GMAT Question of the Day - Daily to your Mailbox; hard ones only

It is currently 15 Oct 2019, 19:16

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel

A and B can do a piece of work in 10 days, while B and C can do the sa

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

Find Similar Topics 
Intern
Intern
avatar
Joined: 11 Sep 2013
Posts: 7
A and B can do a piece of work in 10 days, while B and C can do the sa  [#permalink]

Show Tags

New post Updated on: 26 Feb 2019, 04:39
1
17
00:00
A
B
C
D
E

Difficulty:

  95% (hard)

Question Stats:

57% (03:13) correct 43% (03:37) wrong based on 134 sessions

HideShow timer Statistics

A and B can do a piece of work in 10 days, while B and C can do the same work in 15 days and C and A in 25 days. they started working together, after 4 days A left. After another 4 days B left. In how many days C can finish the remaining work?

A. 16
B. 32
C. 64
D. 96
E. None of These

Originally posted by Emdadul28 on 08 Nov 2016, 02:45.
Last edited by Bunuel on 26 Feb 2019, 04:39, edited 2 times in total.
Edited the question.
Most Helpful Expert Reply
Math Expert
User avatar
V
Joined: 02 Sep 2009
Posts: 58340
Re: A and B can do a piece of work in 10 days, while B and C can do the sa  [#permalink]

Show Tags

New post 08 Nov 2016, 03:03
6
4
Emdadul28 wrote:
A and B can do a piece of work in 10 days, while B and C can do the same work in 15 days and C and A in 25 days. they started working together, after 4 days A left. After another 4 days B left. In how many days C can finish the remaining work?

A. 16
B. 32
C. 64
D. 96
E. None of These


Let the rates of A, B and C be a, b, and c respectively.

A and B can do a piece of work in 10 days: a + b = 1/10;
B and C can do the same work in 15 days: b + c = 1/15;
C and A can do the same work in 25 days: c + a = 1/25.

Sum the above 3 equations: 2(a + b + c) = 31/150 --> a + b + c = 31/300
Subtract a + b = 1/10 from above to get c = 1/300.

For 4 days all 3 worked and completed 4*(a + b + a) = 124/300 of the work.
For the next 4 days B and C worked and they completed 4(b + c) = 4/15 = 80/300 of the work.

So, by the time C is left alone 1 - (124/300 + 80/300) = 96/300 of the work is left to be completed by C alone.
Time = Job/Rate = (96/300)/(1/300) = 96 days.

Answer: D.
_________________
General Discussion
Intern
Intern
avatar
Joined: 11 Sep 2013
Posts: 7
Re: A and B can do a piece of work in 10 days, while B and C can do the sa  [#permalink]

Show Tags

New post 08 Nov 2016, 05:01
Bunuel wrote:
Emdadul28 wrote:
A and B can do a piece of work in 10 days, while B and C can do the same work in 15 days and C and A in 25 days. they started working together, after 4 days A left. After another 4 days B left. In how many days C can finish the remaining work?

A. 16
B. 32
C. 64
D. 96
E. None of These


Let the rates of A, B and C be a, b, and c respectively.

A and B can do a piece of work in 10 days: a + b = 1/10;
B and C can do the same work in 15 days: b + c = 1/15;
C and A can do the same work in 25 days: c + a = 1/25.

Sum the above 3 equations: 2(a + b + c) = 31/150 --> a + b + c = 31/300
Subtract a + b = 1/10 from above to get c = 1/300.

For 4 days all 3 worked and completed 4*(a + b + a) = 124/300 of the work.
For the next 4 days B and C worked and they completed 4(b + c) = 4/15 = 80/300 of the work.

So, by the time C is left alone 1 - (124/300 + 80/300) = 96/300 of the work is left to be completed by C alone.
Time = Job/Rate = (96/300)/(1/300) = 96 days.

Answer: D.


Quote:
Assume that total units of work =LCM (10,15,25) = 60 units

Since A and B finish the work in 10 days, work done by them in a day = 60/10 = 6 units/day

AND B and C finish the work in 15 days, work done by them in a day = 60/15 = 4 units/day

AND C and A finish the work in 20 days, work done by them in a day = 60/20 = 3 units/day


@@@ Thanks for this. Can I do this math like this way? If so then help me to complete this math.
Math Expert
User avatar
V
Joined: 02 Sep 2009
Posts: 58340
Re: A and B can do a piece of work in 10 days, while B and C can do the sa  [#permalink]

Show Tags

New post 08 Nov 2016, 06:35
Emdadul28 wrote:
Bunuel wrote:
Emdadul28 wrote:
A and B can do a piece of work in 10 days, while B and C can do the same work in 15 days and C and A in 25 days. they started working together, after 4 days A left. After another 4 days B left. In how many days C can finish the remaining work?

