Last visit was: 22 Apr 2026, 17:01 It is currently 22 Apr 2026, 17:01
Close
GMAT Club Daily Prep
Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GMAT score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Close
Request Expert Reply
Confirm Cancel
User avatar
Siam98
Joined: 09 Sep 2024
Last visit: 24 Jan 2025
Posts: 6
Own Kudos:
5
 [5]
Given Kudos: 100
Posts: 6
Kudos: 5
 [5]
2
Kudos
Add Kudos
3
Bookmarks
Bookmark this Post
User avatar
Spectre26
Joined: 20 May 2023
Last visit: 22 Dec 2025
Posts: 104
Own Kudos:
150
 [3]
Given Kudos: 82
Location: India
Concentration: Strategy, Operations
GMAT Focus 1: 645 Q85 V81 DI79
GPA: 8.5/10
WE:Project Management (Manufacturing)
Products:
GMAT Focus 1: 645 Q85 V81 DI79
Posts: 104
Kudos: 150
 [3]
2
Kudos
Add Kudos
1
Bookmarks
Bookmark this Post
User avatar
HarshavardhanR
Joined: 16 Mar 2023
Last visit: 22 Apr 2026
Posts: 488
Own Kudos:
Given Kudos: 67
Status:Independent GMAT Tutor
Affiliations: Ex - Director, Subject Matter Expertise at e-GMAT
Products:
Expert
Expert reply
Active GMAT Club Expert! Tag them with @ followed by their username for a faster response.
Posts: 488
Kudos: 574
Kudos
Add Kudos
Bookmarks
Bookmark this Post
User avatar
Rahilgaur
Joined: 24 Jun 2024
Last visit: 26 Jan 2026
Posts: 162
Own Kudos:
Given Kudos: 47
GMAT Focus 1: 575 Q81 V82 DI72
Products:
GMAT Focus 1: 575 Q81 V82 DI72
Posts: 162
Kudos: 125
Kudos
Add Kudos
Bookmarks
Bookmark this Post
Siam98
Working 11 hours per day, 24 men and 33 women can complete the construction of a road in 78 days. The working capacity of 3 women equals to that of 1 man. Now the authority decides that the road is to be constructed in 55 days, working 13 hours per day. If there are only 27 women present, how many men will be needed?

A. 33
B. 45
C. 87
D. 99
E. None
Let efficiency of Woman = X, Men= 3x

Total Work = 78days*11 hours/day* (24*3x +33*x){efficiency of man & woman per hour}...........1
Now, work remains same but working days, hours and no. of man woman is different. Let's say Y man required which also what we need to find out..
W= 55 days*13 hours/day (27*x + 3x* y)..........2
Equate 1 & 2
78days*11 hours/day* (24*3x +33*x) = 55 days*13 hours/day (27*x + 3x* y)
126 = 27+3y
y=99/3= 33........Option A