GMAT Question of the Day - Daily to your Mailbox; hard ones only

It is currently 17 Oct 2018, 19:58

Close

GMAT Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel

Solve Time and Work Problems Efficiently using Efficiency Method!

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  
Author Message
TAGS:

Hide Tags

e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post Updated on: 07 Aug 2018, 06:11
7
9
Added the PDF of the article at the end of the post! :)


Solve Time and Work Problems Efficiently using Efficiency Method!


Image


Objective of the article
Why you should read this article?
    • Are you someone who takes a long time to solve Time and Work?
    • Do you get stuck in the fractional and decimal calculation related to Time and Work problems?
    • Do you face problem in understanding how positive and negative efficiency works in Time and Work problems?
If the answer to any of the above questions is yes, then we strongly recommend you continue reading this article.

What will you learn from this article?
In this article, you will learn:
    • The application of LCM to solve Time and Work questions easily.
    • A comparative study of methods of solving Time and Work problems – by using fraction and by using LCM method, which one should be used and when?
    • How efficiency is defined and in what ways it can be implemented in problem solving
In this article, we have only used official sources to help you understand the above aspects. Also, at the end of the article, we have provided some practice questions where you can apply your learning from the article.

Solving Time and Work Problem: Conventional Method
In time and work problem, where people with different constant efficiencies do a certain work, we assume the total work to be constant. Mostly we solve these questions assuming the total work to be 1 unit. Let’s look at the following example:

e-GMAT Example 1
It would take one machine 4 hours to complete a large production order and another machine 3 hours to complete the same order. How many hours would it take both machines, working simultaneously at their respective constant rates, to complete the order?

Solution 1A: Conventional Method

Image


Here it is given that two machines, working independently with their different constant efficiency, complete a large production order in 4 hours and 3 hours respectively.
    • As the total work done by both the machines are same, the work is constant here.
Let us assume the total work of production order is 1 unit. Therefore, we can say:
    • 1st machine in 4 hours can compete 1 unit of work
      • Hence, 1st machine in 1 hour can complete \(\frac{1}{4}\) units of work
    • Similarly, 2nd machine in 3 hours can complete 1 unit of work
      • Hence, 2nd machine in 1 hour can complete \(\frac{1}{3}\) units of work
    • If both the machines work together simultaneously, then in 1 hour they will complete (\(\frac{1}{4} + \frac{1}{3}\)) units of work = \(\frac{(3+4)}{12}\) units of work = \(\frac{7}{12}\) units of work
    • As the machines can complete \(\frac{7}{12}\) units of work in 1 hour time, to complete the whole work of 1 unit, they will take = \(\frac{1}{(7/12)}\) hours = \(\frac{12}{7}\) hours

Hence, working together, both the machines will take \(\frac{12}{7}\) hours to complete the production order.

Important observation
In the beginning of the solution, we have assumed the total constant work to be 1 unit.
    • Important thing one can observe here is that assuming the total work to be 1 unit or x units can make life difficult for us – because, when we calculate the 1-day work of that person or machine, chances are very high that we will be getting fractional values.
Now we all know, dealing with fractional calculations can be difficult and it increases the chances of making error to a great extent. But the question is how we can avoid it?
Again, if you look carefully, the 1-day work of a person or a machine is calculated as the ratio of total work and the time taken.
    • Therefore, if the assumed value of the total work is a multiple of the time taken, then the 1-day work will certainly be an integer value.

    • So, when we are assuming a value for the total work, we need to consider such a value which should be a multiple of the time taken by the different parties working on that job.
      • In other words, the assumed value of the total work can be taken as the least common multiple (LCM) of the given individual time taken by the persons or machines working on that job.


Let us try to solve the same question using the method that we just mentioned.

Image



Solution 1B: Changing the total work value
Let us assume the total work of production order is 12 units. Therefore, we can say:
    • In 4 hours 1st machine can complete 12 units of work
      • Hence, in 1 hour 1st machine can complete 3 units of work
    • Similarly, 2nd machine in 3 hours can complete 12 units of work
      • Hence, in 1 hour 2nd machine can complete 4 units of work
    • If both the machines work simultaneously together, in 1 hour they will complete (3 + 4) units of work = 7 units of work
    • As the complete work is 12 units, to complete the order they need to do total 12 units of work together
    • Combined together, the machines are completing 7 units of work in 1 hour
      • Therefore, the machines will complete 12 units of work together in \(\frac{12}{7}\) hours
Hence, working together, both the machines will take \(\frac{12}{7}\) hours to complete the production order.

