I really had to take a step back for a second because I thought there was some underlying trick hidden.
The hardest part with this problem is getting all the Information understood and organized.
2 Key Facts that make this question much easier:
(1) Takes from the Beginning of ONE Day ---------> to the END of NEXT Day to Finish a Product (a full 2 Days)
from this Fact, we can only finish products if we Start them on Monday or Tuesday. Otherwise, the Products will NOT be Finished by End of Work day Wednesday.
In effect, Wednesday is a throw away Day and starting projects on Wednesday will NOT help.
(2) AT MOST we can only be working on 5 of these products at ANY ONE TIME.
No matter how many components we have (even if there is beyond 5 of Each Component avialable) -----
If we Start X Products on Monday ------> it will take until END of Tuesday to finish the X Products
Therefore, at Beginning of Work on Tuesday ----> we can only Start (5 - X) Products
because the X products we Started Monday will still be on-going and we can only have a MAX of 5 products going at any one time
(I) START of DAY Monday:
Since we need All 3 Parts available on the Day we start making the product, we are limited by the 3-A parts that are available. The most products we can start on Monday morning = 3 products
(II) START of DAY Tuesday:
the components we will have to work with are -
A = 6
B = (3 not used yesterday) + 3 = 6
C = (1 not used yesterday) + 7 = 8
Even though we have enough parts to make 6 on Tuesday, we already have the 3 products in-process that we started making on Monday. These will NOT be Finished until END of Work Day Tuesday.
Therefore the MOST we can Start on Tuesday = 2 products
(III)END of Work Day Tuesday: the 3 products we started on Monday will be Finished
(IV) BEGINNING of Work Day Wednesday:
Even though we can start more products, we will NOT be able to Finish the products in time. Wednesday becomes a throw-away day.
(V)END of Work Day Wednesday: the 2 products we started on Tuesday will be Finished
5 Products will be Finished and this is the MOST we can make.
-B-
NOTE: you can try it with any amount of products started on Monday up to the MAX of 5
If we start only 1 on Monday
then when we get to Tuesday, we will only be able to Start 4 More because the Monday product will still be in-process.
And again, because it takes a full 2 Days to finish the product, we will only be able to finish 5 products by End of Work Day Wednesday