GMAT Question of the Day - Daily to your Mailbox; hard ones only

It is currently 20 Jun 2019, 01:14

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel

A furniture manufacturer has two machines, but only one can

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

 
Intern
Intern
avatar
Joined: 19 Dec 2009
Posts: 27
A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 07 Jan 2011, 11:33
3
24
00:00
A
B
C
D
E

Difficulty:

  75% (hard)

Question Stats:

60% (03:05) correct 40% (03:03) wrong based on 727 sessions

HideShow timer Statistics

A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

A. 14
B. 13
C. 11
D. 9
E. 7
Most Helpful Expert Reply
Math Expert
User avatar
V
Joined: 02 Sep 2009
Posts: 55719
Re: work rates  [#permalink]

Show Tags

New post 07 Jan 2011, 11:50
11
14
rtaha2412 wrote:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

14
13
11
9
7


Machine A needs 12 days * 2 shifts = 24 shifts to do the whole job;
Machine B needs 15 days * 2 shifts = 30 shifts to do the whole job;

In one day each machine works 1.5 shifts (3/2 shifts), doing (3/2)/24+(3/2)/30)=9/80 th of the whole job in one day, thus with the current work schedule they'll need 80/9=~9 days.

Answer: D.
_________________
Most Helpful Community Reply
Intern
Intern
avatar
Joined: 17 May 2013
Posts: 1
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 31 May 2013, 19:42
5
1
rtaha2412 wrote:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

A. 14
B. 13
C. 11
D. 9
E. 7



Machine A: 12 days to complete task working two shifts -> 24 days working one shift -> 48 days working half shifts
Machine B: 15 days to complete task working two shifts -> 30 days working one shift -> 60 days working half shifts

In one day, each works 3 half shifts, so: 3 * (1/48 + 1/60) -> 1/16 + 1/20 = 9/80 of job per day, so ~ 9 days to complete total job.
General Discussion
Manager
Manager
avatar
Joined: 28 Aug 2010
Posts: 170
Re: work rates  [#permalink]

Show Tags

New post 26 Feb 2011, 18:02
1
Bunuel.... please could you point out anymore questions of this type ? Thanks for all your help.
Math Expert
User avatar
V
Joined: 02 Sep 2009
Posts: 55719
Re: work rates  [#permalink]

Show Tags

New post 26 Feb 2011, 18:04
1
Math Expert
User avatar
V
Joined: 02 Sep 2009
Posts: 55719
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 30 May 2013, 05:10
1
Manager
Manager
avatar
Joined: 27 Feb 2012
Posts: 117
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 01 Jun 2013, 01:04
1
Quote:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

A. 14
B. 13
C. 11
D. 9
E. 7


Let us look for LCM f 15 and 12. Say 60 is total work.
A completes in 12 days 2 shifts which means it works 2.5 hrs per shift. (60/12 = 5 hrs two shifts)
Similarly B completes in 15 days or works 2 hrs per shift.
Now, per day work as per shift plan 2.5 (A) + 2 (B) + (2.5 + 2)/2 (A and B combined) = 6.75 hrs per day
Total time = 60/6.75 which comes around 9 days.
_________________
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Please +1 KUDO if my post helps. Thank you.
Intern
Intern
avatar
Joined: 06 May 2013
Posts: 8
GMAT 1: 660 Q48 V34
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 22 Jun 2013, 15:49
4
machine A finish the job in 2*12 shifts = 24 shifts
machine B finish the job in 2*15 shifts = 30 shifts

Lets assume total work require 120 shifts

Therefore,
rate of A = 5 shifts/day
rate of B = 4 shifts/day
rate of (A+B) = 9 shifts/day

According to current schedule work complete in a day = 5+4+(9/2) =13.5 shifts/day

Therefore, Time required to finish 120 shifts = (120/13.5) = 8.88.. days ~ 9 days
Manager
Manager
avatar
Joined: 09 Jan 2013
Posts: 53
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 26 Sep 2013, 01:31
Machines A & B work for 1.5 shifts a day.
So, in 2 days 3 shifts.(imagine 2 days=1 schedule)

