as productive. So:

Original: 40 employees --- 8 h/day --- 30 days --- 1 work
Now : 40 employees --- 8 h/day --- 30 days --- 1/2 + 1/4 = 3/4 work (because new employees are half as productive)

We know from the problem that the new crew needed to increase hours per day to complete the remaining work in 20 days, hence:

40 employees --- 8 h/day --- 30 days --- 3/4 work (the work rate of new crew)
40 employees --- x h/day --- 20 days --- 2/3 work (the remaining work needed to be done in 20 days)

We got the following equation: x/8 * 20/30 = (2/3) / (3/4), equal to x = (12 * 8)/9 = 10.66

Answers C
There was a link to an article to easily solve this kind of problem by Karishma but i can't post in since my post count is way too low
Senior SC Moderator
avatar
V
Joined: 22 May 2016
Posts: 1979
Premium Member CAT Tests
40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 06 Feb 2018, 08:38
hoang221 wrote:

Answers C

There was a link to an article to easily solve this kind of problem by Karishma but i can't post in since my post count is way too low

hoang221 , welcome!

Please send me a PM with the link. I will be happy to post it for you here, with credit to you and VeritasPrepKarishma.
_________________

In the depths of winter, I finally learned
that within me there lay an invincible summer.

-- Albert Camus, "Return to Tipasa"

Senior SC Moderator
avatar
V
Joined: 22 May 2016
Posts: 1979
Premium Member CAT Tests
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 06 Feb 2018, 09:11
hoang221 wrote:
We got the following equation: x/8 * 20/30 = (2/3) / (3/4), equal to x = (12 * 8)/9 = 10.66

Answers C
There was a link to an article to easily solve this kind of problem by @VeritasPrepKarishma but i can't post in since my post count is way too low


The excellent article to which hoang221 refers is Work-Rate Questions Made Easy!
_________________

In the depths of winter, I finally learned
that within me there lay an invincible summer.

-- Albert Camus, "Return to Tipasa"

Target Test Prep Representative
User avatar
G
Status: Head GMAT Instructor
Affiliations: Target Test Prep
Joined: 04 Mar 2011
Posts: 2835
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task.  [#permalink]

Show Tags

New post 08 Feb 2018, 16:37
Sangeeta2018 wrote:
40 employees take 30 days,working at 8 hrs per day,to complete a task. 40 employees start the work but after 10 days,20 leave and are replaced by employees who are 1/2 as productive.How many hours per day should the new team work if the work has to be completed in the scheduled timeline?

1. 12
2. 20
3. 10.6
4. 6
5. 30



The rate for the 40 workers is 1/(30 x 8) = 1/240 task/hour

So after 10 days, the amount of work completed is 1/240 x 10 x 8 = 80/240 = 1/3 of the job and thus 2/3 is left to be completed.

Since 20 workers leave, the rate of the remaining 20 workers is 1/2 x 1/240 = 1/480 task/hour and the 20 new workers who join in have a rate that is half of 1/480, or 1/960, task/hour. Thus the new rate of the 40 workers (20 original and 20 new workers) is 1/480 + 1/960 = 3/960 = 1/320 task/hour.

They still have to finish the task in 20 more days. If we let n = the number of hours they work per day, then it must be true that:

1/320 x 20 x n = 2/3

1/16 x n = 2/3

n = 2/3 x 16

n = 32/3 = 10 ⅔ ≈ 10.6

Alternate Solution:

The number of worker-hours required for the entire job is 40 workers x 30 days x 8 hours/day = 9600 worker-hours. In the first 10 days, the workers have accomplished 40 workers x 10 days x 8 hours/day = 3200 worker-hours, leaving 6400 worker-hours to be accomplished.

The remaining work will be accomplished by 20 original workers plus 20 new workers who work at half-speed. The total amount of work accomplished, then, is equivalent to the work of 30 original workers.

With 6400 worker-hours needing to be done by (the equivalent of) 30 workers, we see that each worker will have to work for 6400/30 ≈ 213.33 hours. This needs to be done in 20 days, so each worker will have to work 213.33/20 ≈ 10.6 hours per day.

Answer: C
_________________

Jeffery Miller
Head of GMAT Instruction

GMAT Quant Self-Study Course
500+ lessons 3000+ practice problems 800+ HD solutions

GMAT Club Bot
Re: 40 employees take 30 days,working at 8 hrs per day,to complete a task. &nbs [#permalink] 08 Feb 2018, 16:37
Display posts from previous: Sort by

40 employees take 30 days,working at 8 hrs per day,to complete a task.

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  

Events & Promotions

PREV
NEXT


Copyright

GMAT Club MBA Forum Home| About| Terms and Conditions and Privacy Policy| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.