Important Takeaway
If we compare the methods explained above, fundamentally they are same, with some difference in value-wise derivation. But the most important thing to observe is that there are no fractional intermediate calculations involved in the second solution.
    • As the total work is assumed to be the LCM of 3 and 4, we are avoiding the fractional calculation, and thus, saving the overall calculation time.


Let us take another example to validate this learning:

e-GMAT Example 2

One inlet pipe fills an empty tank in 5 hours. A second inlet pipe fills the same tank in 3 hours. If both pipes are used together, how long will it take to fill 2/3rd of the tank?

Solution 2A: Conventional Method
In this question, it is given that one inlet pipe can fill an empty tank in 5 hours. A second inlet pipe fills the same tank in 3 hours.

Image


As the capacity of the tank remains same, let’s assume the capacity of the tank is 1 unit.
    • As the 1st pipe takes 5 hours to fill 1 unit,
      • In 1 hour it will fill \(\frac{1}{5}\) units
    • Similarly, the 2nd pipe takes 3 hours to fill 1 unit
      • Hence, in 1 hour it will fill \(\frac{1}{3}\) units
    • If both pipes are used together, in 1 hour they will fill = (\(\frac{1}{5} + \frac{1}{3}\)) units = \(\frac{(3+5)}{15}\) units = \(\frac{8}{15}\) units

Hence, to fill \(\frac{2}{3}\)rd of the tank, they will take = \(\frac{2}{3}/\frac{8}{15}\) hrs = \(\frac{2}{3} * \frac{15}{8}\) hrs = \(\frac{5}{4}\) hrs

Now, let’s try solving the same question using the LCM method:

Solution 2B: LCM Method
As the capacity of the tank remains same, let’s assume the capacity of the tank is 15 units.
[notice that 15 = LCM (3,5)]
    • As the 1st pipe takes 5 hours to fill 15 units,
      • In 1 hour it will fill 3 units
    • Similarly, the 2nd pipe takes 3 hours to fill 15 units
      • Hence, in 1 hour it will fill 5 units
    • If both pipes are used together, in 1 hour they will fill = (3 + 5) units = 8 units
    • The total work to be completed = (\(\frac{2}{3} * 15\)) = 10 units

Hence, to fill \(\frac{2}{3}\)rd of the tank, they will take = \(\frac{10}{8}\) hrs = \(\frac{5}{4}\) hrs

Important Takeaway
As you can see, both the problems can be solved using conventional method as well as LCM method. However, application of LCM method significantly decreases the calculation related, and therefore the time taken to solve a particular question becomes less.

Let us solve couple of more examples using the LCM method to reinforce our learning.

Image


e-GMAT Example 2

Solving Time and Work Problem: LCM Method
In the following questions, we will solve the problems by applying LCM method only.

e-GMAT Example 3
Machines A and B always operate independently and at their respective constant rates. When working alone, Machine A can fill a production lot in 3 hours, and Machine B can fill the same lot in x hours. If A and B worked alternatively, while each work for 1 hour at a time, the total work gets completed in 4 hours. What is the value of x?
Solution 3
In this question it is given that machine A can fill a production lot in 3 hours, and machine B can fill the same production lot in x hours, when they are working alone.
However, they will take 4 hours to complete the job, when they are working alternatively for 1 hour each.
Let us assume the total work to be 3x units (LCM of 3 and x)
    • As machine A takes 3 hours to fill 3x units,
      • In 1 hour it will fill \(\frac{3x}{3}\) units = x units
    • Similarly, machine B takes x hours to fill 3x units,
      • Hence, in 1 hour it will fill \(\frac{3x}{x}\) units = 3 units
    • It is also given that; machine A and machine B, working alternatively, take 4 hours to fill 3x units
      • Therefore, in 2 hours’ time they will fill = (x + 3) units
      • Hence, in 1 hour the production lot they fill = \(\frac{1}{2} * (x + 3)\) units
    • Now we can say in 4 hours,
      • Units filled by A + units filled by B = total production units
      Or, \(4 * \frac{1}{2} * (x + 3)\) = 3x
      Or, 2x + 6 = 3x
      Or, x = 6 hours
Hence, the value of x is 6.

Important Takeaway
Unlike the previous questions, in this question we have a variable defined as x. Even in such case, we can apply the LCM method, as we did in the solved example, to get quick and accurate answer.

e-GMAT Example 4
Working at a constant rate, pump X pumped out half of the water in a flooded basement in 4 hours. Then pump Y was started and the two pumps, working independently at their respective constant rates, pumped out the rest of the water in 3 hours. How many hours would it have taken pump Y, operating alone at its own constant rate, to pump out all of the water that was pumped out of the basement?

