Last visit was: 17 Jul 2025, 13:59 It is currently 17 Jul 2025, 13:59
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Raksat
Joined: 20 Feb 2017
Last visit: 13 Feb 2025
Posts: 151
Own Kudos:
506
 [15]
Given Kudos: 489
Location: India
Concentration: Operations, Strategy
WE:Engineering (Other)
Posts: 151
Kudos: 506
 [15]
1
Kudos
Add Kudos
14
Bookmarks
Bookmark this Post
User avatar
chetan2u
User avatar
GMAT Expert
Joined: 02 Aug 2009
Last visit: 17 Jul 2025
Posts: 11,294
Own Kudos:
41,794
 [3]
Given Kudos: 333
Status:Math and DI Expert
Products:
Expert
Expert reply
Posts: 11,294
Kudos: 41,794
 [3]
1
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
User avatar
Raksat
Joined: 20 Feb 2017
Last visit: 13 Feb 2025
Posts: 151
Own Kudos:
506
 [1]
Given Kudos: 489
Location: India
Concentration: Operations, Strategy
WE:Engineering (Other)
Posts: 151
Kudos: 506
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
JeffTargetTestPrep
User avatar
Target Test Prep Representative
Joined: 04 Mar 2011
Last visit: 05 Jan 2024
Posts: 2,996
Own Kudos:
Given Kudos: 1,646
Status:Head GMAT Instructor
Affiliations: Target Test Prep
Expert
Expert reply
Posts: 2,996
Kudos: 7,945
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Raksat
Sam and David agreed to complete a work in 14 days. They also agreed to forfeit thrice the amount of wages corresponding to the unfinished if they failed to complete the work in 14 days. As they could not complete the work in 14 days, they lost 3/8th of the amount that they would have together received had they completed the work in time. If Sam alone can complete the work in 80 days,the time that David alone would take to complete the work is

A. 20 days
B. 24 days
C. 30 days
D. 35 days
E. 40 days

Since they lost 3/8 of the amount that they would have together received had they completed the job on time and they actually forfeited thrice the amount of wages corresponding to the unfinished, we can relate these two quantities as: ⅜ = 3x, and so x = ⅛, which means that they only had 1/8 of the job unfinished. In other words, they finished 7/8 of the job.

We can let n = the number of days David would take to complete the work alone. We are given that Sam would take 80 days to complete the work alone; thus, his rate would be 1/80, and David’s rate would be 1/n. Since they both worked 14 days, and they finished 7/8 of the job, we can create the following equation:

14 x 1/80 + 14 x 1/n = 7/8

14/80 + 14/n = 7/8

Multiply the equation by 80n we have:

14n + 1120 = 70n

1120 = 56n

n = 1120/56 = 20

Answer: A
User avatar
hellosanthosh2k2
Joined: 02 Apr 2014
Last visit: 07 Dec 2020
Posts: 362
Own Kudos:
Given Kudos: 1,227
Location: India
Schools: XLRI"20
GMAT 1: 700 Q50 V34
GPA: 3.5
Schools: XLRI"20
GMAT 1: 700 Q50 V34
Posts: 362
Kudos: 565
Kudos
Add Kudos
Bookmarks
Bookmark this Post
chetan2u
Raksat
Sam and David agreed to complete a work in 14 days. They also agreed to forfeit thrice the amount of wages corresponding to the unfinished if they failed to complete the work in 14 days. As they could not complete the work in 14 days, they lost 3/8th of the amount that they would have together received had they completed the work in time. If Sam alone can complete the work in 80 days,the time that David alone would take to complete the work is

A. 20 days
B. 24 days
C. 30 days
D. 35 days
E. 40 days

self - made Question


hi...

you would see such Q more frequently in CAT

but let's solve it.

they were to lose thrice the amount of wages of work that was left ....
so if they lost \(\frac{3}{8}\) of work, they did not do \(\frac{3}{8} * \frac{1}{3} = \frac{1}{8}\) of work

In other words they did only \(1-\frac{1}{8} = \frac{7}{8}\) of work
if they do 7/8 of work in 14 days, they will do complete job in 14*8/7 = 16 days..

David's one day work = \(\frac{1}{16}-\frac{1}{80} = \frac{5-1}{80}=\frac{4}{80}=\frac{1}{20}\)
so david does it in 20 days

A

Hi chetan2u, CAT - are you referring to IIM CAT exams?

Thanks
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 37,439
Own Kudos:
Posts: 37,439
Kudos: 1,013
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Hello from the GMAT Club BumpBot!

Thanks to another GMAT Club member, I have just discovered this valuable topic, yet it had no discussion for over a year. I am now bumping it up - doing my job. I think you may find it valuable (esp those replies with Kudos).

Want to see all other topics I dig out? Follow me (click follow button on profile). You will receive a summary of all topics I bump in your profile area as well as via email.
Moderators:
Math Expert
102603 posts
PS Forum Moderator
697 posts