Last visit was: 19 May 2026, 18:33 It is currently 19 May 2026, 18:33
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
PriyamRathor
Joined: 17 Aug 2021
Last visit: 24 May 2024
Posts: 146
Own Kudos:
125
 [8]
Given Kudos: 161
Location: India
WE:Corporate Finance (Accounting)
Posts: 146
Kudos: 125
 [8]
1
Kudos
Add Kudos
7
Bookmarks
Bookmark this Post
User avatar
gmatophobia
User avatar
Quant Chat Moderator
Joined: 22 Dec 2016
Last visit: 10 May 2026
Posts: 3,173
Own Kudos:
11,578
 [4]
Given Kudos: 1,860
Location: India
Concentration: Strategy, Leadership
Posts: 3,173
Kudos: 11,578
 [4]
3
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
chetan2u
User avatar
GMAT Expert
Joined: 02 Aug 2009
Last visit: 18 May 2026
Posts: 11,239
Own Kudos:
45,209
 [1]
Given Kudos: 337
Status:Math and DI Expert
Location: India
Concentration: Human Resources, General Management
GMAT Focus 1: 735 Q90 V89 DI81
Products:
Expert
Expert reply
GMAT Focus 1: 735 Q90 V89 DI81
Posts: 11,239
Kudos: 45,209
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Apeksha2101
Joined: 31 May 2018
Last visit: 06 Jun 2025
Posts: 41
Own Kudos:
Given Kudos: 28
Posts: 41
Kudos: 10
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I calculated total work = 40 x 30 = 1200, why can't we use this as total work.
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 19 May 2026
Posts: 110,698
Own Kudos:
815,795
 [1]
Given Kudos: 106,315
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 110,698
Kudos: 815,795
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Apeksha2101
A group of 40 mechanics working together have to complete a piece of work in 30 days . If all the mechanics work at constant rate and after 20 days , it was found that only 1/4th of the was completed ,then how many more mechanics should be recruited so that work gets completed on time ?

A. 32
B. 100
C. 200
D. 240
E. 280

I calculated total work = 40 x 30 = 1200, why can't we use this as total work.

Because we are not told that 40 mechanics can complete the piece of work in 30 days. Instead, this is the goal. Therefore, we cannot assume the total work equals 40 * 30 units.

The question is actually straightforward:

1/4 of the work took 40 mechanics 20 days. So, the remaining 3/4 of the work would take them 3 times as long, or 60 days. However, we want the work completed in just 10 days, which is 6 times faster. This means the workforce needs to increase 6 times, from 40 to 240 mechanics. Therefore, we need to add 200 more mechanics.

Answer: C.