Solution 4

Image


In this question there are two pumps working separately at their own constant rate.
    • Pump X cleared half of the water present in the flooded basement in 4 hours
      • Therefore, to clear all the water, pump A would have taken twice the amount of time, i.e. 8 hours
    • After pump X worked for 4 hours, pump Y also started working, and together they took 3 hours to clear the remaining half of the water
      • As they took 3 hours to clear half the total amount of water, they would have taken double of that time, i.e. 6 hours, to clear the whole water
With this inference, we actually have a simple problem, which is very similar to the previous ones that we solved.
    • Pump X takes 8 hours to clear the whole water
    • Pump X and Y together take 6 hours to clear the whole water
Let us assume the total amount of water to be 24 units
    • In 8 hours, pump X clears 24 units,
      • Hence, in 1 hour, pump X clears \(\frac{24}{8}\) units = 3 units
    • Similarly, in 6 hours, pump X and Y clears 24 units,
      • Hence, in 1 hour, pump X and Y together clear \(\frac{24}{6}\) units = 4 units
    • Now in 1 hour, out of the 4 units of water cleared by pump X and Y together, 3 units were cleared by X only
      • Therefore, amount of water cleared by Y in 1 hour = (4 – 3) unit = 1 unit

As pump Y can clear 1 unit of water in 1 hour, it will take \(\frac{24}{1}\) hours = 24 hours to clear the whole amount of water, when working alone at its constant rate.

Important Observation
Apart from the usual application of the LCM method, another distinct observation we can do from this question, which is applicable in the previous question also. Let us see that:
    • X can complete the whole work alone in 8 hours
    • Y can complete the whole work alone in 24 hours
    • X and Y together can complete the whole work in 6 hours
It is noticeable that the time taken by them together to complete the work is much less than their individual time. This is happening because of their difference in individual efficiencies.

Application of Efficiency in Time and Work problems
As we know, efficiency essentially means the rate of work, i.e. the amount of work done in unit time.
    • The more time one takes to complete a job, the less efficient the person is.
    • Similarly, the less time one takes to complete a job, the more efficient the person is.
Therefore, we can say that, efficiency is inversely proportional to the time taken to complete the work.
In a given scenario, efficiency can be used to explain the work rate either of an individual or of a group consists of similar objects. For a group, it is generally assumed that everyone within that group has the same efficiency.

Let us take an example of a time and work problem, which relates to the concept of efficiency:

e-GMAT Example 5
At a loading dock, each worker on the night crew loaded 3/4 as many boxes as each worker on the day crew. If the night crew has 4/5 as many workers as the day crew, what fraction of all the boxes loaded by the two crews did the day crew load?

Solution 5
In this question we have two separate groups of people to consider.
    • Each member within the group has the same efficiency as other members
    • However, group wise the efficiencies are different from each other
      • This means that everyone in the night crew has the same efficiency and everyone in the day crew has the same efficiency. However, the efficiency of day and night crew in this case is different.

Image


Let us look at the problem in detail.

It is given that there are two groups of workers – one operates at day time and the other one operates at night time.
    • Each worker on the night crew loaded \(\frac{3}{4}\) as many boxes as each worker on the day crew
      • This statement defines the difference in efficiency of each worker belongs to night crew and day crew
      • If we assume that each worker in the day crew loaded 4 boxes, then each worker in the night crew must have loaded \(4 * \frac{3}{4}\) boxes = 3 boxes
    • It is also given that night crew has \(\frac{4}{5}\) as many workers as the day crew
      • If we assume that there are 5 workers in the day crew, then there will be \(5 * \frac{4}{5}\) = 4 workers in the night crew
[notice that we have intentionally assumed the number of box loaded and number of day crew workers as 4 and 5, to avoid any fractional calculation. Both the numbers could have been assumed as 1 or any other number – the end result would have been same, but may lead to fractional calculations]

We can show the whole data in the following table:
Image


As we can see, total boxes loaded by day crew are 20 and by night crew are 12.
Hence, the boxes loaded by day crew as the fraction of all the boxes loaded by both the crew = \(\frac{20}{(20+12)} = \frac{20}{32} = \frac{5}{8}\)

Let us take one last example to demonstrate the application of efficiency:

e-GMAT Example 6
Machines X and Y work at their respective constant rates. How many more hours does it take machine Y, working alone, to fill a production order of a certain size than it takes machine X, working alone?
    A. Machines X and Y, working together, fill a production order of this size in two-thirds the time that machine X, working alone, does.
    B. Machine Y, working alone, fills a production order of twice the size in 6 hrs.