A. 16
B. 32
C. 64
D. 96
E. None of These


Let the rates of A, B and C be a, b, and c respectively.

A and B can do a piece of work in 10 days: a + b = 1/10;
B and C can do the same work in 15 days: b + c = 1/15;
C and A can do the same work in 25 days: c + a = 1/25.

Sum the above 3 equations: 2(a + b + c) = 31/150 --> a + b + c = 31/300
Subtract a + b = 1/10 from above to get c = 1/300.

For 4 days all 3 worked and completed 4*(a + b + a) = 124/300 of the work.
For the next 4 days B and C worked and they completed 4(b + c) = 4/15 = 80/300 of the work.

So, by the time C is left alone 1 - (124/300 + 80/300) = 96/300 of the work is left to be completed by C alone.
Time = Job/Rate = (96/300)/(1/300) = 96 days.

Answer: D.


Quote:
Assume that total units of work =LCM (10,15,25) = 60 units

Since A and B finish the work in 10 days, work done by them in a day = 60/10 = 6 units/day

AND B and C finish the work in 15 days, work done by them in a day = 60/15 = 4 units/day

AND C and A finish the work in 20 days, work done by them in a day = 60/20 = 3 units/day


@@@ Thanks for this. Can I do this math like this way? If so then help me to complete this math.


You can continue basically exactly the same way with this approach.
_________________
Senior Manager
Senior Manager
avatar
Joined: 06 Jun 2016
Posts: 256
Location: India
Concentration: Operations, Strategy
Schools: ISB '18 (D)
GMAT 1: 600 Q49 V23
GMAT 2: 680 Q49 V34
GPA: 3.9
Re: A and B can do a piece of work in 10 days, while B and C can do the sa  [#permalink]

Show Tags

New post 08 Nov 2016, 07:06
Emdadul28 wrote:
Bunuel wrote:
Emdadul28 wrote:
A and B can do a piece of work in 10 days, while B and C can do the same work in 15 days and C and A in 25 days. they started working together, after 4 days A left. After another 4 days B left. In how many days C can finish the remaining work?

A. 16
B. 32
C. 64
D. 96
E. None of These


Let the rates of A, B and C be a, b, and c respectively.

A and B can do a piece of work in 10 days: a + b = 1/10;
B and C can do the same work in 15 days: b + c = 1/15;
C and A can do the same work in 25 days: c + a = 1/25.

Sum the above 3 equations: 2(a + b + c) = 31/150 --> a + b + c = 31/300
Subtract a + b = 1/10 from above to get c = 1/300.

For 4 days all 3 worked and completed 4*(a + b + a) = 124/300 of the work.
For the next 4 days B and C worked and they completed 4(b + c) = 4/15 = 80/300 of the work.

So, by the time C is left alone 1 - (124/300 + 80/300) = 96/300 of the work is left to be completed by C alone.
Time = Job/Rate = (96/300)/(1/300) = 96 days.

Answer: D.


Quote:
Assume that total units of work =LCM (10,15,25) = 60 units LCM(10,15,25)=300

Since A and B finish the work in 10 days, work done by them in a day = 60/10 = 6 units/day 300/10= 30 units

AND B and C finish the work in 15 days, work done by them in a day = 60/15 = 4 units/day 300/15= 20 units

AND C and A finish the work in 20 days, work done by them in a day = 60/20 = 3 units/day
AND C and A finish the work in 25 days, work done by them in a day = 300/25 = 12 units/day


Certain data have been wrongly noted down

@@@ Thanks for this. Can I do this math like this way? If so then help me to complete this math.
Board of Directors
User avatar
D
Status: QA & VA Forum Moderator
Joined: 11 Jun 2011
Posts: 4778
Location: India
GPA: 3.5
WE: Business Development (Commercial Banking)
GMAT ToolKit User
Re: A and B can do a piece of work in 10 days, while B and C can do the sa  [#permalink]

Show Tags

New post 08 Nov 2016, 11:01
3
Emdadul28 wrote:
A and B can do a piece of work in 10 days, while B and C can do the same work in 15 days and C and A in 25 days. they started working together, after 4 days A left. After another 4 days B left. In how many days C can finish the remaining work?

A. 16
B. 32
C. 64
D. 96
E. None of These


Let the total work be 150 units

Efficiency of A + B = 15 units/day
Efficiency of B + C = 10 units/day
Efficiency of A + C = 6 units/day

Efficiency of A + B + C = 15.5 units/day

So, Efficiency of A is = Efficiency of A + B + C - Efficiency of B + C

Or, Efficiency of A is = 15.5 - 10

Or, Efficiency of A is = 5.5

Similarly Efficiency of B is = 9.5 and, Efficiency of C is = 0.50


Quote:
they started working together, after 4 days A left.


