Last visit was: 16 May 2025, 00:26 It is currently 16 May 2025, 00:26
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
R2I4D
Joined: 23 Dec 2009
Last visit: 26 Oct 2015
Posts: 29
Own Kudos:
174
 [19]
Given Kudos: 7
Concentration: General, Finance, Entrepreneurship
Schools:HBS 2+2
 Q49  V42
GPA: 4.0
WE 1: Consulting
WE 2: Investment Management
Posts: 29
Kudos: 174
 [19]
Kudos
Add Kudos
18
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
onedayill
Joined: 25 Feb 2010
Last visit: 08 Mar 2017
Posts: 207
Own Kudos:
332
 [6]
Given Kudos: 10
Posts: 207
Kudos: 332
 [6]
5
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
cipher
Joined: 25 Jun 2009
Last visit: 04 Aug 2013
Posts: 131
Own Kudos:
345
 [5]
Given Kudos: 6
 Q49  V22 GMAT 2: 700  Q50  V35
Posts: 131
Kudos: 345
 [5]
2
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
General Discussion
avatar
skipjames
Joined: 08 May 2010
Last visit: 10 Mar 2011
Posts: 101
Own Kudos:
Given Kudos: 39
Posts: 101
Kudos: 120
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Without looking at the reveal. I have to say that I think it is not possible for them to complete the project in 8 hours. Thus we can answer the question and the answer is C both statements are needed in combination to complete the answer. The limits of Sally's ability are between 11 and 27 hours solo. Georgia from 3 to 11 hours solo. Lastly Andy 5-13 hours solo. Additively they will not be able to finish the project in the alloted time.

I will check out the reveal and see if I was right.
avatar
skipjames
Joined: 08 May 2010
Last visit: 10 Mar 2011
Posts: 101
Own Kudos:
Given Kudos: 39
Posts: 101
Kudos: 120
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Okay I checked out the reveal and I had it totally upside down. I added up the slowest limit of their work. This seems like a good idea but understanding that Georgia and Andy could do it themselves, (making statement #2 sufficient) was not a possibility that i had explored. Gotta stick to your system. First is #1 sufficient?, then # 2? then the combination? I just assumed that it had to be the combination since Sally was not addressed in #1. Good question.
avatar
pardeepattri
Joined: 31 Mar 2010
Last visit: 18 Sep 2010
Posts: 69
Own Kudos:
90
 [1]
Given Kudos: 45
Posts: 69
Kudos: 90
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Please explain..If statement 2 is sufficient why not statement 1?
User avatar
cipher
Joined: 25 Jun 2009
Last visit: 04 Aug 2013
Posts: 131
Own Kudos:
Given Kudos: 6
 Q49  V22 GMAT 2: 700  Q50  V35
Posts: 131
Kudos: 345
Kudos
Add Kudos
Bookmarks
Bookmark this Post
onedayill
nitishmahajan
pardeepattri
Please explain..If statement 2 is sufficient why not statement 1?

(1) Sally can finish the project alone in 4k+7 hours, where k is a positive integer with a minimum value of 1 and a maximum value of 5.

Insufficient- Because it just mentions that sally can complete the work in between 11( when K=1) hours and 27 ( when k =5) hours but we dont have any info about the rest of the people.

(2) Working alone, Georgia will take 2k+1 hours, and Andy will take 3+2k hours, where k is a positive integer with a minimum value of 1 and a maximum value of 5.

Sufficient -
Georgia can complete the work in between 3 hours and 11 hours ,

Similarly Sally can complete the work in 5 hours and 13 hours

Now lets calculate the worst case scenario for these 2 together ( i.e when K =5 and they take the maximum time to complete the work)

\(\frac{1}{5} + \frac{1}{13} = \frac{1}{x}\)

\(x = \frac{5*13}{5+13} = \frac{65}{18} = 3.6\) ( approx)

So basically Georgia and Sally can complete the work in 3.6 hours even without Andy and hence they all can definitely complete the work within 8 hours.


Looks like a mistake.

it should be

\(\frac{1}{11} + \frac{1}{13} = \frac{1}{x}\)

\(x = \frac{11*13}{11+13} = 5\) ( approx)

Still the answer will be B :P

Oh yeah, thats true, my mistake, it should have been 11 and 13, but anyway answer B will still hold.

