superpus07
Machine A currently takes x hours to complete a certain job. Machine B currently takes y hours to complete the same job. If x=4y, by what percent will x have to decrease so that A and B together can complete the job in \(\frac{3y}{8}\) hours ?
A. 15%
B. 25%
C. 30%
D. 62,5%
E. 85%
Thanks.
The question intends to say that A has increased his rate of work and as a result, the total time taken by both of them has also decreased.
Consider the initial time that was supposed to be taken by both of them.
\(\frac{1}{x} + \frac{1}{y}\) is the combined rate of work.
Since \(x=4y\),
hence combined rate of work will come out to be \(\frac{5y}{4}\).
Since the work is 1 unit, therefore time required at this rate to complete this much of work will be \(\frac{4y}{5}\).
BUT, they are supposed to complete the work in \(\frac{3y}{8}\) hours. So first we calculate the reduction in total time.
\(reduction in time=\frac{4y}{5} - \frac{3y}{8}= \frac{17y}{40}\)
Only A is credited with this reduction of time.
Percentage decrease=4y-[15y/40]/4y
=(29/32)*100.
We need not calculate thsi value because if we see the options, only E is close to this value.
Hence E.