A's production rate 12 days 2 shifts, so in 1 schedule rate is 8.
B's production rate 15 days 2 shifts, so in 1 schedule rate is 10

This implies: T=8*10/8+10 = 80/18 (for 1 schedule)
and we know 1 schedule is of 2 days,

(80/18)*2 = 9days (Approx)

Hence D. :)
Manager
Manager
avatar
Joined: 26 Sep 2013
Posts: 190
Concentration: Finance, Economics
GMAT 1: 670 Q39 V41
GMAT 2: 730 Q49 V41
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 20 Nov 2013, 10:41
1
rtaha2412 wrote:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

A. 14
B. 13
C. 11
D. 9
E. 7


I actually got one of these right!!!!!!!!!!!!!!!! First time in about 80 attempts at a work rate problem! I'm so happy

So based on the info given, it takes 24 shifts for A to complete the job, and 30 shifts for B to complete the job, if they each worked independently. So the rate for A is 1/24 and for B 1/30. If each day they're working 1.5 shifts, then each day A completes 1.5/24 (which equals 1/16) and B is completing 1.5/30 (which equals 20). Finding a common denominator of 80, their total work per day combined is 9/80. Thus after working 1.5 shifts each per day for 9 days they'll have completed the whole job (8/9ths through the 9th day).
Retired Moderator
User avatar
Joined: 20 Dec 2013
Posts: 171
Location: United States (NY)
GMAT 1: 640 Q44 V34
GMAT 2: 710 Q48 V40
GMAT 3: 720 Q49 V40
GPA: 3.16
WE: Consulting (Venture Capital)
GMAT ToolKit User Reviews Badge
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 26 Dec 2013, 00:04
curious why some questions will specify an "approx" solution and provide rounded answer choices, others will not, however provide fractional answers (when applicable), and then others, such as above, will do neither/both? I understand the above job wasn't done until partly into the 8th day, so it did take 9 days to complete...

Bunuel, is a question such as the above fair game on the test? I have been under the impression that the answer choices will be exact, unless the question specifies an "approx" solution or the answer choices are based on objects that can't be physically split (people, cars, etc)...isn't a day an interval and/or unit of measure? thank you.
_________________
Director
Director
User avatar
G
Affiliations: CrackVerbal
Joined: 03 Oct 2013
Posts: 564
Location: India
GMAT 1: 780 Q51 V46
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 26 Dec 2013, 00:59
rtaha2412 wrote:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

A. 14
B. 13
C. 11
D. 9
E. 7


Let us say that the total work is of 240 units

A ---- 12 days ---- 2 shifts ----- 10 units per shift

B ---- 15 days ---- 2 shifts ----- 8 units per shift

When they work together A + B + (A+B)/2 = 10 + 8 + 9 = 27 units per shift

Every 3 shifts ---- 27 units
x 8 x 8

Every 24 shifts ---- 216 units

26 shifts ----- 216 + 18 = 234

In 27th shift the work will get finishe

1 Day ---- 3 shifts hence total days taken = 27/3 = 9 days

Pushpinder Gill
_________________
- CrackVerbal Prep Team

For more info on GMAT and MBA, follow us on @AskCrackVerbal

Register for the Free GMAT Kickstarter Course : http://bit.ly/2DDHKHq

Register for our Personal Tutoring Course : https://www.crackverbal.com/gmat/personal-tutoring/

Join the free 4 part GMAT video training series : http://bit.ly/2DGm8tR
Retired Moderator
User avatar
S
Joined: 14 Dec 2013
Posts: 2871
Location: Germany
Schools: German MBA
GMAT 1: 780 Q50 V47
WE: Corporate Finance (Pharmaceuticals and Biotech)
GMAT ToolKit User Reviews Badge
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 26 Dec 2013, 01:46
rtaha2412 wrote:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