Option choices:
A) Statement (1) ALONE is sufficient, but statement (2) alone is not sufficient.
B) Statement (2) ALONE is sufficient, but statement (1) alone is not sufficient.
C) BOTH statements TOGETHER are sufficient, but NEITHER statement ALONE is sufficient.
D) EACH statement ALONE is sufficient.
E) Statements (1) and (2) TOGETHER are NOT sufficient.


Image



Solution 6
In this question, two machines X and Y, with different efficiency, can work on a certain job.
    • The question asks the number of extra hours that machine Y takes to complete the job when working alone, compared to the time taken by machine X to complete the same job, working alone.
As no other information was provided in the question stem, we will analyse the given statements.
Analysing Statement 1:
    • As per the information given in statement 1, machines X and Y, working together, fill a production order of the same size in two-thirds the time that machine X, working alone, does.
    • If we assume that machine X, working alone, takes t hours to complete the job, then from statement 1 we can say
      • Machine X and Y, working together, complete the whole work in \(\frac{2}{3}\)t hours
    • As both the machines work on their constant efficiencies throughout, we can say in \(\frac{2}{3}\)t hrs machine X can complete \(\frac{2}{3}\)rd of the total work.
    • Therefore, in that \(\frac{2}{3}\)t hours, machine Y completes \(\frac{1}{3}\)rd of the total work.
      • Hence, machine Y can complete the total work in \(\frac{2}{3}\)t * 3 hours = 2t hours
    • But we cannot deduce the exact value of t from this statement.

Hence, statement 1 is not sufficient to answer the question.

Analysing Statement 2:
    • As per the information given in statement 2, machine Y, working alone, fills a production order of twice the size in 6 hrs
    • Hence, if we consider a production order of the original volume, machine Y will take 3 hours to complete it
    • But from this statement, we cannot figure out any information regarding the work rate or time taken by X to complete the work

Hence, statement 2 is not sufficient to answer the question.

Combining Both Statements:
    • If we consider both statements together, we can say machine Y takes 2t hours to complete the whole job, which is equal to 3 hours
      • Hence, the value of t = \(\frac{3}{2}\) hours
    • We also know that machine X takes t hours to complete the whole job working alone
      • As we already know t is equal to \(\frac{3}{2}\) hours, we can say machine X takes \(\frac{3}{2}\) hours to complete the job working alone
    • Therefore, machine Y takes (\(3 – \frac{3}{2}\)) hours = \(\frac{3}{2}\) hours more than what machine X takes to complete the work, working individually.

As information from both the statements are required to solve the question, we can say the correct answer choice is Option C.

Takeaway from this article
    • In Time and Work problems where we are supposed to assume the value of total work, it is always a good practice to assume the total work as the LCM of the given days (or any multiple of LCM), rather than assuming the total work as 1 unit – as it decreases the complex calculations involve with fractions.
    • LCM method can still be applied when one of the data points are given in terms of variable
    • Efficiency is inversely proportional to time taken.
    • When working in groups, all are considered to be equally efficient within a group, whereas people have different efficiencies across groups.

Image



What next in this series of article??

Next week we will come up with one more article in the Distance series.
In that article, we are going to discuss 3 common errors students make while solving Time and Work problems


Did you enjoy this article??
If you have enjoyed the article, then try the practice questions given below.
Attachments

Time and work.pdf [599.89 KiB]
Downloaded 169 times

To download please login or register as a user


_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com


Originally posted by EgmatQuantExpert on 23 May 2018, 04:18.
Last edited by EgmatQuantExpert on 07 Aug 2018, 06:11, edited 6 times in total.
e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post Updated on: 13 Aug 2018, 05:25

Hey Everyone,




Here is a list of questions specifically designed to help you apply the learnings from this article.

Exercise Questions


Question 1

Question 2

Question 3

Question 4



Detailed solutions will be posted soon.


Happy Learning! :)
_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com


Originally posted by EgmatQuantExpert on 23 May 2018, 04:20.
Last edited by EgmatQuantExpert on 13 Aug 2018, 05:25, edited 1 time in total.
e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Re: Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post 27 May 2018, 05:34
1
Hey everyone,

The official answers to all the practice questions have been posted.

Regards,
Tamal
e-GMAT
_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com

e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Re: Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post 27 May 2018, 23:06
1
Hey everyone,

We have added the pdf of the article. :-)

Happy learning,

Regards,
Tamal
Quant Expert
e-GMAT
_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com

e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Re: Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post 13 Jun 2018, 23:54
Hello all,

We have added a new article to help you avoiding the major concerns students face in solving Percentage problems.

