Last visit was: 22 Apr 2026, 10:52 It is currently 22 Apr 2026, 10:52
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
555-605 (Medium)|   Non-Math Related|               
User avatar
guddo
Joined: 25 May 2021
Last visit: 22 Apr 2026
Posts: 1,009
Own Kudos:
11,310
 [39]
Given Kudos: 32
Posts: 1,009
Kudos: 11,310
 [39]
2
Kudos
Add Kudos
37
Bookmarks
Bookmark this Post
Most Helpful Reply
User avatar
yashikaaggarwal
User avatar
Senior Moderator - Masters Forum
Joined: 19 Jan 2020
Last visit: 29 Mar 2026
Posts: 3,089
Own Kudos:
3,158
 [7]
Given Kudos: 1,510
Location: India
GPA: 4
WE:Analyst (Internet and New Media)
Posts: 3,089
Kudos: 3,158
 [7]
4
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
User avatar
yashikaaggarwal
User avatar
Senior Moderator - Masters Forum
Joined: 19 Jan 2020
Last visit: 29 Mar 2026
Posts: 3,089
Own Kudos:
3,158
 [6]
Given Kudos: 1,510
Location: India
GPA: 4
WE:Analyst (Internet and New Media)
Posts: 3,089
Kudos: 3,158
 [6]
4
Kudos
Add Kudos
2
Bookmarks
Bookmark this Post
General Discussion
avatar
palaknayyar
avatar
Current Student
Joined: 31 Jul 2015
Last visit: 20 Jul 2022
Posts: 44
Own Kudos:
12
 [1]
Given Kudos: 597
Location: India
GPA: 3.46
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
From what I understood of this question, "Contractor B must be scheduled to work exactly two days after Contractor A is."
B should have been Thursday since B should be scheduled AFTER 2 days of A.

Anyone else think the wording was a bit vague in this one?
User avatar
Will2020
User avatar
Current Student
Joined: 24 Jan 2017
Last visit: 04 Mar 2022
Posts: 130
Own Kudos:
Given Kudos: 1,120
Location: Brazil
Concentration: Entrepreneurship, Strategy
GPA: 3.2
WE:Consulting (Healthcare/Pharmaceuticals)
Products:
Posts: 130
Kudos: 54
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Sajjad1994
Martine is scheduling five contractors (Contractors A through E) to do various tasks during Monday through Friday of the upcoming week. For each day, exactly one contractor will be scheduled to work, and each contractor's task will be completed on the day for which he or she is scheduled. The scheduling must conform to the following constraints.

  • Contractor A must be scheduled to work on Monday.
  • Contractor B must be scheduled to work exactly two days after Contractor A is.
  • Contractor E must be scheduled to work exactly three days after Contractor C is.

Select from each drop-down menu the option that creates the most accurate statement based on the information provided.

Statement: Given the constraints, Martine must schedule Contractor B to work on___________and Contractor D to work on___________.

A. Monday
B. Tuesday
C. Wednesday
D. Thursday
E. Friday

Wednesday
Thursday

Project IR Butler 2019-20 - Get one IR Question Everyday
Question # 348, Date : 14-Sep-2020
This post is a part of Project IR Butler 2019-20. Click here for Details

Hi KarishmaB! Can you help me with this question? Why don't we count weekend days? Why contractor C works on Tuesday? Is it because of the constrain "For each day, exactly one contractor will be scheduled to work"? I though I count the next week when the other contractors might have finished... Thank you! :please:
User avatar
KarishmaB
Joined: 16 Oct 2010
Last visit: 21 Apr 2026
Posts: 16,439
Own Kudos:
79,386
 [5]
Given Kudos: 484
Location: Pune, India
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 16,439
Kudos: 79,386
 [5]
4
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
Will2020
Sajjad1994
Martine is scheduling five contractors (Contractors A through E) to do various tasks during Monday through Friday of the upcoming week. For each day, exactly one contractor will be scheduled to work, and each contractor's task will be completed on the day for which he or she is scheduled. The scheduling must conform to the following constraints.

  • Contractor A must be scheduled to work on Monday.
  • Contractor B must be scheduled to work exactly two days after Contractor A is.
  • Contractor E must be scheduled to work exactly three days after Contractor C is.

Select from each drop-down menu the option that creates the most accurate statement based on the information provided.

Statement: Given the constraints, Martine must schedule Contractor B to work on___________and Contractor D to work on___________.

A. Monday
B. Tuesday
C. Wednesday
D. Thursday
E. Friday

Wednesday
Thursday

Project IR Butler 2019-20 - Get one IR Question Everyday
Question # 348, Date : 14-Sep-2020
This post is a part of Project IR Butler 2019-20. Click here for Details

Hi KarishmaB! Can you help me with this question? Why don't we count weekend days? Why contractor C works on Tuesday? Is it because of the constrain "For each day, exactly one contractor will be scheduled to work"? I though I count the next week when the other contractors might have finished... Thank you! :please:

The 5 contractors are being scheduled for the 5 days (Monday thru Friday of next week) such that each contractor works on exactly one day. It doesn't say anything about scheduling next to next week. We must schedule the 5 people on the 5 days of next week only.

Monday - A
2 days after Monday is Wednesday so
Wednesday - B
We are left with Tuesday, Thursday & Friday
C - - - E
Only if C were on Tuesday, then E can be on Friday. If C were on Thursday or Friday, we would have no day for E. Think about it - if C were scheduled on Friday, E would be moved to Monday of next to next week and on one day of next week, there would be no contractor. We must schedule all contractors on the 5 days of next week only.

Tuesday - C
Friday - E
Leftover are D and Thursday
Thursday - D


Note - Even if you get confused that 2 days after Monday must be Thursday, by that logic 3 days after Tuesday would have to be Saturday which is not possible.
Hence, we can fi sure out that 2 days after Monday must be Wednesday only.
User avatar
lawyeroffduty
Joined: 22 May 2024
Last visit: 16 Feb 2026
Posts: 38
Own Kudos:
Given Kudos: 240
Location: India
Concentration: General Management, Strategy
GPA: 8.07
WE:Law (Law)
Products:
Kudos
Add Kudos
Bookmarks
Bookmark this Post
so going forward for all the language of similar type, we will consider that particular day included in exactly two days period? or it depends upon the language of the question stem. i'm confused here
yashikaaggarwal

It might get people confused. But 2 days after doesn't mean 2 days gap in between. For ex. Let's say. Contractor A started work on 9:00 AM sharp on Monday, 2 days later it will be wednesday. Monday will be count as a day too. Hence, B is scheduled for Wednesday.

Posted from my mobile device
User avatar
Bunuel
User avatar
Math Expert
Joined: 02 Sep 2009
Last visit: 22 Apr 2026
Posts: 109,748
Own Kudos:
810,640
 [1]
Given Kudos: 105,821
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 109,748
Kudos: 810,640
 [1]
1
Kudos
Add Kudos
Bookmarks
Bookmark this Post
lawyeroffduty
so going forward for all the language of similar type, we will consider that particular day included in exactly two days period? or it depends upon the language of the question stem. i'm confused here

“Exactly two days after” always means move forward 2 days on the calendar.

If A is on Monday:
One day after Monday is Tuesday.
Two days after Monday is Wednesday.
So B must be on Wednesday.