Thanks mate
User avatar
AN225
Joined: 29 Sep 2010
Last visit: 01 Mar 2017
Posts: 233
Own Kudos:
Given Kudos: 48
Status:Happy to join ROSS!
Concentration: General Management, Strategy
Products:
Posts: 233
Kudos: 292
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Guys, I am not a native speaker, yet for me 'will' in below sentence:
"If the team of three has to begin work now and no one else can work on this project, will Project Alpha be completed by the deadline?"
means there shall be a 100% guarantee the project will be completed.

However, both gents MAY NEED more than 8 hours to finish the projects, because their number of hours is flexible.

Therefore, for me this question appears as not worded correctly and the answer shall be E.

Alternatively, if we change the question to
"If the team of three has to begin work now and no one else can work on this project, IS THERE A POSSIBILITY for Project Alpha to be completed by the deadline?"
the answers will be B
User avatar
Zatarra
User avatar
Verbal Forum Moderator
Joined: 31 Jan 2010
Last visit: 07 May 2016
Posts: 310
Own Kudos:
Given Kudos: 149
 Q49  V42
WE 1: 4 years Tech
Posts: 310
Kudos: 356
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Ans has to be B,
The slowest rate at which Georgia and Andy can work in 1 hr. is 8/15
In 8 hours, then can do almost 5 times the work
User avatar
gmatchase
Joined: 06 May 2012
Last visit: 23 Aug 2016
Posts: 45
Own Kudos:
Given Kudos: 16
Posts: 45
Kudos: 207
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I couldn't get previous explanations and I found below with an example

Andy, George and Sally are a team of consultants working on Project Alpha. They have an eight hour deadline to complete the project. The team members work at constant rates throughout the eight hour period. If the team of three has to begin work now and no one else can work on this project, will Project Alpha be completed by the deadline?

1.Sally can finish the project alone in 4k + 7 hours, where k is a positive integer with a minimum value of 1 and a maximum value of 5.
2.Working alone, George will take 2k + 1 hours and Andy will take 3 + 2k hours, where k is a positive integer with a minimum value of 1 and a maximum value of 5


Statement 1 as you said is insufficient as we don't have any info about the rates of the other ppl.

From Statement two, Lets assume that a total of 143 pages need to be typed in 8 hrs. For andy and george, Lets assume that k=5 so Andy finishes 143 pages by himself in 13 hrs and George finishes 143 pages by himself in 11 hours.

Andy's Rate=143/13=11 pages/hr So in 8 hrs he will finish 88 pages
George's Rate=143/11=13 pages/hr so in 8 hrs he will finish 104 pages. So in 8 hrs if Andy and George alone can finish 192 pages, with Sally's help they'd we able to finish even more in 8 hrs over exceeding the target of 143 pages. Hence SUFFICIENT.
User avatar
IanStewart
User avatar
GMAT Tutor
Joined: 24 Jun 2008
Last visit: 15 May 2025
Posts: 4,132
Own Kudos:
10,415
 [4]
Given Kudos: 97
 Q51  V47
Expert
Expert reply
Posts: 4,132
Kudos: 10,415
 [4]
4
Kudos
Add Kudos
Bookmarks
Bookmark this Post
R2I4D
Andy, George, and Sally are a team of consultants working on Project Alpha. They have an 8 hour deadline to complete the project. The team members work at constant rates throughout the 8 hour period. If the team of three has to begin work now and no one else can work on this project, will Project Alpha be completed by the deadline?

(1) Sally can finish the project alone in 4k+7 hours, where k is a positive integer with a minimum value of 1 and a maximum value of 5.

(2) Working alone, Georgia will take 2k+1 hours, and Andy will take 3+2k hours, where k is a positive integer with a minimum value of 1 and a maximum value of 5.

The wording in this question is really bad, and not at all GMAT-like. For one thing, there is no need to make k a variable in each statement (a real GMAT question would never do that; instead k would have a single fixed value within the range given - they'd say "where 1 < k < 5"). Then if you choose to combine the statements, because the letters have been turned into variables, it isn't at all clear if the k referred to in Statement 1 must have the same value as the k referred to in Statement 2.

Regardless, one can see why Statement 2 is sufficient fairly quickly. Even in the worst case, Georgia would take 11 hours alone, and Andy 13 hours. Two workers exactly like Andy would take 13/2 = 6.5 hours to do the job. Well, Georgia is faster than Andy, so one worker like Georgia and one worker like Andy must take less time than two workers like Andy, so Andy and Georgia together must take less than 6.5 hours. So even in the worst case, the job is certainly finished in less than 6.5 hours, and the answer is B.
Moderator:
Math Expert
101448 posts