You can go through the article from here: 3 Major Concerns Students Face in Solving Percentage Problems

Stay tuned for more articles.

Happy learning. :)

Regards,
Tamal
e-GMAT
_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com

e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Re: Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post 25 Jun 2018, 22:59
Hello all,

We have added a new article to help you learning 3 unusual, yet must learn applications of percentage.

You can go through the article from here: 3 Must Learn Applications of Percentages

Stay tuned for more articles.

Happy learning. :)

Regards,
Tamal
e-GMAT
_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com

Intern
Intern
avatar
B
Joined: 22 Apr 2018
Posts: 6
Re: Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post 24 Jul 2018, 00:44
I didn't understand the following line in Solution 4:


Similarly, in 6 hours, pump Y clears 24 units,---- How do we know that Pump Y clears 24 units in 6 hours this is what we have to find right??
• Hence, in 1 hour, pump X and Y together clear
24
6

246
units = 4 units

Also in Solution 6:
As both the machines work on their constant efficiencies throughout, we can say in
2/3


Can anybody please explain? I'm really confused
2/3t hrs machine X can complete
2/3

2/3rd of the total work.
------------------- How do we know that Machine X will complete 2/3rd of work??
e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Re: Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post 24 Jul 2018, 01:13
Quote:
I didn't understand the following line in Solution 4:


Similarly, in 6 hours, pump Y clears 24 units,---- How do we know that Pump Y clears 24 units in 6 hours this is what we have to find right??
• Hence, in 1 hour, pump X and Y together clear
24
6

246
units = 4 units


It should be X and Y, not Y only - the X was missing. However, it can be understood from the next immediate line, where the 1 hour work of X and Y together is calculated.

Quote:
Also in Solution 6:
As both the machines work on their constant efficiencies throughout, we can say in
2/3


Can anybody please explain? I'm really confused
2/3t hrs machine X can complete
2/3

2/3rd of the total work.
------------------- How do we know that Machine X will complete 2/3rd of work??


It is assumed that machine X, working alone, takes t hours to complete the job.
Hence, in \(\frac{2}{3}\)t hours, it will complete \(\frac{2}{3}\)rd of the whole job.
_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com

e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post 27 Sep 2018, 03:51

Hey Everyone,



We've added 4 practice questions in which you can apply your learning of Time and Work concepts.

Exercise Questions


Question 1

Question 2

Question 3

Question 4


Detailed solutions will be posted soon.


Happy Learning! :)
_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com

e-GMAT Representative
User avatar
P
Joined: 04 Jan 2015
Posts: 2065
Re: Solve Time and Work Problems Efficiently using Efficiency Method!  [#permalink]

Show Tags

New post 03 Oct 2018, 05:19
Hey everyone,

The official answers to all the practice questions have been posted.

Regards,
Sandeep
e-GMAT
_________________








Register for free sessions
Number Properties | Algebra |Quant Workshop

Success Stories
Guillermo's Success Story | Carrie's Success Story

Ace GMAT quant
Articles and Question to reach Q51 | Question of the week

Must Read Articles
Number Properties – Even Odd | LCM GCD | Statistics-1 | Statistics-2
Word Problems – Percentage 1 | Percentage 2 | Time and Work 1 | Time and Work 2 | Time, Speed and Distance 1 | Time, Speed and Distance 2
Advanced Topics- Permutation and Combination 1 | Permutation and Combination 2 | Permutation and Combination 3 | Probability
Geometry- Triangles 1 | Triangles 2 | Triangles 3 | Common Mistakes in Geometry
Algebra- Wavy line | Inequalities

Practice Questions
Number Properties 1 | Number Properties 2 | Algebra 1 | Geometry | Prime Numbers | Absolute value equations | Sets



| '4 out of Top 5' Instructors on gmatclub | 70 point improvement guarantee | www.e-gmat.com

GMAT Club Bot
Re: Solve Time and Work Problems Efficiently using Efficiency Method! &nbs [#permalink] 03 Oct 2018, 05:19
Display posts from previous: Sort by

Solve Time and Work Problems Efficiently using Efficiency Method!

  new topic post reply Question banks Downloads My Bookmarks Reviews Important topics  


Copyright

GMAT Club MBA Forum Home| About| Terms and Conditions and Privacy Policy| GMAT Club Rules| Contact| Sitemap

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne

Kindly note that the GMAT® test is a registered trademark of the Graduate Management Admission Council®, and this site has neither been reviewed nor endorsed by GMAC®.