Work done by A + B + C in 4 days is 15.5*4 = 62

Now, B + C works

Quote:
After another 4 days B left.


Work done by B + C in 4 days is 10*4 = 40 units

So, total work done is 102 units, and work left is 48 units..

Time taken by C to finish this work is \(\frac{48}{0.5}\) = 96 days...

Hence, answer will be (D) 96 days..

_________________
Thanks and Regards

Abhishek....

PLEASE FOLLOW THE RULES FOR POSTING IN QA AND VA FORUM AND USE SEARCH FUNCTION BEFORE POSTING NEW QUESTIONS

How to use Search Function in GMAT Club | Rules for Posting in QA forum | Writing Mathematical Formulas |Rules for Posting in VA forum | Request Expert's Reply ( VA Forum Only )
SVP
SVP
User avatar
P
Joined: 03 Jun 2019
Posts: 1689
Location: India
Premium Member Reviews Badge CAT Tests
Re: A and B can do a piece of work in 10 days, while B and C can do the sa  [#permalink]

Show Tags

New post 12 Aug 2019, 22:22
Emdadul28 wrote:
A and B can do a piece of work in 10 days, while B and C can do the same work in 15 days and C and A in 25 days. they started working together, after 4 days A left. After another 4 days B left. In how many days C can finish the remaining work?

A. 16
B. 32
C. 64
D. 96
E. None of These


Given: A and B can do a piece of work in 10 days, while B and C can do the same work in 15 days and C and A in 25 days. they started working together, after 4 days A left. After another 4 days B left.

Asked: In how many days C can finish the remaining work?

Let us assume that A, B & C can finish the job in a, b & c days respectively

A and B can do a piece of work in 10 days
\(\frac{1}{a} + \frac{1}{b} = \frac{1}{10}\) (1)
B and C can do the same work in 15 days
\(\frac{1}{b} + \frac{1}{c} = \frac{1}{15}\) (2)
C and A can do the same work in 25 days
\(\frac{1}{c} + \frac{1}{a} = \frac{1}{25}\) (3)

Adding (1) + (2) + (3)
\(2 (\frac{1}{a} + \frac{1}{b}+ \frac{1}{c}) = \frac{1}{10} + \frac{1}{15} + \frac{1}{25} = \frac{31}{150}\)
\frac{1}{a} + \frac{1}{b}+ \frac{1}{c} = \frac{31}{300}[/m] (4)


they started working together, after 4 days A left
In 4 days, work completed = \(4 * \frac{31}{300} = \frac{124}{300}\)
After 4 days, work balance = 1 - \frac{124}{300} = \frac{176}{300} = \frac{44}{75}

Balance work is done by B & C together for 4 days
After another 4 days B left.
Work done by B & C in 4 days\(= 4 * \frac{1}{15} = \frac{4}{15}\)

Work balance = \(\frac{44}{75} - \frac{4}{15} = \frac{24}{75} = \frac{8}{25}\)

Balance work is done by C alone
\(\frac{1}{c} = \frac{31}{300} - \frac{1}{10} = \frac{1}{300}\)
No of days taken by C \(= \frac{8}{25}/\frac{1}{300} = \frac{8*300}{25} = 96\)

IMO D
_________________
"Success is not final; failure is not fatal: It is the courage to continue that counts."

Please provide kudos if you like my post. Kudos encourage active discussions.

My GMAT Resources: -

Efficient Learning
All you need to know about GMAT quant

Tele: +91-11-40396815
Mobile : +91-9910661622
E-mail : kinshook.chaturvedi@gmail.com
Senior Manager
Senior Manager
User avatar
P
Joined: 16 Jan 2019
Posts: 471
Location: India
Concentration: General Management
WE: Sales (Other)
Re: A and B can do a piece of work in 10 days, while B and C can do the sa  [#permalink]

Show Tags

New post 12 Aug 2019, 22:35
Let the total work be 300 units

A+B = 30 units/day
B+C = 20 units/day
A+C = 12 units/day

2(A+B+C) = 62 units/day
A+B+C = 31 units/day

Substituting for A+B,

30+C = 31 units/day
C=1 unit/day

In the first 4 days, work done = 31*4 = 124 units
In the next 4 days, work done = 20*4 = 80 units

This leaves [300-(124+80)] = 96 units of work to be done.

Since C works at only 1 unit/day, C will need 96 days to complete the remaining work

Answer is (D)
GMAT Club Bot
Re: A and B can do a piece of work in 10 days, while B and C can do the sa   [#permalink] 12 Aug 2019, 22:35
Display posts from previous: Sort by

A and B can do a piece of work in 10 days, while B and C can do the sa

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  





Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne