Last visit was: 29 May 2024, 18:17 It is currently 29 May 2024, 18:17
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
SORT BY:
Date
Tags:
Show Tags
Hide Tags
Math Expert
Joined: 02 Sep 2009
Posts: 93518
Own Kudos [?]: 627658 [12]
Given Kudos: 81989
Send PM
Most Helpful Reply
Math Expert
Joined: 02 Sep 2009
Posts: 93518
Own Kudos [?]: 627658 [1]
Given Kudos: 81989
Send PM
General Discussion
Manager
Manager
Joined: 19 Nov 2022
Posts: 58
Own Kudos [?]: 58 [2]
Given Kudos: 30
Location: India
GPA: 4
WE:Consulting (Consulting)
Send PM
Senior Manager
Senior Manager
Joined: 31 Mar 2022
Posts: 268
Own Kudos [?]: 206 [2]
Given Kudos: 19
Location: India
Concentration: General Management, International Business
GMAT 1: 700 Q50 V35
GPA: 2.8
Send PM
Re: 12 Days of Christmas GMAT Competition - Day 5: Amy and Beth, both work [#permalink]
2
Kudos
(1) Amy alone can complete the same task in 8 days
This statement alone is insufficient because we don't know anything about Beth. Further, we also don't know anything about the total work.

(2) Beth alone can complete the same task in 20 days
This statement is insufficient because we don't know anything about Amy. Further, we also don't know anything about the total work.

Now combining 1 and 2
Let's assume total work to be 40 units
Amy per day efficiency= 5 units
Beth per day efficiency= 2 units
Now we know that they started working alternatively
If Amy starts then
Day 1 --> 5 units
Day 2 --> 2 units
Day 3 --> 5 units
Day 4 --> 2 units
Day 5 --> 5 units
Day 6 --> 2 units
Day 7 --> 5 units
Day 8 --> 2 units
Day 9 --> 5 units
Day 10 --> 2 units
Day 11--> 5 units
Work gets completed on 11th day itself.
If Beth starts
Day 1 --> 2 units
Day 2 --> 5 units
Day 3 --> 2 units
Day 4 --> 5 units
Day 5 --> 2 units
Day 6 --> 5 units
Day 7 --> 2 units
Day 8 --> 5 units
Day 9 --> 2 units
Day 10 --> 5 units
Day 11--> 2 units
Day 12--> 3 units
work gets completed on day 12
Therefore combining 1 and 2 is also insufficient
Option E
GMAT Club Legend
GMAT Club Legend
Joined: 03 Jun 2019
Posts: 5220
Own Kudos [?]: 4033 [1]
Given Kudos: 160
Location: India
GMAT 1: 690 Q50 V34
WE:Engineering (Transportation)
Send PM
Re: 12 Days of Christmas GMAT Competition - Day 5: Amy and Beth, both work [#permalink]
1
Kudos
Given: Amy and Beth, both working at their respective constant rates, were assigned a task that they had to complete together. However, they decided to individually work on the task on alternate days till the task gets completed.
Asked: If they started the task from 1st of January, then on which day in January will the task get completed?

Quote:
(1) Amy alone can complete the same task in 8 days.

Since days in which Beth alone can complete the same task is unknown.
NOT SUFFICIENT

Quote:
(2) Beth alone can complete the same task in 20 days

Since days in which Amy alone can complete the same task is unknown.
NOT SUFFICIENT

(1) + (2)
Quote:
(1) Amy alone can complete the same task in 8 days.

Quote:
(2) Beth alone can complete the same task in 20 days


Case 1: Amy started on 1st of January
Task completion = 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8
Task completion requires 11 days and will be completed on 11th January.

Case 2: Beth started on 1st of January
Task completion = 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 1/8 + 1/20 + 3/40
Task completion requires 12 days and will be completed on 12th January.

NOT SUFFICIENT

IMO E
Senior Manager
Senior Manager
Joined: 23 Oct 2015
Posts: 297
Own Kudos [?]: 271 [1]
Given Kudos: 33
Location: United States (NH)
Concentration: Leadership, Technology
Schools: Wharton '25
WE:Information Technology (Non-Profit and Government)
Send PM
Re: 12 Days of Christmas GMAT Competition - Day 5: Amy and Beth, both work [#permalink]
1
Kudos
Condition 1:
We know Amy alone can complete within 8 days, but we don't know how long Beth can take. Then we can't find when the work will complete. Eliminate A and D.

Condition 2:
We know Beth alone can complete within 20 days, but we don't know how long Amy can take. Then we can't find when the work will complete. Eliminate B.

Condition 1 & 2:
We know amount of work both Amy and can do in a day. So,

Every 2 days, the amount of work that can complete is:
1/8 +1/20 = (5+2)/40 = 7/40


But still, we don't know who will start the work.
After 5x2= 10 days, the amount of work completed will be 5x7/40 = 35/40.
If Amy works on 11th day, then the total amount is 35/40+ 1/8 = 1. The work will be done on 11th January.
But, if Beth works on 11th day, then the total amount of work 35/40+1/20 = 37/40. The work will not complete 11th January, but will complete on 12th January.

So 2 answers are possible and we can't say when the work will complete. Eliminate option C.

Hence E is the best answer choice.
Manager
Manager
Joined: 16 Jan 2021
Posts: 51
Own Kudos [?]: 89 [1]
Given Kudos: 5
GMAT 1: 710 Q47 V40
Send PM
Re: 12 Days of Christmas GMAT Competition - Day 5: Amy and Beth, both work [#permalink]
1
Kudos
When we speak about two people doing some work together, we need to know the respective speeds of both of them - otherwise, there's no way of calculating the time they need to finish the task. That being said, conditions 1 and 2 will obviously not suffice separately (options A, B and D are out).

However, will we have enough information from both conditions combined?
Amy's speed will be \(a=\frac{1}{8}=\frac{5}{40}\), and Beth's will look as follows: \(b=\frac{1}{20}=\frac{2}{40}\)

Together, in any two consecutive days, they will manage to do \(a+b=\frac{5}{40} +\frac{ 2}{40} =\frac{ 7}{40}\) of their task. Therefore, after 10 days of work, they will finish \(5*\frac{7}{40} = \frac{35}{40}\).

And here's what the trouble is: now it becomes really important, who starts to work on January 1st. If it's Amy, then on January 11th she'll finish the job.
However, if it's Beth's turn, she will only do a small part, and the task will be finished only the following day by Amy, with \(\frac{35}{40}+\frac{2}{40}+\frac{5}{40} = \frac{42}{40}\).

Therefore, even two options together aren't sufficient, so the answer is E.
Director
Director
Joined: 26 Jan 2019
Posts: 514
Own Kudos [?]: 447 [1]
Given Kudos: 118
Location: India
Send PM
Re: 12 Days of Christmas GMAT Competition - Day 5: Amy and Beth, both work [#permalink]
1
Kudos
Bunuel wrote:
12 Days of Christmas GMAT Competition with Lots of Fun

Amy and Beth, both working at their respective constant rates, were assigned a task that they had to complete together. However, they decided to individually work on the task on alternate days till the task gets completed. If they started the task from 1st of January, then on which day in January will the task get completed?

(1) Amy alone can complete the same task in 8 days
(2) Beth alone can complete the same task in 20 days

 


This question was provided by GMATWhiz
for the 12 Days of Christmas Competition.

Win $30,000 in prizes: Courses, Tests & more

 



(1) Amy alone can complete the same task in 8 days
Cannot find the days required to complete the task as the rate of work of Beth is not available

(2) Beth alone can complete the same task in 20 days
Cannot find the days required to complete the task as the rate of work of Amy is not available

Combining (1) and (2) we get the following scenarios:

a ) Amy starts on the first day and ends on the last day
Let's suppose Beth takes 'n' days to complete, hence
=> (n+1)(1/8) +n(1/20) = 1
=> n(7/40) = 7/8
=> n = 5 days

a ) Amy starts on the first day and Beth ends on the last day
Let's suppose Beth takes 'n' days to complete, hence
=> n(1/8) +n(1/20) = 1
=> n(7/40) = 1
=> n = 40/7 ≈ 6 days

a ) Beth starts on the first day and ends on the last day
Let's suppose Amy takes 'n' days to complete, hence
=> n(1/8) + (n+1)(1/20) = 1
=> n(7/40) = 19/20
=> n = (19/20)
=> n = 38/7 ≈ 6 days

Hence we get different values for the times.

Option E
GMAT Club Bot
Re: 12 Days of Christmas GMAT Competition - Day 5: Amy and Beth, both work [#permalink]
Moderator:
Math Expert
93518 posts