A. 14
B. 13
C. 11
D. 9
E. 7

The clause "while both work half of the third shift" is confusing. The phrase "each work half of the third phrase" would have had more clarity.
Manager
Manager
User avatar
Joined: 10 Mar 2013
Posts: 185
GMAT 1: 620 Q44 V31
GMAT 2: 690 Q47 V37
GMAT 3: 610 Q47 V28
GMAT 4: 700 Q50 V34
GMAT 5: 700 Q49 V36
GMAT 6: 690 Q48 V35
GMAT 7: 750 Q49 V42
GMAT 8: 730 Q50 V39
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 08 Jan 2014, 21:11
This question should have asked "approximately" how many days will it take for the machines to do the job.
Veritas Prep GMAT Instructor
User avatar
D
Joined: 16 Oct 2010
Posts: 9337
Location: Pune, India
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 08 Jan 2014, 22:17
1
TooLong150 wrote:
This question should have asked "approximately" how many days will it take for the machines to do the job.


'Approximately' could actually make such a question ambiguous. Not this one though but a similar question with the answer as 9.2 days. You round off 8.89 days as 9 days and everything is fine in this question. What do you do when you get 9.2 days? Do you need 9 days or 10 days? Can you round off 9.2 as 9 even though that is what you do with numbers? No, because in 9 days your work is not over. You do need 10 days.

To finish a work say you need to work full 9 days and a part of the 10th day. If I ask you how many days do you need to complete the work, will you say 9 or 10? You will say 10 even if you don't use the 10th day fully.
_________________
Karishma
Veritas Prep GMAT Instructor

Learn more about how Veritas Prep can help you achieve a great GMAT score by checking out their GMAT Prep Options >
Intern
Intern
avatar
B
Joined: 17 Oct 2013
Posts: 40
Schools: HEC Dec"18
GMAT Date: 02-04-2014
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 08 Jan 2014, 23:26
3
rtaha2412 wrote:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

A. 14
B. 13
C. 11
D. 9
E. 7



in one shift, A can do 1/24 of the work
in one shift, B can do 1/30 of the work
no of days required for the completion of the task by A and B together in the current schedule is (3/2)*((1/24)+(1/30))*t=1
t=8.888=9
Director
Director
User avatar
S
Joined: 17 Dec 2012
Posts: 630
Location: India
A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 06 Jun 2017, 03:53
1
rtaha2412 wrote:
A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?

A. 14
B. 13
C. 11
D. 9
E. 7

1 .Each machine works 1.5 shifts a day
2. Machine A can do the job in 24 shifts or 16 days
3. Machine B can do the job in 30 shifts or 20 days.
4. Both together can do the job in 1/ (1/16 + 1/20) = 80/9= 9 days
_________________
Srinivasan Vaidyaraman
Sravna Test Prep
http://www.sravnatestprep.com

Holistic and Systematic Approach
Intern
Intern
User avatar
B
Joined: 06 Sep 2018
Posts: 37
GMAT 1: 760 Q50 V44
GMAT 2: 740 Q48 V44
Reviews Badge
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 19 Oct 2018, 09:58
Hi, if the GMAT says "how many days will it take to do the job" shouldn't the answer choices be exact? Otherwise it would say "approximately" correct? This is confusing me big time. I'll be grateful if someone could help me clarify! Thanks!
Intern
Intern
avatar
B
Joined: 10 Dec 2017
Posts: 26
Location: India
Concentration: Entrepreneurship, Social Entrepreneurship
GMAT 1: 710 Q48 V42
GPA: 3.41
Re: A furniture manufacturer has two machines, but only one can  [#permalink]

Show Tags

New post 21 Oct 2018, 02:09
A requires 12 days working 2shifts.
So working one shift it requires 24 days. Similarly b requires 30 days.
Also together they work half shift so further divide by 2.

The equation becomes 1/24+1/30+9/240

Which gives 27/240.
Reciprocal gives 9days
GMAT Club Bot
Re: A furniture manufacturer has two machines, but only one can   [#permalink] 21 Oct 2018, 02:09
Display posts from previous: Sort by

A furniture manufacturer has two machines, but only one can

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  


Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne