Last visit was: 22 Apr 2026, 20:44 It is currently 22 Apr 2026, 20:44
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
avatar
superpus07
Joined: 20 Jun 2011
Last visit: 14 Apr 2014
Posts: 33
Own Kudos:
483
 [126]
Given Kudos: 1
Posts: 33
Kudos: 483
 [126]
6
Kudos
Add Kudos
119
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,688
 [38]
21
Kudos
Add Kudos
17
Bookmarks
Bookmark this Post
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 21 Apr 2026
Posts: 16,439
Own Kudos:
79,389
 [8]
Given Kudos: 484
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,439
Kudos: 79,389
 [8]
3
Kudos
Add Kudos
5
Bookmarks
Bookmark this Post
General Discussion
User avatar
Marcab
Joined: 03 Feb 2011
Last visit: 22 Jan 2021
Posts: 840
Own Kudos:
4,943
 [4]
Given Kudos: 221
Status:Retaking after 7 years
Location: United States (NY)
Concentration: Finance, Economics
GMAT 1: 720 Q49 V39
GPA: 3.75
GMAT 1: 720 Q49 V39
Posts: 840
Kudos: 4,943
 [4]
3
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
superpus07
Machine A currently takes x hours to complete a certain job. Machine B currently takes y hours to complete the same job. If x=4y, by what percent will x have to decrease so that A and B together can complete the job in \(\frac{3y}{8}\) hours ?

A. 15%
B. 25%
C. 30%
D. 62,5%
E. 85%



Thanks.
The question intends to say that A has increased his rate of work and as a result, the total time taken by both of them has also decreased.
Consider the initial time that was supposed to be taken by both of them.
\(\frac{1}{x} + \frac{1}{y}\) is the combined rate of work.
Since \(x=4y\),
hence combined rate of work will come out to be \(\frac{5y}{4}\).
Since the work is 1 unit, therefore time required at this rate to complete this much of work will be \(\frac{4y}{5}\).
BUT, they are supposed to complete the work in \(\frac{3y}{8}\) hours. So first we calculate the reduction in total time.
\(reduction in time=\frac{4y}{5} - \frac{3y}{8}= \frac{17y}{40}\)

Only A is credited with this reduction of time.
Percentage decrease=4y-[15y/40]/4y
=(29/32)*100.
We need not calculate thsi value because if we see the options, only E is close to this value.
Hence E.
User avatar
jkaustubh
Joined: 24 Sep 2012
Last visit: 08 Jul 2019
Posts: 185
Own Kudos:
88
 [6]
Given Kudos: 31
Status:MBA Candidate, Class of 2017
Affiliations: SMU Cox
Location: United States (TX)
Concentration: General Management, Strategy
GMAT 1: 710 Q48 V39
GPA: 3.75
WE:Project Management (Energy)
GMAT 1: 710 Q48 V39
Posts: 185
Kudos: 88
 [6]
5
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Let Machine A take x' hours to complete the job so that both machines A and B can complete the job in 3y/8 hrs.
now
1/x'=8/3y-1/y

this gives x'=3y/5
now calculate the %age decrease

i.e
[4y-(3y/5)]/4y=17/20=0.85

this was my approach. not sure abt your calculation speed, but it took me less that a min to solve it
User avatar
AccipiterQ
Joined: 26 Sep 2013
Last visit: 03 Sep 2020
Posts: 144
Own Kudos:
Given Kudos: 40
Concentration: Finance, Economics
GMAT 1: 670 Q39 V41
GMAT 2: 730 Q49 V41
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Bunuel
superpus07
Machine A currently takes x hours to complete a certain job. Machine B currently takes y hours to complete the same job. If x=4y, by what percent will x have to decrease so that A and B together can complete the job in 3y/8 hours ?

A. 15%
B. 25%
C. 30%
D. 62,5%
E. 85%

We need \(x\) to decrease so that A and B together can complete the job in \(\frac{3y}{8}\) hours, so we need the combined rate of machines A and B to be \(rate=\frac{job}{time}=\frac{1}{(\frac{3y}{8})}=\frac{8}{3y}\) job/hour --> \(\frac{1}{x}+\frac{1}{y}=\frac{8}{3y}\) --> \(x=\frac{3y}{5}\) hours.

We have that in order A and B together to complete the job in \(\frac{3y}{8}\) hours, the time in which machine A completes the job must be \(\frac{3y}{5}\) hours instead of \(4y\) hours.

Percentage decrease should be \(\frac{change}{original}*100=\frac{4y-\frac{3y}{5}}{4y}=85%\).

Answer: E.

Hope it's clear.


could you explain how you flipped the fraction over in there, I don't get any of what was done for this problem
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,754
Own Kudos:
810,688
 [1]
Given Kudos: 105,823
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,754
Kudos: 810,688
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
AccipiterQ
Bunuel
superpus07
Machine A currently takes x hours to complete a certain job. Machine B currently takes y hours to complete the same job. If x=4y, by what percent will x have to decrease so that A and B together can complete the job in 3y/8 hours ?

A. 15%
B. 25%
C. 30%
D. 62,5%
E. 85%

We need \(x\) to decrease so that A and B together can complete the job in \(\frac{3y}{8}\) hours, so we need the combined rate of machines A and B to be \(rate=\frac{job}{time}=\frac{1}{(\frac{3y}{8})}=\frac{8}{3y}\) job/hour --> \(\frac{1}{x}+\frac{1}{y}=\frac{8}{3y}\) --> \(x=\frac{3y}{5}\) hours.

We have that in order A and B together to complete the job in \(\frac{3y}{8}\) hours, the time in which machine A completes the job must be \(\frac{3y}{5}\) hours instead of \(4y\) hours.

Percentage decrease should be \(\frac{change}{original}*100=\frac{4y-\frac{3y}{5}}{4y}=85%\).

Answer: E.

Hope it's clear.


could you explain how you flipped the fraction over in there, I don't get any of what was done for this problem

\(\frac{1}{(\frac{3y}{8})}=1*\frac{8}{3y}=\frac{8}{3y}\).
User avatar
sujoykrdatta
Joined: 26 Jun 2014
Last visit: 14 Apr 2026
Posts: 587
Own Kudos:
Given Kudos: 14
Status:Mentor & Coach | GMAT Q51 | CAT 99.98
GMAT 1: 740 Q51 V39
Expert
Expert reply
GMAT 1: 740 Q51 V39
Posts: 587
Kudos: 1,191
Kudos
Add Kudos
Bookmarks
Bookmark this Post
superpus07
Machine A currently takes x hours to complete a certain job. Machine B currently takes y hours to complete the same job. If x=4y, by what percent will x have to decrease so that A and B together can complete the job in 3y/8 hours ?

A. 15%
B. 25%
C. 30%
D. 62,5%
E. 85%


We can assume a suitable value of y (and hence x) and calculate the answer:
Let y = 8 hours => Time taken by B to complete the work = 8 hours
=> x = 32 hours => Time taken by A to complete the work = 32 hours

Note: At the above rates, fraction of work done by A and B in 1 hour = 1/8 + 1/32 = 5/32
=> Time taken by A and B together to complete the work = 32/5 hours

However, we need to complete the work in 3y/8 = 3 hours

Thus, in each hour, A and B should do 1/3 rd of the work
=> Work done by A in 1 hour (after the value of x is changed) = 1/3 - 1/8 = 5/24

=> Time (new) taken by A to complete the work = 24/5 = 4.8 hours

The question asks: "what percent will x have to decrease"
Thus, it is asking about the percent change in time

=> Required percent = (32 - 4.8)/32 * 100 = 85%

Answer E
User avatar
GMATGuruNY
Joined: 04 Aug 2010
Last visit: 02 Apr 2026
Posts: 1,347
Own Kudos:
Given Kudos: 9
Schools:Dartmouth College
Expert
Expert reply
Posts: 1,347
Kudos: 3,905
Kudos
Add Kudos
Bookmarks
Bookmark this Post
superpus07
Machine A currently takes x hours to complete a certain job. Machine B currently takes y hours to complete the same job. If x=4y, by what percent will x have to decrease so that A and B together can complete the job in 3y/8 hours ?

A. 15%
B. 25%
C. 30%
D. 62,5%
E. 85%

Let y=8 hours and x=32 hours, implying that the desired time for the job \(= \frac{3y}{8} = \frac{3*8}{8} = 3\) hours.

Let the job = LCM(8, 32, 3) = 96 units.
Since A takes x=32 hours to produce 96 units, A's rate \(= \frac{work}{time} = \frac{96}{32} = 3\) units per hour.
Since B takes y=8 hours to produce 96 units, B's rate \(= \frac{work}{time} = \frac{96}{8} = 12\) units per hour.

Required rate to complete the 96-unit job in the desired time of 3 hours \(= \frac{work}{time} = \frac{96}{3} = 32\) units per hour.
Since B's rate = 12 units per hour, A's rate must increase from 3 units per hour to 20 units per hour.
Rate and time have a RECIPROCAL RELATIONSHIP.
Since A's new rate is 20/3 of its current rate, A's new time must be 3/20 of its current time, a decrease of \(\frac{17}{20} =\) 85%.

User avatar
Manifesting710
Joined: 04 Oct 2023
Last visit: 30 Jan 2025
Posts: 35
Own Kudos:
Given Kudos: 245
Location: India
GMAT Focus 1: 615 Q83 V83 DI75
GPA: 3.3
GMAT Focus 1: 615 Q83 V83 DI75
Posts: 35
Kudos: 713
Kudos
Add Kudos
Bookmarks
Bookmark this Post
I took a longer approach, might be helpful to someone
\(\\
­Rate A = \frac{1}{X}\\
­Rate B = \frac{1}{Y}\\
 X = 4Y\\
\\
\frac{1}{X} + \frac{1}{Y} = \frac{8}{3Y}­\\
\)­
\(\\
\frac{1}{4Y} + \frac{1}{Y} = \frac{8}{3Y}­\\
\)­
\( \frac{1}{4Y*(P/100)} + \frac{1}{Y} = \frac{8}{3Y}\)­, Where P = 100 - x,  x is what we need to find
\(\\
\frac{1}{4Y*(P/100) } + \frac{1*4*(P\100) }{Y*4*(P/100) } = \frac{8}{3Y}\\
\)
simplifying
\(\frac{ 1 + (P\25)}{ (PY/25)  } = \frac{8}{3Y}\)

Simplifying
\(\\
3Y = \frac{8PY}{25} - \frac{3PY}{25}\\
\\
3Y = \frac{5PY}{25}\\
\)
P = 15

P = 100 - X -> X = 85 , Hence (E) 
 ­
avatar
Him2323
Joined: 21 Jun 2024
Last visit: 24 Apr 2025
Posts: 3
Given Kudos: 33
Posts: 3
Kudos: 0
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Marcab

superpus07
Machine A currently takes x hours to complete a certain job. Machine B currently takes y hours to complete the same job. If x=4y, by what percent will x have to decrease so that A and B together can complete the job in \(\frac{3y}{8}\) hours ?

A. 15%
B. 25%
C. 30%
D. 62,5%
E. 85%



Thanks.
The question intends to say that A has increased his rate of work and as a result, the total time taken by both of them has also decreased.
Consider the initial time that was supposed to be taken by both of them.
\(\frac{1}{x} + \frac{1}{y}\) is the combined rate of work.
Since \(x=4y\),
hence combined rate of work will come out to be \(\frac{5y}{4}\).
Since the work is 1 unit, therefore time required at this rate to complete this much of work will be \(\frac{4y}{5}\).
BUT, they are supposed to complete the work in \(\frac{3y}{8}\) hours. So first we calculate the reduction in total time.
\(reduction in time=\frac{4y}{5} - \frac{3y}{8}= \frac{17y}{40}\)

Only A is credited with this reduction of time.
Percentage decrease=4y-[15y/40]/4y
=(29/32)*100.
We need not calculate thsi value because if we see the options, only E is close to this value.
Hence E.
­Hello, I checked the value of the calculation in the last part. It's coming out to be 90.6%. Can you please re-check the method employed?
User avatar
bumpbot
User avatar
Non-Human User
Joined: 09 Sep 2013
Last visit: 04 Jan 2021
Posts: 38,964
Own Kudos:
Posts: 38,964
Kudos: 1,117
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Automated notice from GMAT Club BumpBot:

A member just gave Kudos to this thread, showing it’s still useful. I’ve bumped it to the top so more people can benefit. Feel free to add your own questions or solutions.

This post was generated automatically.
Moderators:
Math Expert
109754 posts
Tuck School Moderator
853 posts