Last visit was: 19 Nov 2025, 02:38 It is currently 19 Nov 2025, 02:38
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
ShalabhsQuants
Joined: 01 Jun 2012
Last visit: 03 Mar 2021
Posts: 5
Own Kudos:
98
 [55]
Posts: 5
Kudos: 98
 [55]
4
Kudos
Add Kudos
51
Bookmarks
Bookmark this Post
Most Helpful Reply
avatar
mandyrhtdm
Joined: 05 Jul 2012
Last visit: 09 Mar 2013
Posts: 53
Own Kudos:
174
 [15]
Given Kudos: 8
Location: India
Concentration: Finance, Strategy
GMAT Date: 09-30-2012
GPA: 3.08
WE:Engineering (Energy)
Posts: 53
Kudos: 174
 [15]
10
Kudos
Add Kudos
5
Bookmarks
Bookmark this Post
General Discussion
User avatar
EvaJager
Joined: 22 Mar 2011
Last visit: 31 Aug 2016
Posts: 514
Own Kudos:
2,325
 [4]
Given Kudos: 43
WE:Science (Education)
Posts: 514
Kudos: 2,325
 [4]
2
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
User avatar
Kmohan1
Joined: 15 Jul 2018
Last visit: 22 Feb 2025
Posts: 10
Given Kudos: 19
Posts: 10
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
In one hour, A does 1/8 of work, B does 1/24 of work and C does 1/48 of work. Since the question states that the machines work on every alternative hour, eg A for the first hour, B for the second hour, and C for the third hour. For any multiples of 3, all 3 machines perform equal hours. In case the hours are 3n+1 ie 1 more than the multiple of 3, the one hour can be added to A, B or C. in case of 3n+2 hours, the additional 2 hours are added to pair of machines ie both to A and B or B and C etc.
For the minimum number of hours taken by all 3, most of the time should be assigned to the machine that does the most work. 15 is thus rejected, since for within 15 hours, all the 3 machines will have to work for 5 hours. Considering 15.5 hours, the number of hours can be distribution in the below fashion, 5 complete cycle of A-B-C and an extra 0.5 to A.
5.5/8 +5/24 + 5/48 = 48/48 hence this is the minimum number of hours.
For maximum number of hours, most of the time should be assigned to the machine that does the least amount of work. Because 17 is a whole number I will choose that. 5 cycles of C-B-A and additional 1 hour for machine C and 1 hour for machine B. 6/48+ 6/24 + 5/24= 48/48- this is the maximum number of hours­
User avatar
PSKhore
Joined: 28 Apr 2025
Last visit: 18 Nov 2025
Posts: 173
Own Kudos:
Given Kudos: 105
Products:
Posts: 173
Kudos: 27
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Lets take the total work done as the LCM of 8,24,48 = 48
So the total work is 48 units
Individual work in units :
A = 48/8 = 6 units
B = 48/24 = 2 units
C = 48/48 = 1 unit
Total work in 3 hours is 9 units
Now 48/9 = 5.xx X 3 = 15.xx
remaining units = 3 units
if A + B work together in 2 hours we can complete the 3 units work.
therefore maximum will be 17 hours

if we want the minimum time to complete those 3 units, we can ask A
A will complete 3 units in half an hour
So, minimum will be 15.5 hours
User avatar
xyzKunal
Joined: 28 Oct 2024
Last visit: 16 Nov 2025
Posts: 5
Own Kudos:
Given Kudos: 16
GMAT Focus 1: 715 Q90 V86 DI80
GMAT Focus 1: 715 Q90 V86 DI80
Posts: 5
Kudos: 2
Kudos
Add Kudos
Bookmarks
Bookmark this Post
This is a simple approach that does not need much calculation-

Let, Work = 48 (LCM of 8,24,48)
so, Rate of a = 6 unit of work an hour
rate of b = 2 unit of work an hour
rate of c = 1 unit of work an hour.

In 3 hours (working simultaneously), they complete 9 units of work.
in 15 hours, they complete 45 units.

Remaining 3 units, will give us the answer.
SLOWEST- C complete 1 unit and B complete 2 unit. ( total- 15+2 = 17 hours)
FASTEST - A complete the 3 units in 1/2 hour (total- 15+0.5 = 15.5 hours)
User avatar
mkeshri185
Joined: 01 May 2025
Last visit: 19 Nov 2025
Posts: 90
Own Kudos:
Given Kudos: 1
Posts: 90
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I took almost same approach. The remaining work is 1/16
Now to finish this in minimum time we are assigning it to the fastest worker that is A and getting the min time.
But for the fastest time why are we not considering assigning it to the slowest worker that is C? or to the second slowest worker that is B? Why are we combining B and C?
EvaJager


If A, B, and C each work for an hour, in a total of 3 hours they accomplish \(\frac{1}{8}+\frac{1}{24}+\frac{1}{48}=\frac{9}{48}=\frac{3}{16}\) of the entire job.
After 5 such cycles, a total of 5 x 3 = 15 hours, they accomplish \(\frac{15}{16}\) of the entire job. For the remaining 1/16th of the job, if it is the slowest worker's turn to work (this is C), another 1/48th is accomplished, then B would do another 1/24th, which gives the missing \(\frac{1}{48}+\frac{1}{24}=\frac{3}{48}=\frac{1}{16}\) of the job. So, the maximum time is 5 x 3 + 2 =17 hours. Choice (D,B) (row, column)

For the minimum time, after the 5 cycles of 3 hours, the fastest worker, which is A, needs just 1/2 an hour to do the remaining 1/16th of the job.
So, minimum time is 5 x 3 + 0.5 =15.5 hours. Choice (B,A) (row, column)
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 Nov 2025
Posts: 105,379
Own Kudos:
Given Kudos: 99,977
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 105,379
Kudos: 778,173
Kudos
Add Kudos
Bookmarks
Bookmark this Post
mkeshri185
I took almost same approach. The remaining work is 1/16
Now to finish this in minimum time we are assigning it to the fastest worker that is A and getting the min time.
But for the fastest time why are we not considering assigning it to the slowest worker that is C? or to the second slowest worker that is B? Why are we combining B and C?


Your doubt is not clear. To minimize the time, you assign the remaining work to the fastest worker, A, because A completes the task the quickest. To maximize the time, you would assign the remaining work to the slowest worker, C, or a combination of slower workers like B and C.
What is unclear there?
User avatar
mkeshri185
Joined: 01 May 2025
Last visit: 19 Nov 2025
Posts: 90
Own Kudos:
Given Kudos: 1
Posts: 90
Kudos: 1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Oh my mistake i got why we are not considering only C to complete the rem work which is 1/16 bcz C would take 3 hrs to do 1/16 work but people are allowed to work for 1 hr at a time only so we can't consider C to do the whole of the rest work. Same with the B which would also take more than 1 hr to complete the rem work. So from this its clear that some part of the remaining part will be done by B and some part by C (bcz they are the slowest so we are combining them)
Bunuel


Your doubt is not clear. To minimize the time, you assign the remaining work to the fastest worker, A, because A completes the task the quickest. To maximize the time, you would assign the remaining work to the slowest worker, C, or a combination of slower workers like B and C.
What is unclear there?
Moderators:
Math Expert
105379 posts
496 posts